Peel Marina Project Board

AuthorityDepartment of Infrastructure
Date received2020-01-15
OutcomeAll information sent
Outcome date2020-02-07
Case ID1134325

Summary

A request was made for minutes of the Peel Marina Project Board meetings, and the Department of Infrastructure disclosed all information including 161 pages of documents covering silt management strategies and environmental data.

Key Facts

  • The project aims to find the best solution for problematic silt at Peel Marina considering cost, environment, and operational impact.
  • Lead levels in 60% of surface silt samples exceeded Cefas Action Level 2 thresholds.
  • The preferred option for existing silt involves dredging, dewatering for 12 months, and moving dry material to the Foxdale Deads.
  • High lead concentrations in water runoff from the Cross Vein Mine area were linked to disturbance by off-road bikes.
  • Water quality changes are expected to take 1-3 years to settle, potentially deteriorating before improving.

Data Disclosed

  • 60% of surface samples exceeded Lead Action Level 2
  • 10% of samples exceeded Zinc Action Level 2
  • 161 pages
  • 11 documents
  • 2020-01-15
  • 2020-02-07
  • 12 months dewatering
  • 1-3 years settlement time
  • 2,153 micrograms/l Lead (Site 1)
  • 10,940 micrograms/l Lead (Site 2)
  • 8,525 micrograms/l Lead (Site 3)
  • 288 milligrams/l Suspended Solids (Site 2)

Original Request

Copies of the minutes of all meetings of the Peel Marina Project Board.

Data Tables (136)

