Energy From Waste Plant Contract

AuthorityDepartment of Infrastructure
Date received2018-07-27
OutcomeRequest lapsed - requested information not provided
Outcome date2018-07-31
Case ID542434

Summary

A request was made for the full contract details of the Isle of Man's Energy From Waste Plant, citing a previous Information Commissioner decision on commercial information disclosure. The request lapsed without the information being provided, though the response included a 403-page conformed copy of the Project Agreement dated July 2016.

Key Facts

  • The request for the full contract details lapsed on 2018-07-31 without the information being formally provided.
  • The original Project Agreement for the Integrated Incinerator was signed on 27 October 2000.
  • The contractor, originally United Waste (Isle of Man) Limited, is now known as SUEZ RECYCLING AND RECOVERY ISLE OF MAN LTD.
  • The provided document is a conformed copy reflecting variations up to July 2016, incorporating Deeds of Variation from 2003 and 2014.
  • The Department of Infrastructure noted that the accuracy of the conformed copy is not warranted and it is for reference only.

Data Disclosed

  • 2018-07-31
  • 2018-07-27
  • 403
  • 2
  • 27 October 2000
  • 5 February 2002
  • 2 April 2016
  • 1 July 2016
  • 1 February 2003
  • 1 October 2014
  • 16th March 2018

Original Request

Please provide the following... 1. The full detail of the current contract with the private contractor appointed to operate the incinerator (Energy From Waste Plant). I believe the thrust of the recent decision notice issued by the Information Commissioner on the 16th March 2018 with regards the disclosure of commercial information is applicable in this case, for exactly the same reasons as listed in that notice (https://www.inforights.im/media/1499/2017_0007_department­ of­ infrastructure_16march2018.pdf). I am interested in the obligations and associated cost implications to and of all parties. I imagine this makes up the majority of the contract, so without knowing how it is structured it is difficult to say how to narrow the request. Ideally I would like the full contract please. I am happy to receive a pdf copy or to pay for a printed copy. I don't mind how large it is

Data Tables (25)

