Foxdale Road project info

AuthorityDepartment of Infrastructure
Date received2017-02-13
OutcomeAll information sent
Outcome date2017-02-27
Case ID355771

Summary

A request for the Foxdale Road project plan, costs, staffing numbers, and completion times was made to the Department of Infrastructure, and all requested information was disclosed.

Key Facts

  • The Department of Infrastructure confirmed that all requested information regarding the Foxdale Road project was sent.
  • The total estimated budget for the project is £1,800,000.
  • Expenditure to date at the time of the response was £337,169.82.
  • The project includes works on drainage, earthworks, pavements, and traffic signs.
  • The response was issued on 27 February 2017 following a request received on 13 February 2017.

Data Disclosed

  • 2017-02-13
  • 2017-02-27
  • £1,800,000
  • £337,169.82
  • £500,000
  • £20,000
  • £230,000
  • £85,000
  • £570,000
  • £250,000
  • £10,000
  • £40,000
  • 5%

Data Tables (1)

General Summary Series 100: Preliminaries Series 200: Site Clearance Series 500: Drainage and Service Ducts Series 600: Earthworks Series 700: Pavements Series 1100: Kerbs Footways & Paved Areas Series 1200: Traffic Signs and Road Markings Series 2700: Accommodation Works and Works for Statutory Undertakers £ 500,000 £ 20,000 £ 230,000 £ 85,000 £ 570,000 250,000 £ 10,000 £ 40,000 Expenditure to date
Total £ 1,705,000 337,169.82
Contingencies (5%) Planning Supervisor Fees £ 85,000 £ 10,000
Total £ 1,800,000 337,169.82

Full Response Text

Department of Infrastructure Sea Terminal Building, Douglas, Isle of Man, IM1 2RF

Dear

FOI Reference No: IM77925I – Foxdale Road project information Request Under The Freedom Of Information Act 2015 (“The Act”)

Thank you for your request dated 13 February 2017.

Your request

  1. a) An action plan or project plan for the road works currently taking place on the Foxdale Road.

b) Estimated costs for the work.

  1. The number of Doi staff involved on site and the number of contractors working on the project.

  2. Planned times of completion for each section/stage of the works

Response to your request

  1. I enclose a copy of all of the information you requested.

a) See Appendix 1 b) Financial Review

General Summary Series 100: Preliminaries Series 200: Site Clearance Series 500: Drainage and Service Ducts Series 600: Earthworks Series 700: Pavements Series 1100: Kerbs Footways & Paved Areas Series 1200: Traffic Signs and Road Markings Series 2700: Accommodation Works and Works for Statutory Undertakers

£ £ £ £ £

£ £

500,000 20,000 230,000 85,000 570,000 250,000 10,000 40,000 Expenditure to date Total £ 1,705,000 337,169.82

Contingencies (5%) Planning Supervisor Fees £ £ 85,000 10,000

Total £ 1,800,000 337,169.82

APPENDIX 1