23.7 1.75 23.1 70.7 0.06 24.2 496 439
19.6 1.6 24 108 0.14 23.1 601 557
21.3 2.33 20.9 65.2 0.09 21.3 743 554
16.9 0.68 22.8 30.9 0.03 23.8 277 253
31.1 2.93 26.2 66.8 0.1 26.1 948 667
40.3 3.65 31.8 75.7 0.11 31.5 1060 797
12.3 1.42 33.5 56.2 0.07 32.8 206 237
34 3.6 28.5 72.5 0.12 27.5 1037 797
37.6 3.59 32.2 74.5 0.08 29.2 976 780
38.1 3.27 32.9 76.3 0.1 30.8 1099 751
17.1 1.06 18.4 31.2 <0.015 20.6 286 258
26.2 2.12 20.2 68.8 <0.015 23 916 640
18 1.36 29.1 60.6 <0.015 26.8 444 417
23.7 0.95 20.9 67.6 <0.015 22.5 729 512
17.6 0.59 34.2 30.2 <0.015 34.2 194 265
1. Welcome and Apologies Apologies received from:- Emma Killip, Project Manager, DOI (EK) Stephanie Gray, Head of Waste Management, DOI (SG)
2. Preferred option to deal with silt already in Marina JR told that the preferred option now is to look at dredging the silt, store to dewater (approx. 12 months) and then move the dry material to the Foxdale Deads. Advantage with this solution is that it would allow the dredging to take place in the January to May 2019 window, and will give DEFA the time to undertake the necessary monitoring at the Deads. TB said that the 12 month drying time is a broad brush figure as do not have to get the material to a specific dryness before moving. JR said that in conversations with MUA and landowners the Department has intimated 12 months and the more the silt is dewatered the less risk there is of liquid being lost during transportation. Likely cost of this method is a quarter of the cost of chemical treatment, and is a simple, more cost effective method. Regarding potential sites, JR told of having spoken to [redacted], who has indicated that he is interested to talk about the field by the power station [redacted]. JR said of being able to pump into the field, form a bund and then use the slope of the field to allow the material to drain, with water either going to the MUA stream or the river itself or back to the marina. JR stated that some of the drying process is through evaporation and therefore the material would not be covered. TB said following the recent meeting that [redacted] had the understanding of the wider good for the Peel community and was also interested if the field could end up as a place of employment for Peel, i.e. with improved road access. JR advised that the access to the site is currently via Mill Road. Extension of the existing access road onto A27 Glenfaba Road, owned by the
AR advised of having some material stored at Turkeylands, and if moved could release funds for leasing/storage of field. TB said of not wishing to move it to the field, but moving it to the Deads could be an option. JR said that this could be identified as a saving in the application for contingency funding.
3. Progress update on other options (a) Wrights Pit North – SG sent in comments to advise that the methodology for sampling has been agreed and await confirmation from contractor re dates for sampling to advise HRS. Project spec for additional Point of Ayre, CHs drafted. Site to be surveyed. (b) Energy from Waste Plant – SG sent in comments to advise within the time constraints this will be progressed once WPN is underway. (c) Material treatment and recycling – JR said that this is still available as an option. Draft PIN response done, however need some information from DEFA.
4. Long Term Options (a) & (b) Geotextile coastal protection and Peel Brickworks Quarry and Silt Traps – AR advised that the JBA report should be available before the next meeting. (c) Glenfaba field – JR informed of being part of the discussions with MUA as to whether some material could be used to fill hole at Glenfaba site. TB said that this adds complexity.
5. Funding & Project Management TB said of currently not having a defined project or money. JR said of the need to write a paper to Treasury (Contingency Fund) and of the need to establish costs ahead of being set up and need to understand what funding DEFA is looking for. BW said that after the two meetings mentioned earlier we will be in a better position to identify the project and funding requirements. JR said of the need to look at who is going to manage the project, ie internal or external/tech specialist. TB advised of requiring conversation with CEO and was concerned about any delay resulting in loss of focus and momentum. JR said that if internal will need technical input. JR informed that he would like to award contract and start on site in January 2019. Regarding land issues, JR said that we may need to find a small space for a compound for the dredging contractor – MK/AR said of previously having a site hut in the boat park. AR advised of having 800m worth of piping – TB queried the contractor bringing their own. BW stated that if help/advice if needed the H&S team would be forthcoming.
6. Overall programme update Programme to be updated. TB noted of requiring conversations with the Quarry owners and [redacted], planning pre-application discussions and meeting with DEFA. Referring to the procurement side, TC said of window being at the start of the year, and queried if we need to have the contractor in place early. JR said that we could put information out to those who expressed interest in the PIN. MK said of the need to wait until we have a firmer understanding of the land commitment – JR said that this would be in the next 2-3 weeks. TB asked for information to be started to be put together. It was noted that the project is now main steam dredging works. TB asked if we are going to be writing back to those who responded with an update. TB queried expression of interest phase as may get people that did not respond to the PIN. JR to talk to procurement. TB stressed that early contractor engagement is key and the more we can do in advance the better. TB said of the need for early engagement with procurement and sending an update letter to PIN responders. JR JR
7. Any Other Business JR told of an individual with an interest in the subject wanting to talk through the history of Peel marina and that a useful view was that the water in the Neb comes from Glen Helen and Foxdale. BW said that the water quality of the lagoons at Rockmount showed some significant metal figures which comes from Glen Helen. One option would be to divert the river when it gets to the marina. He also mentioned university/academic research and that we should approach a university to look at. JR queried if we should be looking for someone to focus on the long term solutions. TB said of the need to concentrate on 2019/20. TB noted that canalisation has not gone off the agenda.