Total Value
Stage Payment No. Local Currency (£) Nominated Currency (ECU) NDPI (In Euros) NDPI Escalation (in £) DPI (in Euros) DPI Escalation (in £) Value of Directly Procured Items in Nominated Currency (ECU) Conditions for Release of Payment Planned Stage Completion Date
1.31 2.(a)32 329,484* 555,887.50** 135,757 71,732 102,377 38,352 1. PSO Application submitted to the Department in accordance with Clauses 4.2.1, 4.2.2 and 4.2.3 of the Project Agreement and 1.8 of the Department’s Requirements 1. Completion of the 4 7
Total Value
Stage Payment No. Local Currency (£) ** Nominated Currency (ECU) NDPI (In Euros) NDPI Escalation (in £) DPI (in Euros) DPI Escalation (in £) Value of Directly Procured Items in Nominated Currency (ECU) Conditions for Release of Payment public enquiry as part of the PSO Application 2. Completion of the Feasibility Study. Planned Stage Completion Date
2aa [New]33 3.
2ab [New]34 4.
2.(b)35 555,887.50 71,732 38,352 1. Design Completion achieved 2. Health and Safety Plan submitted.
3.36 884,675 987,846 987,846 1. SHEP 3 (HAZOP review) completed 10
Total Value
Stage Payment No. Local Currency (£) Nominated Currency (ECU) NDPI (In Euros) NDPI Escalation (in £) DPI (in Euros) DPI Escalation (in £) Value of Directly Procured Items in Nominated Currency (ECU) Conditions for Release of Payment Planned Stage Completion Date
2. Final release of orders for: • Water treatment plant • Turbine generator set • Air condenser • Bag house filter • Secondary Incinerator stream 3. Civil works ordered 4. Orders placed for: • Shredder • Compactor/baler • Boiler feed water preheater • Boiler feed water pumps
Total Value
Stage Payment No. Local Currency (£) Nominated Currency (ECU) NDPI (In Euros) NDPI Escalation (in £) DPI (in Euros) DPI Escalation (in £) Value of Directly Procured Items in Nominated Currency (ECU) Conditions for Release of Payment Planned Stage Completion Date
5. Site established by the civil contractor carrying out initial mobilisation, placing site cabins on site and establishing a permanent site presence 6. Enquiry for Structural steelwork issued
4.37 395,105 888,949 661,476 1. PFD’s and PID’s issued at AFD (Approved for design) status 2. Plant layout drawings issued at AFD status 12
Total Value
Stage Payment No. Local Currency (£) Nominated Currency (ECU) NDPI (In Euros) NDPI Escalation (in £) DPI (in Euros) DPI Escalation (in £) Value of Directly Procured Items in Nominated Currency (ECU) Conditions for Release of Payment Planned Stage Completion Date
3. Control description and philosophy issued at AFD status 4. Order placed for structural steelworks 5. Enquiry issued for MCC switchgear 6. Detail design of Primary Incinerator issued at AFD status.
5.38 1,188,839 4,437,302 2,886,000 1. Orders placed for: • Plant control system • MCC switchgear 2. Excavation of primary waste bunker complete 15
Total Value
Stage Payment No. Local Currency (£) Nominated Currency (ECU) NDPI (In Euros) NDPI Escalation (in £) DPI (in Euros) DPI Escalation (in £) Value of Directly Procured Items in Nominated Currency (ECU) Conditions for Release of Payment Planned Stage Completion Date
3. Primary Incinerator and turbine generator foundations complete 4. Structural erection contractor mobilised 5. Construction tower crane erected 6. Structural steelworks erection commenced
6.39 1,305,780 8,820,194 4,584,896 154,851 5,249,862 167,704 1. SHEP 4 (HAZOP prior to construction) complete (*****) 2. First shipment made of Primary Incinerator to Site. 3. PID’s issued at AFC 18/12/02
Total Value
