Foxdale Road project info
| Authority | Department of Infrastructure |
|---|---|
| Date received | 2017-02-13 |
| Outcome | All information sent |
| Outcome date | 2017-02-27 |
| Case ID | 355771 |
Summary
A request for the Foxdale Road project plan, costs, staffing numbers, and completion times was made to the Department of Infrastructure, and all requested information was disclosed.
Key Facts
- The Department of Infrastructure confirmed that all requested information regarding the Foxdale Road project was sent.
- The total estimated budget for the project is £1,800,000.
- Expenditure to date at the time of the response was £337,169.82.
- The project includes works on drainage, earthworks, pavements, and traffic signs.
- The response was issued on 27 February 2017 following a request received on 13 February 2017.
Data Disclosed
- 2017-02-13
- 2017-02-27
- £1,800,000
- £337,169.82
- £500,000
- £20,000
- £230,000
- £85,000
- £570,000
- £250,000
- £10,000
- £40,000
- 5%
Data Tables (1)
| General Summary Series 100: Preliminaries Series 200: Site Clearance Series 500: Drainage and Service Ducts Series 600: Earthworks Series 700: Pavements Series 1100: Kerbs Footways & Paved Areas Series 1200: Traffic Signs and Road Markings Series 2700: Accommodation Works and Works for Statutory Undertakers | £ 500,000 £ 20,000 £ 230,000 £ 85,000 £ 570,000 250,000 £ 10,000 £ 40,000 | Expenditure to date |
|---|---|---|
| Total | £ 1,705,000 | 337,169.82 |
| Contingencies (5%) Planning Supervisor Fees | £ 85,000 £ 10,000 | |
| Total | £ 1,800,000 | 337,169.82 |
Full Response Text
Department of Infrastructure Sea Terminal Building, Douglas, Isle of Man, IM1 2RF
Dear
FOI Reference No: IM77925I – Foxdale Road project information Request Under The Freedom Of Information Act 2015 (“The Act”)
Thank you for your request dated 13 February 2017.
Your request
- a) An action plan or project plan for the road works currently taking place on the Foxdale Road.
b) Estimated costs for the work.
-
The number of Doi staff involved on site and the number of contractors working on the project.
-
Planned times of completion for each section/stage of the works
Response to your request
- I enclose a copy of all of the information you requested.
a) See Appendix 1 b) Financial Review
General Summary Series 100: Preliminaries Series 200: Site Clearance Series 500: Drainage and Service Ducts Series 600: Earthworks Series 700: Pavements Series 1100: Kerbs Footways & Paved Areas Series 1200: Traffic Signs and Road Markings Series 2700: Accommodation Works and Works for Statutory Undertakers
£ £ £ £ £
£ £
500,000 20,000 230,000 85,000 570,000 250,000 10,000 40,000 Expenditure to date Total £ 1,705,000 337,169.82
Contingencies (5%) Planning Supervisor Fees £ £ 85,000 10,000
Total £ 1,800,000 337,169.82
APPENDIX 1