Major projects board

AuthorityTreasury
Date received2025-06-19
OutcomeSome information sent but part exempt
Outcome date2025-07-24
Case ID4739249

Summary

The request sought agendas, minutes, and project documents regarding onshore renewables from the Major Projects Board, resulting in partial disclosure where specific meeting details were released but other items were withheld under exemption s.25.

Key Facts

  • A Major Projects Board meeting was held on Thursday 27th June 2024 via MS Teams.
  • Barry O'Driscoll served as the Chair of the meeting.
  • The agenda included a discussion on MUA Onshore Wind which was marked as out of scope.
  • Turbine lead times are estimated at 14 months based on the Prior Information Notice process.
  • The proposed contracting structure involves at least 2 or 3 key contractors rather than a single EPC contractor.

Data Disclosed

  • 27th June 2024
  • 14:00 – 15:30
  • 12 months
  • 3 months
  • 6 months
  • 33 months
  • 1 April 2024
  • December 2026
  • 14 months
  • January 2023
  • 06 June 2024
  • 04 June 2024
  • s.25

Exemptions Cited

  • s.25

Original Request

Copies of all agendas and minutes of the Major Projects Board meetings since inception concerning onshore renewables . All business cases, reports, risk assessments or project evaluation documents submitted to or discussed by the Major Projects Board in relation to onshore renewables

Data Tables (12)