Stage Payment No. Local Currency (£) Nominated Currency (ECU) NDPI (In Euros) NDPI Escalation (in £) DPI (in Euros) DPI Escalation (in £) Value of Directly Procured Items in Nominated Currency (ECU) Conditions for Release of Payment Planned Stage Completion Date
(Approved for construction) status. Except Seghers 4. Lime silo delivered to Site 5. Gas Plant C.I.S Floor (6m Lev.) constructed. 6. Treated Water, Ammonia Storage & Low Sulphur Oil Tanks Installed. Bottom ash conveyors, installation commenced. 7. Piping general arrangements issued at AFC status 8. Structural steelworks
Total Value
Stage Payment No. Local Currency (£) Nominated Currency (ECU) NDPI (In Euros) NDPI Escalation (in £) DPI (in Euros) DPI Escalation (in £) Value of Directly Procured Items in Nominated Currency (ECU) Conditions for Release of Payment Planned Stage Completion Date
40% (by weight, excluding cladding) erected. 9.
6a.40 832,779 1,625,584 54,903 2,142,531 72,362 2,142,531 1. Primary Incinerator installation commenced 2. Secondary incinerator installation commenced 3. Air Condenser ready for shipment. 4. Turbine and Turbine Hall Crane delivered to site. 5. Pipework installation commenced. 20/01/03
Total Value
Stage Payment No. Local Currency (£) Nominated Currency (ECU) NDPI (In Euros) NDPI Escalation (in £) DPI (in Euros) DPI Escalation (in £) Value of Directly Procured Items in Nominated Currency (ECU) Conditions for Release of Payment Planned Stage Completion Date
6. Structural Steelworks Fabrication complete. 7. Pri. & Sec. Air Preheaters delivered to site.
6b.41 832,779 1,625,584 54,903 2,142,531 72,362 1. Secondary Waste Heat Boiler Installation Commenced 2. Underground Drains, and Mains completed 3. Seghers PID's issued at AFC (Approved for Construction) status. 20/02/03
7.42 11,574,189 1,625,586 54,903 2,426,937 72,362 6697,435 4. Draft Procedures for 20/03/03
Total Value
Stage Payment No. Local Currency (£) Nominated Currency (ECU) NDPI (In Euros) NDPI Escalation (in £) DPI (in Euros) DPI Escalation (in £) Value of Directly Procured Items in Nominated Currency (ECU) Conditions for Release of Payment Planned Stage Completion Date
903,044 Commissioning the Facility submitted Steam turbine, Gearbox, Generator and ancillaries mechanically erected 5. MCC switchgear delivered and landed 6. Air Cooled Condenser installation commenced. 7. Spray drier absorbers mechanically erected. 8. Structural steelworks
Total Value
Stage Payment No. Local Currency (£) Nominated Currency (ECU) NDPI (In Euros) NDPI Escalation (in £) DPI (in Euros) DPI Escalation (in £) Value of Directly Procured Items in Nominated Currency (ECU) Conditions for Release of Payment Planned Stage Completion Date
80% (by weight excluding cladding) erected.
7a.43 762,195 1,081,167 36,515 2,028,282 68,503 1. All Stack modules delivered to site. 2. Excavate Primary Waste Bunker Complete. 3. Building Cladding commenced 22/04/03
8.44 1,607,986 6,398,794 1,369,430 46,251 1,242,834 35,572 4,236,460, 1. Civils at and below ground level within the Building Footprint complete (This includes building and 20/05/03
Total Value
Stage Payment No. Local Currency (£) Nominated Currency (ECU) NDPI (In Euros) NDPI Escalation (in £) DPI (in Euros) DPI Escalation (in £) Value of Directly Procured Items in Nominated Currency (ECU) Conditions for Release of Payment Planned Stage Completion Date
equipment foundations, bunkers and ground floor slabs but excludes concrete works at higher levels, internal partition walls, roads and pavings outside the building footprint). 2. Bag house filter mechanically erected. Secondary Incinerator mechanically erected. 3. Pipework 50% mechanically erected (by meters). 4. Building cladding
Total Value
