New Liverpool Ferry Terminal
| Authority | Department of Infrastructure |
|---|---|
| Date received | 2024-08-27 |
| Outcome | All information sent |
| Outcome date | 2024-09-16 |
| Case ID | 4082714 |
Summary
The requester asked for the construction completion date and the name of the Project Manager for the New Liverpool Ferry Terminal. The Department of Infrastructure disclosed that construction was completed on 5 April 2024, with contract completion occurring 12 months later, and identified Turner & Townsend as the Project Manager.
Key Facts
- Construction of the New Liverpool Ferry Terminal was completed on 5 April 2024.
- The contract completion date is set for twelve months after the construction completion date.
- Turner & Townsend is the Project Manager for the project.
- The project was carried out under a 'Target Cost' contract.
- Recent cost estimates for the terminal are upwards of £70-75 million.
Data Disclosed
- 5th April 2024
- twelve months
- £70-75 million
- 65 weeks
- 4082714
- 27 August 2024
- 13 September 2024
Original Request
These are extracts from a Manx Radio News report dated the 26th August 2024 - "Final cost of Liverpool Ferry Terminal STILL unknown Figure expected 65-weeks after construction completion The Infrastructure Minister says the final cost of the Liverpool Ferry Terminal is still not known. Tim Crookall says, due to the type of contract the project was carried out on, the final price tag won't be known until 65 weeks after completion. Recent estimates put the figure at upwards of £70-75 million. Responding to a Tynwald Question for Written Answer, Minister Crookall says the construction was carried out on a 'Target Cost' contract, where by the contractor estimates the project cost, including overheads and preliminaries, at tender stage. "Adjustments to the Target Cost can occur during the contract project through compensation events." he says. "Final payment is assessed by the Project Manager post-completion, with mechanisms in place for dispute resolution if the assessment is contested."" I require to know - 1. The date on which, under the contract, construction of the the New Ferry Terminal was "completed"; and 2. The name of the Project Manager.
Data Tables (1)
Full Response Text
Department of Infrastructure Sea Terminal Building, Douglas, Isle of Man, IM1 2RF
Contact: FOI Response Team Telephone: (01624) 686785 Email: dpo-doi@gov.im
Our ref: 4082714 13 September 2024
Dear ###
We write further to your request, received 27 August 2024, which states:
"These are extracts from a Manx Radio News report dated the 26th August 2024 -
"Final cost of Liverpool Ferry Terminal STILL unknown
Figure expected 65-weeks after construction completion
The Infrastructure Minister says the final cost of the Liverpool Ferry Terminal is still not known.
Tim Crookall says, due to the type of contract the project was carried out on, the final price tag won't be known until 65 weeks after completion.
Recent estimates put the figure at upwards of £70-75 million.
Responding to a Tynwald Question for Written Answer, Minister Crookall says the construction was carried out on a 'Target Cost' contract, where by the contractor estimates the project cost, including overheads and preliminaries, at tender stage.
"Adjustments to the Target Cost can occur during the contract project through compensation events." he says.
"Final payment is assessed by the Project Manager post-completion, with mechanisms in place for dispute resolution if the assessment is contested.""
I require to know -
-
The date on which, under the contract, construction of the the New Ferry Terminal was "completed"; and
-
The name of the Project Manager."
Our response to your request is as follows: Information held
Construction was completed on the 5th April 2024 but the contract completion will be twelve months from this date.
The project manager is Turner & Townsend (Global Headquarters in Leeds).
Please quote the reference number 4082714 in any future communications.
Your right to request a review
If you are unhappy with this response to your freedom of information request, you may ask us to carry out an internal review of the response, by completing a complaint form and submitting it electronically or by delivery/post.
An electronic version of our complaint form can be found by going to our website at https://services.gov.im/freedom-of-information/Review . If you would like a paper version of our complaint form to be sent to you by post, please contact me and I will be happy to arrange for this. Your review request should explain why you are dissatisfied with this response, and should be made as soon as practicable. We will respond as soon as the review has been concluded.
If you are not satisfied with the result of the review, you then have the right to appeal
to the Information Commissioner for a decision on;
1. Whether we have responded to your request for information in accordance with
Part 2 of the Freedom of Information Act 2015; or
2. Whether we are justified in refusing to give you the information requested.
In response to an application for review, the Information Commissioner may, at any
time, attempt to resolve a matter by negotiation, conciliation, mediation or another
form of alternative dispute resolution and will have regard to any outcome of this in
making any subsequent decision.
More detailed information on your right to a review can be found on the Information
Commissioner’s website at www.inforights.im.
Should you have any queries concerning this letter, please do not hesitate to contact
me.
Further information about freedom of information requests can be found at
www.gov.im/foi.
I will now close your request as of this date.