Summary
The requester asked for a cost breakdown, roles, and impact assessment of four UK consultants employed by the Department of Infrastructure's Highway services. The authority disclosed the total net cost and the reason for employment but refused to provide an opinion on whether the costs were detrimental to other services.
Key Facts
- The overall net cost for the four UK consultants was £177,340.
- The consultants were employed between 1 July 2019 and 25 March 2020.
- The agency workers were hired to fill staffing gaps within the Department.
- The Department refused to answer if the costs were detrimental to other services as it constitutes an opinion rather than recorded information.
- The request was handled by the Department of Infrastructure in the Isle of Man.
Data Disclosed
- £177,340
- 1 July 2019
- 25 March 2020
- 4 UK consultants
- 26 June 2020
- 10 July 2020
- 1347242
Exemptions Cited
- Request for opinion rather than information held
Original Request
Could the Department give a breakdown on cost's asssociated with the 4 UK consultants employed by the Highway services maintenance at Ellerslie from 1 July 2019 until 25 March 2020 and what was the role the were carrying out and was the cost detrimental to any other maintenance service the Department carry out?
Data Tables (1)
Full Response Text
Department of Infrastructure Sea Terminal Building, Douglas, Isle of Man, IM1 2RF
Contact: FOI Response Team/DWG/MF Telephone: (01624) 686785 Email: dpo-doi@gov.im
Our ref: 1347242 10 July 2020
Dear ###
We write further to your request which was received on 26 June 2020 and which states (sic) numbered for ease of reference:
"1. Could the Department give a breakdown on cost's asssociated with the 4 UK consultants employed by the Highway services maintenance at Ellerslie from 1 July 2019 until 25 March 2020 and 2. what was the role the were carrying out and 3. was the cost detrimental to any other maintenance service the Department carry out?"
The answers to your questions are:
1.
The overall nett cost was £177,340.
2.
The agency workers were employed to fill the gaps in staffing that the Department
had during that time.
3.
This is asking for an opinion rather than being a request for ‘information held’.
For this reason, the Department is unable to provide an answer as no such opinion has
been recorded.
Please quote the reference number 1347242 in any future communications.
Your right to request a review
If you are unhappy with this response to your freedom of information request, you may ask us to carry out an internal review of the response, by completing a complaint form and submitting it electronically or by delivery/post.
An electronic version of our complaint form can be found by going to our website at https://services.gov.im/freedom-of-information/Review . If you would like a paper version of our complaint form to be sent to you by post, please contact us and we will be happy to arrange for this. Your review request should explain why you are dissatisfied with this response, and should be made as soon as practicable. We will respond as soon as the review has been concluded.
If you are not satisfied with the result of the review, you then have the right to appeal
to the Information Commissioner for a decision on;
1. Whether we have responded to your request for information in accordance with
Part 2 of the Freedom of Information Act 2015; or
2. Whether we are justified in refusing to give you the information requested.
In response to an application for review, the Information Commissioner may, at any
time, attempt to resolve a matter by negotiation, conciliation, mediation or another
form of alternative dispute resolution and will have regard to any outcome of this in
making any subsequent decision.
More detailed information on your right to a review can be found on the Information
Commissioner’s website at www.inforights.im.
Should you have any queries concerning this letter, please do not hesitate to contact
us.
Further information about freedom of information requests can be found at
www.gov.im/foi.
We will now close your request as of this date.
Yours sincerely