Stage Payment No. Local Currency (£) Nominated Currency (ECU) NDPI (In Euros) NDPI Escalation (in £) DPI (in Euros) DPI Escalation (in £) Value of Directly Procured Items in Nominated Currency (ECU) Conditions for Release of Payment Planned Stage Completion Date
delivered on Site (complete).
9.45 186,232 1,157,875 288,264 9,736 585,085 843 1. Stack installation complete 2. First systems ready for construction handover to commissioning as defined by Safety Transfer certificate issued for: • 13,3 kV incoming electrical system • Towns water incoming supply • Instrument air 18/07/03
Total Value
Stage Payment No. Local Currency (£) Nominated Currency (ECU) NDPI (In Euros) NDPI Escalation (in £) DPI (in Euros) DPI Escalation (in £) Value of Directly Procured Items in Nominated Currency (ECU) Conditions for Release of Payment Planned Stage Completion Date
compressors • Primary Incinerator Slag and Ash Handling Systems mechanically installed.
9a.46 310,507 72,365 2,444 642,831 21,711 1. Civil Construction (excluding Building Finished and Punch Listing) complete. 2. Primary Incinerator and Boiler delivered (complete). 3. Services setting to work commenced. Water & Air. 20/08/03
9b.47 310,507 72,365 2,444 642,831 21,711 1. Primary Incinerator 19/09/03
Total Value
Stage Payment No. Local Currency (£) Nominated Currency (ECU) NDPI (In Euros) NDPI Escalation (in £) DPI (in Euros) DPI Escalation (in £) Value of Directly Procured Items in Nominated Currency (ECU) Conditions for Release of Payment Planned Stage Completion Date
mechanically erected. 2. Commence Gas Cleaning cold commissioning. 3. Services commissioning completed. 4.
10.48 522,679 2,222,503 72,366 2,444 723,896 21,711 1. Grid Connection Tests complete (for electricity import). 2. MCC checked. 3. Refractory and Inconel in primary Incinerator and Boiler installed. 4. Primary Boiler 20/10/03
Total Value
Stage Payment No. Local Currency (£) Nominated Currency (ECU) NDPI (In Euros) NDPI Escalation (in £) DPI (in Euros) DPI Escalation (in £) Value of Directly Procured Items in Nominated Currency (ECU) Conditions for Release of Payment Planned Stage Completion Date
pressure test completed. 5.
10a.49 371,412 66,384 2,242 597,613 20,184 1. Safety Systems test achieved. 2. Primary Incinerator Refractory dried out. 3. Steam Blowing complete. 4. Plant ready for Waste Introduction (Start of Trial Period). 20/01/04
11.50 2,488,301 147,837 4,993 1,695,119 44,949 1. Reliability test 12/04/04
Total Value
Stage Payment No. Local Currency (£) Nominated Currency (ECU) NDPI (In Euros) NDPI Escalation (in £) DPI (in Euros) DPI Escalation (in £) Value of Directly Procured Items in Nominated Currency (ECU) Conditions for Release of Payment Planned Stage Completion Date
1,356,826 (proving trials and functional test) completed. 2. Tests demonstrating Minimum Performance Standards achieved 3. Take Over of the Works 4. Taking Over Certificate issued
SUM51 13,212,604 [+25,000] 6,593,318 12,631,828 426,629 20,120,352 619974 4,714,403
Stage Payment Number Adjustment to Stage Payment totals* Payment Date
1 0 June 2001
2a 0 August 2001
2aa [New] 185,432 September 2001
2ab [New] 185,433** End of Remedial Works
2b 203,282 December 2001
3 -122,108*** March 2002
4 21,947 May 2002
5 -71,409 August 2002
653 -51,244 November 2002
754 0 February 2003
8 0 April 2003
9 0 June 2003
10 -10,989 September 2003
11 -10,989 December 2003
Circumstance Abatement Cure Period