Funding Funding approval is required by March 2024 if the project is to be delivered by 2026. There do not appear to be alternative routes which would enable the project to be delivered by 2026 if funding approval is not achieved. There is no other route for funding of the project. Tynwald briefing will be completed prior to March Tynwald debate to help members understand need to tender before planning permission can be sought.
Resourcing Resource from Business as Usual will be required to support the project working groups, both within Manx Utilities and Isle of Man Government. The release of key personnel from their duties is not within control of the project team or Programme Board. Project Manager will work with the Programme Manager to engage with Business Change Managers at the Programme Board level as well as Finance Director and HR Manager to agree release of staff from business-as-usual functions and ensure this release is limited to a reasonable time-frame each month. A full resource plan is also being developed to ensure dedicated personnel available within the project team to support all working groups. Tight control and scheduling of meetings to ensure there is no scope creep, making use of Business Change Engineers’ time. Close collaboration within working groups and effective horizon scanning for potential issues to make efficient use of subject matter expert resources.
Health and Safety The Health and Safety at Work Act requires Safe System of Work for future operation and maintenance. Public/contractor/MU staff access to wind site. Two Senior Authorised Persons on Project Team. Develop enduring Safe System of Work (SSW) utilising Onshore wind safety council, Safety-On to develop safety rules specific for wind generation. Seek advice from Health and Safety experts in MU and IOMG (and UK if required) develop guidelines for site visits and carry out site inductions.
Political and public support Policy decisions not made in a timely manner preventing projects from progressing. Resistance to projects or sites selected for project by the public or other stakeholders, which impacts the planning stage. Stakeholders are briefed in a timely manner ensuring the need for decisions is understood by policy makers in advance of each project commencing A Communications and Stakeholder Engagement plan is being developed to support the Transition Programme and the existing MU Public Relations & Media Communications Procedure. An FAQ page has been developed to anticipate popular enquiries and assist Communications team. Public engagement early in the process by Manx Utilities can help improve public perception and reduce the risk of objections.
s.3
0s.3
s0.3
Coole, Joanne (Treasury)
18 June 2024 11:28
Sidebottom, Andrew (Treasury)
FW: 240523 MU Onshore Wind Exemption Request.docx
Turbine Procurement - CPN Exemption Note.pdf; MU2407 - Energy Transition - Onshore Wind.docx; 2024-06-04 Wind procurement risks v4.docx; 240606 TP Manx Utilities Exemption Request re Onshore Wind Farm final.docx
Section Exemption considered Required? Comment
Section 5 – Capital Schemes – The Scope
5.1 We believe criteria met, MUA to consider Scope is defined, apart from some O&M requirements, which are set out as minimum requirements but requiring the tenderer to provide more detailed proposals as part of the tender return.
5.2 Criteria largely met, MUA to consider A few areas (for example, final layout, site access) are based on assumptions due to need to finalise some surveys and complete detailed design, or will be dependent upon tender returns (i.e. no. of turbines & therefore layout).
5.3 Criteria largely met, MUA to consider Some elements of requirements (for example, final details of grid connection) may still require finalisation, but those elements are more relevant to the BOP contract.
5.4 Criteria met
5.5 Criteria met
5.6 We believe criteria met, MUA to consider We consider this requirement is likely addressed, in conjunction with LOD workstreams, but MUA to consider.
5.7 Criteria met
5.8 Criteria largely met, MUA to consider, as possibly requires exemption Considered that there are unlikely to be wholesale changes to the project as a result of the extensive work completed to date, and that the procurement of a Turbine Contractor at this stage will actually contribute to lessening the likelihood of changes later in the project.
5.9 Criteria met
5.10 MUA to confirm has been completed This is considered to largely sit with MUA
5.11 We believe criteria met, MUA to consider Various elements of quality and cost have been determined at feasibility and minimum requirements set in the WI, but some elements will need to be clarified as part of the tender returns and therefore compliance with 5.11 will be partially delivered by MUA setting appropriate Quality questions in the tender.
5.12 Consider N/A for this project
5.13 Consider N/A for this project
5.14 Consider N/A for this project
5.15 Consider N/A for this project
5.16 Consider N/A for this project
5.17 Consider N/A for this project
Section 8.4 – Stage I2 Technical Design
8.4.1 We believe criteria met, MUA to confirm
8.4.2 Exemption required? Scheme has not been fully designed at this stage.
8.4.3 Exemption required? Turbine Contractor will not be a domestic supplier (assuming that the BOP is to be considered the ‘main contractor’ for this project).
8.4.4 Exemption required? Linked to the above.
8.4.5 MUA to confirm the criteria has been met
8.4.6 Exemption required? As detailed design not completed yet, and we are essentially at the end of Stage I1 from a design perspective, it is not possible to identify or highlight any changes in design as compared to I1.
8.4.7 MUA to confirm the criteria has been met
8.4.8 Exemption required Final drawings and specification not complete. The Turbine Contractor will be required to feed into final design and detail final equipment specifications. However, designs and minimum specifications in the WI are considered sufficient for the needs of this procurement.
8.4.9 Exemption required Key M&E elements will form part of the subsequent BOP Contract, with some elements specific to the turbines to be determined and designed by the Turbine Contractor as part of the outcome of this contract.
8.4.10 Exemption required Final civil design not completed. Cannot be completed until Turbine Contractor appointed and feeds into the design.
8.4.11 MUA to confirm LOD have completed
8.4.12 MUA to confirm has been completed
8.4.13 MUA to confirm the criteria has been met
8.4.14 Consider N/A for this project
8.4.15 Criteria met
8.4.16 Consider N/A for this project
8.4.17 Consider N/A for this project
8.4.18 Consider N/A for this project
8.4.19 Criteria met
8.4.20 Consider N/A for this project
8.4.21 MUA to confirm SMS have completed
Clague, Simon (MU)
06 June 2024 16:34
De-Yoxall, Sarah
Randall, Caldric (Treasury); Sidebottom, Andrew (Treasury)
RE: Windfarm(s) - airport radar
s.30
s.30
Clague, Simon (MU)
30 October 2024 14:27
Lord, Jason
RE: Treasury paper - onshore wind
Proposal 005 - Additional EIA Works.pdf
Transport Walkover PEA Update/TN £3,600.00
Aerial Tree Assessment £41,100.00
Stakeholder Engagement £4,900.00
Data Records £2,600.00
ES Update 2025 £10,500.00
Ecology – TOTAL £524,400.00
EIA
Health ES Chapter £20,400.00
Non-Technical Natural Disaster Comments £3,100.00
EIA Coordination & Addendum £32,900.00
EIA – TOTAL £56,400.00
LVIA
Offshore visual assessment and seascape assessment reported as part of the SLVIA £6,400.00
Night-time Assessment reported as an appendix within the SLVIA £14,600.00
Photomontages for public consultation £5,400.00
Cumulative assessment £4,700.00
LVIA – TOTAL £31,100.00
Peat
Outline Peat and Soils Management Plan £6,500.00
Peat – TOTAL £6,500.00
Socio Economics
Additions to the SIA Study £5,600.00
Socio Economics – TOTAL £5,600.00
TOTAL £736,400.00
Month/Year March 2025
Project Name Cair Vie Onshore Windfarm
Project Code (Job) No. RGW001
Scope of Works Feasibility: Environmental Impact Assessment for Earystane + Planning submission of environmental chapters Design following planning approval Construction of an onshore windfarm at Earystane site to include all site preparation, installation and Civil works. Planning supervisor services Cost consultant Network modelling (initial feasibility complete)
Project Phase EIA / Feasibility Compiling D1 documents, (seek waiver for elements of the construction of projects’ due to procurement of components)
Contract Form/Strategy Awaiting procurement specialist advice NEC for EIA stage
Manx Utilities Project Manager Mark Inman
Project Sponsor Lizzie Riley
Project SRO Adrian Dobbins
Designer Wardell Armstrong LLP
Planning Supervisor Safety Management Services appointed
Cost Consultant Long O Donnell QS appointed
NEC Project Manager N/A Bell Burton (Service Manager for WA contract) no NEC PM appointed
Business Case Budget N/A Pre-project estimate £36M approved by Manx Utilities Board D1 Budget TBD £41,727,607.63 estimated for micro- site Latest update provided by QS
I1 Budget I2 Budget
I3 Budget Concurrence Budget Total: £3.3
£2.1M EIA £1.2M (EIA Extension + Legal)
Actual Cost to Date £3,070,779.61 Expected Final Cost TBD £41,727,607.63 Microsite design estimate

