The Department of Infrastructure responded to a request for maintenance costs of The Donkey Track/U72 in Andreas, disclosing a detailed breakdown of labor and equipment expenses totaling £6,556.56 for works carried out in February 2019.

Key Facts

  • The request covered total expenditure and dates of maintenance works on The Donkey Track/U72.
  • The disclosed costs relate to a specific operation in February 2019 involving a 5-ton excavator and a Hiab.
  • The total running cost for the works was £6,556.56.
  • Labor costs were calculated at flat basic rates without profit or overheads.
  • The response included costs for a second visit to clear a soil bund stockpile.

Data Disclosed

  • £6,556.56
  • 17 November 2020
  • 27 November 2020
  • 10-02-19
  • 17-02-19
  • 24-02-19
  • £1,211.65
  • £881.60
  • £316.83
  • £1,006.25
  • £1,680.00
  • £1,190.00
  • £46.24
  • £84.00
  • £140.00
  • 1563109

Original Request

Please specify the following: 1. The total expenditure of maintenance and/or road works on The Donkey Track/U72 at Andreas by the DOI and each of its predecessors; and 2. The dates upon which each works were carried out and completed and the cost of those individual works.

Data Tables (1)

we 10-02-19 we 17-02-19 we 24-02-19 total hours cost/hr total Notes
Chargehand 42.5 34.5 8.75 85.75 £14.13 £1,211.65
laborer 40 32 8 80 £11.02 £881.60
laborer 19 9.75 28.75 £11.02 £316.83
Hyab 19 9.75 28.75 £35.00 £1,006.25 hyab including operator
360 exc 40 40 2 weeks £840.00 £1,680.00 based on hire charge from Ace Hire
2 culvert units £595.00 £1,190.00 cost units from BPD.
360 operator 4 4 £11.56 £46.24 second operation reinstateing access
360 exc 4 4 £21.00 £84.00 based on 40hr cost above
hyab 4 4 £35.00 £140.00 second operation reinstateing access
£6,556.56 Running total

Full Response Text

we 10-02-19 we 17-02-19 we 24-02-19 total hours cost/hr total Notes Chargehand 42.5 34.5 8.75 85.75 £14.13 £1,211.65 laborer 40 32 8 80 £11.02 £881.60 laborer 19 9.75 28.75 £11.02 £316.83 Hyab 19 9.75 28.75 £35.00 £1,006.25 hyab including operator 360 exc 40 40 2 weeks £840.00 £1,680.00 based on hire charge from Ace Hire 2 culvert units £595.00 £1,190.00 cost units from BPD. 360 operator 4 4 £11.56 £46.24 second operation reinstateing access 360 exc 4 4 £21.00 £84.00 based on 40hr cost above hyab 4 4 £35.00 £140.00 second operation reinstateing access £6,556.56 Running total * the cost of labour is the flat basic rate paid to the operator in early 20119 with no profit or overhead No allowance has been made for vehicles or welfare facilities except for the Hyab rate.


Department of Infrastructure Sea Terminal Building, Douglas, Isle of Man, IM1 2RF

Contact: FOI Response Team Telephone: (01624) 686785 Email: dpo-doi@gov.im

Our ref: 1563109 27 November 2020

Dear ###

We write further to your request which was received on 17 November 2020 and which states:

"Please specify the following: 1. The total expenditure of maintenance and/or road works on The Donkey Track/U72 at Andreas by the DOI and each of its predecessors; and 2. The dates upon which each works were carried out and completed and the cost of those individual works."

The answers to your questions are shown in the attached table. The figures are based on a gang with a 5 ton 360 excavator and a hiab (lift wagon) and include the second visit to clear the stockpile (soil bund). Please quote the reference number 1563109 in any future communications.

Your right to request a review

If you are unhappy with this response to your freedom of information request, you may ask us to carry out an internal review of the response, by completing a complaint form and submitting it electronically or by delivery/post.

An electronic version of our complaint form can be found by going to our website at https://services.gov.im/freedom-of-information/Review . If you would like a paper version of our complaint form to be sent to you by post, please contact us and we will be happy to arrange for this. Your review request should explain why you are dissatisfied with this response, and should be made as soon as practicable. We will respond as soon as the review has been concluded. If you are not satisfied with the result of the review, you then have the right to appeal to the Information Commissioner for a decision on; 1. Whether we have responded to your request for information in accordance with Part 2 of the Freedom of Information Act 2015; or 2. Whether we are justified in refusing to give you the information requested.

In response to an application for review, the Information Commissioner may, at any time, attempt to resolve a matter by negotiation, conciliation, mediation or another form of alternative dispute resolution and will have regard to any outcome of this in making any subsequent decision. More detailed information on your right to a review can be found on the Information Commissioner’s website at www.inforights.im. Should you have any queries concerning this letter, please do not hesitate to contact us. Further information about freedom of information requests can be found at www.gov.im/foi. We will now close your request as of this date.

Yours sincerely

FOI Response Team