1. a) The Facility is not Available.67 b) The Primary Waste Stream only is not Available.68 c) The Secondary Waste Stream only is not Available.69 £10,000 (ten thousand pounds) per day, the Availability Fee, calculated at a daily rate, for each day, or part of a day, during which the Facility is not Available. £9,000 (nine thousand pounds) per day and the Availability Fee, calculated at a daily rate, for each day, or part of a day, during which the Primary Waste Stream only is not Available. £1,000 (one thousand pounds) per day and the Availability Fee, calculated at a daily rate, for each day, or part of a day, during which the Secondary Waste Stream only is not Available. 24 hours from receipt of a written notice of breach served on ProjectCo by or on behalf of the Department. 24 hours from receipt of a written notice of breach served on ProjectCo by or on behalf of the Department. 24 hours from receipt of a written notice of breach served on ProjectCo by or on behalf of the Department.
2. There is an Emergency and there is no encapsulation equipment at the Facility to enable the baling of waste. £500 per day or part of a day so long as the failure continues. -
3. For each occasion on which ProjectCo is served with a formal notice of breach of the Regulator’s Licence £5,000 per incident. -
4. For each occasion on which the relevant authority notifies ProjectCo in writing of a breach of any of the conditions set out in the Planning Scheme Order. £1,000 per day, or part of a day, per waste stream until the day on which full compliance is achieved. -
5. For each occasion (so that there may be more than one £5,000 per occasion. 24 hours from receipt of a written notice of breach
Circumstance Abatement Cure Period
occasion in a day) on which any Residues delivered to the Department for disposal fail to comply with applicable specifications set out in the Department’s Requirements. served on ProjectCo by or on behalf of the Department.
6. Failure to produce the guaranteed annual electricity export in any Operating Year with due consideration to the Allowance. Reference is made to Annex 1. 90% of the product of (the difference between the actual amount of electricity exported and sold to the MEA at the unit rate as set out in Schedule 6, Clause 6.1 and the guaranteed minimum annual electricity export) multiplied with the MEA tariff applying at that time.
7. Failure to provide complete monthly, annual, quinquennial and (in any Emergency) daily reports at the times required by the Project Agreement. £500 per day, or part of a day, until the day on which all such reports shall have been provided. 24 hours from receipt of a written notice of breach served on ProjectCo by or on behalf of the Department.
8. Failure to maintain the Site in the state and condition (including internal and external appearance) specified in the Department’s Requirements. £500 per day, or part of a day, until the end of the day on which full compliance is achieved. 72 hours from receipt of a written notice of breach served on ProjectCo by or on behalf of the Department.
9. All weighbridges are unavailable for use. £300 per failure plus £500 per day, or part of a day, for so long as the failure continues. 24 hours from receipt of a written notice of breach served on ProjectCo by or on behalf of the Department.
10. For each occasion on which the vehicle turnaround time for delivery of Primary Waste to the Facility exceeds fifteen minutes, where such delivery has been reasonably uniform throughout the day and before and after the relevant vehicle turnaround. £300 per occasion. -
11. The failure of the internet home page described in the Department’s Requirements £1,000 per failure plus £500 per day, or part of a day, for so long as the failure to continues. 24 hours from receipt of a written notice of breach served on ProjectCo by or