Full Response Text

Major Projects Board

Meeting to be held Thursday 27th June 2024 Via MS- Teams 14:00 – 15:30

Attendees

Barry O’Driscoll - Chair

Andrew Sidebottom

Sarah D-Yoxall

Elizabeth Smith - Minutes


AGENDA

 MUA Onshore Wind

Out of scope s.25

c:\users\tresols\appdata\local\microsoft\windows\inetcache\content.outlook\6uhk6v09\2024-06-04 wind procurement risks v4.docxc:\users\meadobbi\appdata\local\microsoft\windows\inetcache\content.outlook\9pa25dtv\2024 05 07 wind procurement risks v3.docx Save date: 06 June 202404 June 2024 Page 2 of 7

  1. One of the challenges with any process we may adopt is the timescale needed to eventually realise the gains. For example, 12 months is being allowed for a planning determination to be secured, Tynwald funding approval may take 3 months, procurement 6 months and construction 12 months, giving a total of 33 months. This would mean an earliest date of operations from 1 April 2024 of December 20261. However; extending the time allowed for this project wouldn’t change the recommended sequence of activities for the programme.
  2. It is also highly desirable for the manufacturer and civils contractor to provide input into the design and planning application, in order that the design is as specific as possible to minimise the risks of challenge to the planning consideration process and the planning determination made. This means that these key suppliers should be appointed prior to the planning application being made and with reference to the standard approach some I3 activities need to take place during the I1 stage. In affect, we have to balance a procurement risk versus a delivery risk and associated later realisation of project benefits.

CURRENT STATUS AND PROPOSALS 6. The lead time on ordering turbines2 is 14 months (based on the Prior Information Notice (PIN) process already undertaken) meaning either the turbines need to be ordered ahead of planning approval being secured or the first operating date will be later than 2026. As such, it has been proposed to undertake a procurement exercise to ascertain the lead times and contractual terms that may be offered by suppliers prior to a planning determination.
7. The proposed contracting structure3 for the scheme was as follows:

1 Note that installation and commissioning of wind turbines is considered only possible over the summer period. 2 Lead times on transformers and blade lifters is also understood to be more than 12 months. 3 Bird and Bird ‘Isle of Man Onshore Renewals Project’ report dated January 2023. The report’s considerations included the optimal contractual structure and procurement approach. The report recommended the publicly owned structure recommended this should be the quickest route to commencing work on the project.

c:\users\tresols\appdata\local\microsoft\windows\inetcache\content.outlook\6uhk6v09\2024-06-04 wind procurement risks v4.docxc:\users\meadobbi\appdata\local\microsoft\windows\inetcache\content.outlook\9pa25dtv\2024 05 07 wind procurement risks v3.docx Save date: 06 June 202404 June 2024 Page 3 of 7

