Promenade

AuthorityDepartment of Infrastructure
Date received2019-08-06
OutcomeAll information sent
Outcome date2019-08-09
Case ID917021

Summary

A request was made regarding delays, contract extensions, and expenditure for the Promenade project, to which the Department of Infrastructure disclosed reasons for the delay, clarified the NEC4 contract mechanism, and provided specific financial figures.

Key Facts

  • The project is 9 weeks behind schedule due to unforeseen underground services and additional instructed utility work.
  • The contract is an NEC4 form which does not allow contractors to make formal 'applications' to extend the contract.
  • The Project Manager issues Instructions and Compensation Events to manage additional works and potential completion date revisions.
  • Actual construction expenditure as of the end of July was significantly lower than the forecasted amount.
  • The Department of Infrastructure confirmed all requested information was sent.

Data Disclosed

  • 9 weeks
  • 2019-08-06
  • 2019-08-09
  • 917021
  • £3,778,704
  • £5,371,368
  • end of July

Original Request

What is the reason for the 9 week behind programme. Has the Contractor made an application to extend the Contract What is the expendture to date and its comparison to the expendture flow in the contract

Data Tables (1)

Full Response Text

0###

Department of Infrastructure Sea Terminal Building, Douglas, IM1 2RF

Contact: FOI Response Team Telephone: (01624) 686785 Email: DPO-DOI@gov.im

Our ref: 917021 9 August 2019

Dear ###

We write further to your request which was received on 6 August 2019 and which states (numbered for ease of reference): "1. What is the reason for the 9 week behind programme.
2. Has the Contractor made an application to extend the Contract 3. What is the expendture to date and its comparison to the expendture flow in the contract"

1. The Contractor is behind on the Accepted Programme for several reasons: • Unforeseen underground services encountered during excavation work have resulted in the need for the isolated redesign of proposals, some utility service diversions which result in delays to construction work and subsequently the construction programme • Additional utility service work has been instructed as the need arises during construction. This additional work has impacted on construction and caused delay to the programme. 2. • The works are being carried out under a NEC4 Contract • There is no mechanism within this form of Contract for the Contractor to make an ‘application’ to extend the Contract • The Project Manager issues Instructions and Compensation Events to cover additional works • The Contractor is currently re-programming the works to take account of the additional instructed works which may result in a revised Completion Date for the whole of the work. 3. • Actual construction expenditure to date (net after retention) as of end of July is £3,778,704 • Forecast construction expenditure (net after retention) up to end of July was £5,371,368

Please quote the reference number 917021 in any future communications. You have the right to request a review

If you are unhappy with this response to your freedom of information request, you may ask us to carry out an internal review of the response, by completing a complaint form and submitting it electronically or by delivery/post.

An electronic version of our complaint form can be found by going to our website at https://services.gov.im/freedom-of-information/Review. If you would like a paper version of our complaint form to be sent to you by post, please contact us and we will be happy to arrange for this. Your review request should explain why you are dissatisfied with this response, and should be made as soon as practicable. We will respond as soon as the review has been concluded. If you are not satisfied with the result of the review, you then have the right to appeal to the Information Commissioner for a decision on; 1. Whether we have responded to your request for information in accordance with Part 2 of the Freedom of Information Act 2015; or 2. Whether we are justified in refusing to give you the information requested.
In response to an application for review, the Information Commissioner may, at any time, attempt to resolve a matter by negotiation, conciliation, mediation or another form of alternative dispute resolution and will have regard to any outcome of this in making any subsequent decision. More detailed information on your right to a review can be found on the Information Commissioner’s website at www.inforights.im. Should you have any queries concerning this letter, please do not hesitate to contact us. Further information about freedom of information requests can be found at www.gov.im/foi. I will now close your request as of this date. Yours sincerely FOI Response Team