Circumstance Abatement Cure Period
to provide Internet users with the information specified in the Department’s Requirements where such failure is wholly attributable to persons or property for which ProjectCo is responsible. on behalf of the Department.
VO D & B Contract Price Provisional Sums Availability Fee Operating Fee
2 & 3 + £27,195 (effective 14.05.2005) + £25,000 / /
5 / / / /
6 / +£211,872 / /
7 / / / /
8 / / / /
10 / / / /
11 / / / /
12 + £212,137351 / + £35,875/annum + £0.15/tonne
13 / / / /
15 - £54,729 / / /
16 / / / /
17 + £33,297 / + £14,391 /
DofV1 The pricing changes made by DofV1 are incorporated into the body of Schedule 1 in the Conformed Copy. In accordance with Clause 9.4 of DofV 2, the Parties record their agreement to the Availability and Operating Fee amounts set out in Appendix 8 to this PA (Appendix 17 of DofV2) which are payable with effect from 0001hrs on August 1st, 2010.
Abatement Number 2004/5 £ 2005/6 £ 2006/7 £ 2007/8 £ 2008/9 £ 2009/10 £ 2010/11 £ 2011/12
Index % 8.3373 3.2837 3.8006 5.0713 4.0762 4.4824 0.2233 4.5966
2 541.69 559.47 580.74 610.19 635.06 663.53 665.01 695.58
3 5416.87 5594.74 5807.37 6101.88 6350.61 6635.27 6650.08 6955.76
4 1083.37 1118.95 1161.47 1220.38 1270.12 1327.05 1330.02 1391.15
5 5416.87 5594.74 5807.37 6101.88 6350.61 6635.27 6650.08 6955.76
6 (unit rate only starts from 0.285 p/kWh) see abatement. 0.309 0.319 0.331 0.348 0.362 0.378 0.379 0.396
7 541.69 559.47 580.74 610.19 635.06 663.53 665.01 695.58
8 541.69 559.47 580.74 610.19 635.06 663.53 665.01 695.58
9 325.01+541.6 9 335.68+559.47 348.44+580.74 366.11+610.19 381.04+635.06 398.12+663.53 399.00+665.01 417.35+695.58
Abatement Number 2004/5 £ 2005/6 £ 2006/7 £ 2007/8 £ 2008/9 £ 2009/10 £ 2010/11 £ 2011/12
10 325.01 335.68 348.44 366.11 381.04 398.12 399.00 417.35
11 1083.37+541. 69 1118.95+559.4 7 1161.47+580.7 4 1220.38+610.1 9 1270.12+635.0 6 1327.05+663.5 3 1330.02+665.0 1 1391.15+695.5 8
Consumables Usage agreed in PR 2009 Included in Operating Gate Fee element 2.2 of Pricing Schedule Unit* Usage Lime kg/tonne 11.63 Carbon kg/tonne 1.15 Ammonia kg/tonne 2.67 QR/PR Tracking Sheet 2009/2010 Water Line 1 cu. m/tonne 0.23 Water Line 2 cu. m/tonne 1.00 August 2009 to July 2010 Fuel lt/tonne 2.00 *tonne = tonne of waste incinerated Unit Aug-09 Sep-09 Oct-09 Nov-09 Dec-09 Jan-10 Feb-10 Mar-10 Apr-10 May-10 Jun-10 Jul-10 Year 1
Variance (monthly) £ 0 Variance (YTD) £ Variance (cummulative) £ 0 0 0 0 0 0 0 0 0 0 0 0
* Cumulative Figure includes previous year's variance Actual tonnage into EfW Aug-09 Sep-09 Oct-09 Nov-09 Dec-09 Jan-10 Feb-10 Mar-10 Apr-10 May-10 Jun-10 Jul-10 Year 1
PWI - Tonnage SWI - Tonnage 0 0
Total Tonnage 0 0 0 0 0 0 0 0 0 0 0 0 0
Annual indexation 000%
CONSUMABLES
Ref. Operating Gate Fee 2.2 Unit Aug-09 Sep-09 Oct-09 Nov-09 Dec-09 Jan-10 Feb-10 Mar-10 Apr-10 May-10 Jun-10 Jul-10
Lime (usage) tonne 000 000 000 000 000 000 000 000 000 000 000 000 Price (gate fee) £/tonne
Price (actual) £/tonne
Variance £ 0 0 0 0 0 0 0 0 0 0 0 0 0
Carbon (usage) tonne 000 000 000 000 000 000 000 000 000 000 000 000 Price (gate fee) £/tonne
Price (actual) £/tonne
Variance £ 0 0 0 0 0 0 0 0 0 0 0 0 0
Ammonia (usage) tonne 000 000 000 000 000 000 000 000 000 000 000 000 Price (gate fee) £/tonne
Price (actual) £/tonne
Variance £ 0 0 0 0 0 0 0 0 0 0 0 0 0
Water (usage) cu m 000 000 000 000 000 000 000 000 000 000 000 000 Price (gate fee) £/cu m
Price (actual) £/cu m
Variance £ 0 0 0 0 0 0 0 0 0 0 0 0 0
Fuel (usage) lt 000 000 000 000 000 000 000 000 000 000 000 000 Price (gate fee) £/lt
Price (actual) £/lt
Variance £ 0 0 0 0 0 0 0 0 0 0 0 0 0