  1. The above structure recommended a single Engineering, Procurement and Construction (EPC) contractor. The PIN process identified that securing a single EPC contractor was unlikely to be possible, with credible turbine manufacturers unlikely to engage in undertaking civil works in the Isle of Man. It is also uncertain if a manufacturer will deliver the turbine components to site, and therefore a potential separate transportation contractor may need to be engaged.
    As such, a least 2 or 3 key contractors are likely to be involved in the scheme, and likely to be contracted to Manx Utilities (as opposed to being sub-contractors of a ‘main contractor’).
  2. This presents a challenge of sequencing the appointments. It is currently proposed that a turbine manufacturer will be appointed first, followed by a civils construction contractor and followed by transportation contractors4 (marine and onshore, as required).
  3. The Bird and Bird report also considered the procurement process. Their recommendations generally followed the Isle of Man Government tendering process but consideration was also given to including commercial negotiations within the tender process. The overall procurement process assumed a single EPC contractor and so did not consider the potential interactions between Manx Utilities and multiple contractors.

4 It may be possible and/or appropriate to place both civils contractor and transportation contracts concurrently depending on the manufacturer selected.

c:\users\tresols\appdata\local\microsoft\windows\inetcache\content.outlook\6uhk6v09\2024-06-04 wind procurement risks v4.docxc:\users\meadobbi\appdata\local\microsoft\windows\inetcache\content.outlook\9pa25dtv\2024 05 07 wind procurement risks v3.docx Save date: 06 June 202404 June 2024 Page 4 of 7

  1. It is currently considered that single-stage contracts be entered into with suppliers, with break clauses included in the event that either planning approval or Tynwald funding is not secured for the scheme. This means that Manx Utilities will be able to terminate the contracts in the event the scheme is not approved but also means that a contracted price will need to be agreed at this stage, with any changes to the scheme being chargeable to Manx Utilities as Compensation Events.
  2. Consideration has been given to a two-stage Early Contractor Involvement (ECI) approach. This would allow a contractor to be engaged under contract to support the design and planning process, with a second contract for the manufacture/construction phase negotiated and agreed following confirmation of planning and funding approval. However, the two contract approach means that the supplier would not be contractually bound at this stage for the second contract, and there is a risk that the contractor does not wish to proceed with the second contract and therefore Manx Utilities needs to repeat design and planning work following funding approval.

KEY PROJECT RISKS 13. Undertaking a procurement process prior to completion of surveys and design work gives risks that contractual costs may not be an accurate reflection of costs.
a. Planning risk – risk that planning approval is not secured and goods (eg. turbines and electrical components) and services (eg. survey and design works) purchased cannot deliver the same value at an alternative site. b. Lack of Scope5 definition and/or Scope change, and gaps in information at the tender stage – can result in higher than anticipated costs through Compensation Events being raised by contractors in response to new information later in the development process. The contracts (and therefore Scopes) must be confirmed prior to each contract being signed, with any further changes being chargeable to Manx Utilities by the contractor as a Compensation Event.
c. Cost effective design – risk of design changes being required following receipt of new information resulting in a less optimal design6 than had fuller information been available earlier in the development process.

5 Scope, as defined for NEC4 contracts. The Scope is a critical document as it defines precisely what a supplier will deliver for the agreed cost; any incorrect items within the Scope or items omitted from the Scope result in additional contractual costs for Manx Utilities. 6 For example, it may that turbine placement assumptions are found to be incorrect later in the process and a turbine must be foregone, as opposed to reconfiguring the placement to retain the proposed number of turbines.

c:\users\tresols\appdata\local\microsoft\windows\inetcache\content.outlook\6uhk6v09\2024-06-04 wind procurement risks v4.docxc:\users\meadobbi\appdata\local\microsoft\windows\inetcache\content.outlook\9pa25dtv\2024 05 07 wind procurement risks v3.docx Save date: 06 June 202404 June 2024 Page 5 of 7

