The request sought details on the Department of Infrastructure's funding and contractual arrangements with the group Footpath Friends. The authority disclosed that the group received £25,000 annually for three years to undertake agreed works, which were monitored on a job-by-job basis, and confirmed the contract has since expired.
Key Facts
- Footpath Friends received £25,000 per year in funding from the Department of Infrastructure.
- The total contract value was £75,000 over a three-year period.
- The contract has expired and no funding is currently available for the group.
- Works and targets were agreed and monitored on a job-by-job basis rather than through fixed KPIs.
- The funding was not awarded through a competitive tender but via an FD8 Waiver.
Data Disclosed
- £25,000
- £75,000
- 3 years
- 2021-08-17
- 2021-08-20
- 1951873
- FD8 Waiver
Original Request
Would you be kind enough to provide information on the Department's arrangements with and funding of the Isle of Man group Footpath Friends? 1. What is the group Footpath Friends paid by the Department do? 2. What are the terms of the contract, or KPIs, or agreement, etc (whatever exists), between the Department and Footpath Friends? 3. Has the group Footpath Friends met the terms of its contract, KPIs, agreement, etc (whatever exists)? 4. How much annual funding is paid by the Department to Footpath Friends (broken down by year if the sum is not the same each year)? 5. Is the Department's funding of Footpath Friends the result of a competitive tendering exercise, publicly advertised opportunity, etc?
Data Tables (1)
Data Tables (reformatted)
| Question | Response |
|---|---|
| 1. What is the group Footpath Friends paid by the Department do? | £25,000 per year. |
| 2. What are the terms of the contract, or KPIs, or agreement, etc (whatever exists), between the Department and Footpath Friends? | The works undertaken by the Footpath Friends are agreed with the Department and targets and timescales agreed and monitored on a job by job basis. |
| 3. Has the group Footpath Friends met the terms of its contract, KPIs, agreement, etc (whatever exists)? | Yes. |
| 4. How much annual funding is paid by the Department to Footpath Friends (broken down by year if the sum is not the same each year)? | The contract was for 3 years with a total of £75,000 paid, annually at £25,000. The contract has now expired so no funding has been made available this year. |
| 5. Is the Department's funding of Footpath Friends the result of a competitive tendering exercise, publicly advertised opportunity, etc? | No, it was undertaken via an FD8 Waiver (copy attached). |
Full Response Text
Department of Infrastructure Sea Terminal Building, Douglas, Isle of Man, IM1 2RF
Contact: FOI Response Team/DW/RH Telephone: (01624) 686785 Email: dpo-doi@gov.im
Our ref: 1951873 20 August 2021
Dear ###
We write further to your request which was received on 17 August 2021 and which states (sic):
"Would you be kind enough to provide information on the Department's arrangements with and funding of the Isle of Man group Footpath Friends? 1. What is the group Footpath Friends paid by the Department do? 2. What are the terms of the contract, or KPIs, or agreement, etc (whatever exists), between the Department and Footpath Friends? 3. Has the group Footpath Friends met the terms of its contract, KPIs, agreement, etc (whatever exists)? 4. How much annual funding is paid by the Department to Footpath Friends (broken down by year if the sum is not the same each year)? 5. Is the Department's funding of Footpath Friends the result of a competitive tendering exercise, publicly advertised opportunity, etc?"
In response to your request
1.
£25,000 per year.
2.
The works undertaken by the Footpath Friends are agreed with the Department
and targets and timescales agreed and monitored on a job by job basis.
3.
Yes.
4.
The contract was for 3 years with a total of £75,000 paid, annually at £25,000.
The contract has now expired so no funding has been made available this year.
5.
No, it was undertaken via an FD8 Waiver (copy attached).
Please quote the reference number 1951873 in any future communications.
Your right to request a review
If you are unhappy with this response to your freedom of information request, you may ask us to carry out an internal review of the response, by completing a complaint form and submitting it electronically or by delivery/post.
An electronic version of our complaint form can be found by going to our website at
https://services.gov.im/freedom-of-information/Review . If you would like a paper
version of our complaint form to be sent to you by post, please contact us and we will
be happy to arrange for this. Your review request should explain why you are
dissatisfied with this response, and should be made as soon as practicable. We will
respond as soon as the review has been concluded.
If you are not satisfied with the result of the review, you then have the right to appeal
to the Information Commissioner for a decision on;
1. Whether we have responded to your request for information in accordance with
Part 2 of the Freedom of Information Act 2015; or
2. Whether we are justified in refusing to give you the information requested.
In response to an application for review, the Information Commissioner may, at any
time, attempt to resolve a matter by negotiation, conciliation, mediation or another
form of alternative dispute resolution and will have regard to any outcome of this in
making any subsequent decision.
More detailed information on your right to a review can be found on the Information
Commissioner’s website at www.inforights.im.
Should you have any queries concerning this letter, please do not hesitate to contact
us.
Further information about freedom of information requests can be found at
www.gov.im/foi.
We will now close your request as of this date.
Yours sincerely
FOI Response Team