Full Response Text

Department of Infrastructure, Isle of Man Government

DATED 27 OCTOBER 2000

DEPARTMENT OF INFRASTRUCTURE (1)

(following a transfer of functions from the DEPARTMENT OF LOCAL GOVERNMENT AND THE ENVIRONMENT)

  • and

SUEZ RECYCLING AND RECOVERY ISLE OF MAN LTD (2)

(ORIGINALLY, UNITED WASTE (ISLE OF MAN) LIMITED and formerly SITA WASTE (ISLE OF MAN) LIMITED)

CONFORMED COPY SHOWING DOCUMENT STATUS AS AT JULY 2016

PROJECT AGREEMENT

INTEGRATED INCINERATOR (ENERGY FROM WASTE)
FACILITY

Department of Infrastructure, Isle of Man Government

INTRODUCTORY NOTE TO THE 2016 CONFORMED COPY

The original Project Agreement (the "PA") was signed on 27 October, 2000. Since then: • the functions of the Department of Local Government and the Environment have transferred to the Department of Infrastructure (the Department)
• ProjectCo changed its name from United Waste (Isle of Man) Limited to SITA Waste (Isle of Man) Limited on 5 February 2002 and then changed its name to SUEZ RECYCLING AND RECOVERY ISLE OF MAN LTD on 2 April 2016 • there have been several changes to the text of the PA as a result of variations and service changes. This conformed copy shows the Variations and Services Changes which are current at 1 July 2016.
These Variations have been embodied in the variation orders ("VO") of two Deeds of Variation, namely Deed of Variation 1 ("DofV1"), dated 1 February 2003 and Deed of Variation 2 ("DofV2"), dated 1 October 2014.
The effective dates for the changes to the PA which were recorded in DofV2 are given in DofV 2 clause 8 and the Appendices to DofV 2. Where a change has been made, a footnote to the principal definition and/or to the text affected shows which variation order and/or appendix number of DofV1 or DofV2 gave rise to the change. While care has been taken in producing this document to capture all available information relating to changes to the original Project Agreement, the accuracy of this conformed copy is not warranted.
This document has been compiled for reference and administration purposes only and is not a substitute for the original documentation which records the agreement between the counterparties.
Department of Infrastructure, Isle of Man Government

1 INDEX

1 DEFINITIONS ........................................................................................................................... 7 2 INTERPRETATION ................................................................................................................ 31 3 CONDITIONS PRECEDENT AND EFFECTIVE DATE .......................................................... 34 4 APPROVALS .......................................................................................................................... 35 5 PROJECTCO’S APPOINTMENT ........................................................................................... 38 6 UNDERTAKINGS OF BOTH PARTIES.................................................................................. 38 7 PAYMENT .............................................................................................................................. 43 8 VARIATIONS AND SERVICES CHANGES ........................................................................... 43 9 WARRANTIES/BONDS/GUARANTEES ................................................................................ 44 10 PROPERTY ISSUES ............................................................................................................. 45 11 EMPLOYMENT RESOURCES AND TRAINING .................................................................... 47 12 RISK AND RESPONSIBILITY ................................................................................................ 48 13 PRICE REVIEW ...................................................................................................................... 56 14 INCOME GENERATION ........................................................................................................ 58 15 FORCE MAJEURE ................................................................................................................. 58 16 RELIEF EVENTS .................................................................................................................... 60 17 INSURANCE ........................................................................................................................... 61 18 DELEGATION ......................................................................................................................... 70 19 DISPUTE RESOLUTION ........................................................................................................ 72 20 ELECTRICITY AGREEMENT ................................................................................................ 75 21 OPEN BOOK ACCOUNTING, ACCESS AND AUDIT ........................................................... 76 22 TERMINATION ....................................................................................................................... 80 23 ASSIGNMENT/SUBCONTRACTING ..................................................................................... 90 24 SEVERANCE .......................................................................................................................... 91 25 GOVERNING LAW ................................................................................................................. 92 26 ENTIRE AGREEMENT ........................................................................................................... 92 27 WAIVER .................................................................................................................................. 93 28 NOTICES ................................................................................................................................ 93 29 CONFIDENTIALITY AND PROPRIETARY INFORMATION .................................................. 94 30 AGENCY ................................................................................................................................. 95 31 NON–PARTNERSHIP ............................................................................................................ 95 32 PASSING OFF ........................................................................................................................ 95 33 INTELLECTUAL PROPERTY RIGHTS .................................................................................. 95 34 PUBLIC RELATIONS ............................................................................................................. 97 35 HANDBACK ............................................................................................................................ 97 36 COST OF FUEL USED IN SECONDARY WASTE STREAM ................................................ 97 SCHEDULE 1 .................................................................................................................................. 118 SCHEDULE OF PAYMENTS .............................................................................................................. 118 1 PART 1 : D & B SCHEDULE OF PAYMENTS ..................................................................... 118 2 PART 2 : O & M SCHEDULE OF PAYMENTS .................................................................... 145 3 PART 3: COMPENSATION SCHEDULE OF PAYMENTS .................................................. 154 SCHEDULE 2 .................................................................................................................................. 163 D & B OBLIGATIONS ......................................................................................................................... 163 1 GENERAL ............................................................................................................................. 163 2 THE DEPARTMENT ............................................................................................................. 163 3 PROJECTCO ........................................................................................................................ 164 4 DESIGN ................................................................................................................................ 173 5 STAFF AND LABOUR .......................................................................................................... 176 6 PLANT, MATERIALS AND WORKMANSHIP ...................................................................... 178 7 COMMENCEMENT, DELAYS AND SUSPENSION ............................................................ 180 8 TESTS ON TAKE OVER ...................................................................................................... 186 9 DEPARTMENT'S TAKING OVER ........................................................................................ 190 10 TESTS AFTER TAKE OVER ................................................................................................ 191 11 DEFECTS LIABILITY............................................................................................................ 193 12 D & B CONTRACT PRICE AND PAYMENT ........................................................................ 195 13 VARIATIONS ........................................................................................................................ 200 14 DEFAULT OF DEPARTMENT ............................................................................................. 203 Department of Infrastructure, Isle of Man Government