d. Programming risks – it is likely that multiple key suppliers will be required for the scheme. For example, the road transport route will require preparation but this will be dependent on the road transport provider, which will be dependent on the manufacturer. This can lead to a delay with one contractor resulting in multiple delay costs being incurred by Manx Utilities to other contractors.
e. Principle Contractor risks – the proposed contract structuring is that Manx Utilities will contract directly and separately with the manufacturer and civils contractor (and possibly transportation contractors). This can result in a lack of clarity in respect of liabilities (including health and safety and warranties) through the scheme.
f. Outstanding information for the tender (see below). 14. Outstanding information for the tender currently includes: a. Pre-tender Health & Safety plan. b. Pre-tender cost consultants report – cost information has been received but scheme uncertainties mean that some aspects of the scheme have not been costed currently.
c. Site information documentation, including survey results. For example, ground conditions reports will not be available until later in the year and so there is a risk that construction costs will increase materially once surveys have been completed.
d. Interface definitions – it is possible that separate contractors will be used for each of manufacture of turbines, marine transportation, onshore transportation, civil works, installation of turbines, electrical and mechanical ‘balance of plant’, grid connection and commissioning. Each contract must state where the responsibilities of a contractor begin and end; multiple contractors mean that there is a heightened risk of gaps between responsibilities or overlaps in works (and overlap of costs).
15. Planning risk is considered to be the key project risk in that both the decision and timing of a final decision are uncertain, and these risks cannot be fully mitigated.
In order to meet the 2026 target it is necessary to select a manufacturer, a civils construction contractor and transportation contractors during 2024. This is so that finalisation of the design and the planning application can be based on a specific turbine design and the risk of changes following a planning approval decision is minimised.

c:\users\tresols\appdata\local\microsoft\windows\inetcache\content.outlook\6uhk6v09\2024-06-04 wind procurement risks v4.docxc:\users\meadobbi\appdata\local\microsoft\windows\inetcache\content.outlook\9pa25dtv\2024 05 07 wind procurement risks v3.docx Save date: 06 June 202404 June 2024 Page 6 of 7

  1. However, this also means that procurement activities to appoint key suppliers need to take place ahead of a planning determination. In the event that a planning decision is rejected then it is possible that costs will have been expended for goods and services that cannot be applied to an alternative scheme. These costs will include the design and survey work undertaken at Earystane, any potential costs with engaged contractors (such as any non- refundable deposits to book manufacturing slots or specialist installation equipment; the proposed tender is to ascertain if such non-refundable deposits would be required) and any route adaptions for the onshore transportation (it may not be possible to delay the commencement of this work until planning approval has been secured and still achieve the 2026 target date).
  2. The contractual risks arise due to imperfections in information required for a robust tendering and contracting process. Once the scheme is committed to, a single stage contract placed at this stage will mean that any variations to the works proposed (as defined by either Manx Utilities or the contractor) will be subject to Compensation Events, and gives rise to the risk of unbounded cost increases. Future Compensation Events are not necessarily an issue where the probability and impact (including financial impact) can be estimated in advance but sufficient information needs to be available to make reliable estimates prior to contracting to understand the potential cost range for the scheme before contracts are signed.

IMPACT OF STANDARD APPROACH 18. It is possible to more closely follow the Government procurement approach for capital schemes. This would require survey and design work to be completed prior to a planning application being submitted. Should this be successful, an application for funding would then be made to Tynwald. Tendering exercises would be undertaken for scheme delivery once planning and funding approvals were successful.
19. There does not currently appear to be a viable programme that would follow this approach and still achieve the 2026 target. 20. Whilst the planning risks above would appear to be mitigated by this approach, there is a different planning risk that a generic turbine design would need to be used for the planning application and a subsequently tendered manufacturing contract may not be sufficiently close to the approved planning application design, and so would require a further planning application to be made.
21. This risk also applies to the civils construction works in that a different turbine design may require a different civils design. It should also be noted that the Environment Impact Assessments (EIA) and subsequent mitigation measures submitted as part of a planning application may be dependent on the turbine and civils designs.
22. The timing and decision risks associated with this may be lower than for the initial application, but the risks remain and it may also be that survey results become time-expired and new surveys are required before a new application can be submitted.

c:\users\tresols\appdata\local\microsoft\windows\inetcache\content.outlook\6uhk6v09\2024-06-04 wind procurement risks v4.docxc:\users\meadobbi\appdata\local\microsoft\windows\inetcache\content.outlook\9pa25dtv\2024 05 07 wind procurement risks v3.docx Save date: 06 June 202404 June 2024 Page 7 of 7

  1. The tendering and contracting risks would appear to be mitigated with this approach. However, it is expected that demand for onshore wind turbines will increase in the coming years (based on recent UK Contract for Difference awards) and therefore costs and availability for the Isle of Man may be higher as a result.
  2. Manx Utilities is currently budgeting to have power station fuel supply costs for 2024-25 of £33 mil

[Response truncated — full text is 176,137 characters]