2 Annex 1 : D&B Subcontractors ........................................................................................................... 205 SCHEDULE 3 .................................................................................................................................. 206 O & M OBLIGATIONS ......................................................................................................................... 206 1 COMMENCEMENT OF THE SERVICE ............................................................................... 206 2 OBLIGATIONS OF PROJECTCO ........................................................................................ 206 3 CHANGE IN LAW ................................................................................................................. 219 4 SERVICES CHANGES ......................................................................................................... 223 5 WASTE DELIVERY .............................................................................................................. 225 6 RESIDUE DISPOSAL OBLIGATIONS ................................................................................. 225 SCHEDULE 4 ...................................................................................................................................... 227 Part 1 : The Site .................................................................................................................................. 227 Part 2 : The Lease ............................................................................................................................... 228 1 DEFINITIONS ....................................................................................................................... 229 2 INTERPRETATION .............................................................................................................. 231 3 DEMISE AND RENT............................................................................................................. 232 4 TENANT'S COVENANTS ..................................................................................................... 232 5 LANDLORD'S COVENANT .................................................................................................. 237 6 PROVISOS AGREEMENTS AND DECLARATIONS ........................................................... 237 SCHEDULE 5 .................................................................................................................................. 246 INSURANCES ..................................................................................................................................... 246 1 CONSTRUCTION “ALL RISKS” ........................................................................................... 246 2 PUBLIC LIABILITY INSURANCE ......................................................................................... 248 3 PROFESSIONAL INDEMNITY INSURANCE....................................................................... 249 4 MARINE CARGO OPEN COVER ........................................................................................ 250 5 STATUTORY POLICIES ...................................................................................................... 251 6 PROPERTY “ALL RISKS ..................................................................................................... 251 7 BUSINESS INTERRUPTION INSURANCE ......................................................................... 252 5. NOTIFICATION DETAILS .................................................................................................... 255 7. LIMITATION OF LIABILITY .................................................................................................. 256 8. GENERAL ............................................................................................................................. 256 SCHEDULE 6 .................................................................................................................................. 258 electricity agreement(s) ....................................................................................................................... 258 1 DEFINITIONS ....................................................................................................................... 259 2 TERM .................................................................................................................................... 261 3 SUPPLY BY THE AUTHORITY ............................................................................................ 261 4 EXPORT SUPPLY BY THE PROJECTCO TO THE AUTHORITY ...................................... 262 5 ASSIGNMENT ...................................................................................................................... 266 6 RESERVATIONS .................................................................................................................. 267 7 FORCE MAJEURE ............................................................................................................... 26