8. Date of next meeting 14th June 2018 at 1500 hours in West 1
1. Welcome and Apologies Apologies received from:- Jeremy Reece, Policy & Strategy, DOI (JR) Bernard Warden, Director of Environment, Safety & Health, DEFA (BW) Emma Killip, Project Manager, DOI (EK) Stephanie Gray, Head of Waste Management, DOI (SG)
2. Preferred option to deal with silt already in Marina JR update via email :- DEFA  I met with DEFA colleagues to discuss the environmental approvals process for a dewatering site at both fields. DEFA have started water sampling for both sites and together with the information from the Rockmount lagoons, do not foresee major problems. They anticipate that once a site is confirmed, a waste disposal licence can be applied for the field and discharge licence can be applied for discharging the water back to the river or marina. Tests will help DEFA determine if waste water will need to be piped back to the marina or via river / Power Station Race. DEFA are working with MUA to determine if Power Station race could be used. A 6 week public consultation will be required, so overall process approx 3 months  Remediation works on Deads likely to require 12 month EIA study.  Placement of remediation material on Deads will need to be timed to avoid bird season (Sept – Feb).  Details of design for Deads will be required, settlement / silt traps required. JBA are working on similar projects in UK, so may be a suitable consultant? Planning permission may be required?  Contingency Fund application to include:- o EIA study o Mine working / geo-physical survey o Appointment of a bio-diversity / environmental officer  BW was at the meeting, so can provide further clarity, if required
Locations  Meeting with [redacted] planned for tomorrow – initial feedback from JBA conversations ref sand quarry, indicate [redacted] are positive about helping with the overall problem  Meeting with planners at 1pm today – I will ring AR with feedback  I have not gone back to [redacted] until after speaking with planners Programme  Target dredging Jan – May 19  Dewatering  Placement of remediation material on Deads – Sept 19 – Feb 2020 Contracting Strategy  Early Contractor Involvement still required  I have not gone back to PIN contractors, will do after planning and [redacted] discussions TC told of new sewerage treatment works to take place in Peel in the Winter with new pipes to go up through the quayside. MK advised East side-TC confirmed along old heritage trail. AR asked about bridge works – TC informed of works to take place August-December 2018.
3. Progress update on other options SG update via email :- WPN planning application for the deposit of marina silts: following analysis commissioned by MUA, DEFA and DOI are considering whether this data can be used to inform the Hydrological Risk Assessment which could circumvent the need for additional Marina sampling and analysis. If agreed then this will save time and resources. WPN void space is being surveyed 04/05/18 and this will advise the planning application in terms of how much dredged or stored silt could be accommodated pre 31/12/19. A decision will need formally to be taken on whether Rockmount is to remain in situ. The draft Specification for the ITT for development of further bore holes around the site is currently being reviewed.
4. Long Term Options AR advised that the JBA report is due back tomorrow. Not yet received costs with regard to engineering view. Noted canalisation project is still in the background.
5. Funding & Project Management Noted Lagoon option information document was circulated with the agenda for meeting. JR update via email :- Project Management & Funding  Paul Slinger has confirmed that Project Management Unit are no
longer able to offer Emma Killip’s services as a PM, due to the volume of funded capital projects they are currently delivering.  PMU will support us in drafting tender docs for external PM / advertising on Portal  JR taking on PM role is not an option  Therefore, we will need to secure services of an external PM / technical advisor, once funding secured  I am happy to put draft funding document together and work with EK on PM remit docs
6. Overall programme update JR update via email :- Procurement  I have not yet made contact with Procurement to alert them to the forthcoming need to tender work.
7. Any Other Business 7.1 Clean up in Wales – BBC news article was mentioned. http://www.bbc.co.uk/news/uk-wales-43961898
8. Date of next meeting 15th June 2018 at 1500 hours in West 1
1. Welcome and Apologies Apologies received from:- Ann Reynolds, Director of Ports, DOI (AR) Tim Cowin, Head of Highways and Asset Management, DOI (TC) Emma Killip, Project Manager, DOI (EK) Stephanie Gray, Head of Waste Management, DOI (SG) JR welcomed those to the meeting and advised on this interim meeting to up-date where we are and on proposals going forward.
1. JR advised on meeting both the two landowners. [Redacted] happy to work with us regarding 1 field adjacent to the power station and his preferred land boundary of first field only. Noted MK/BW took a walk round the area and felt the field was in a good position. [Redacted] are also willing to work with the project and are encouraging. [Redacted] are unwilling to consider the field immediately west of the MUA Glenfaba House site, also JR commented that the proposed access route to this field through MUA site is not practical and MK also highlighted additional costs with pumping to this field. [Redacted] are willing to work with us on the field to the north of Glenfaba House, alongside the river Neb. JR noted that there may be some issues having to terrace off the lagoon and involve more civil works. JR advised on the proposed timetable, with both options having contingencies for 12 months. 2. Noted MUA have changed their mind about access through the lower field, as they want a larger laydown / storage area and are willing to move some of their permanent works away to allow the access route – costs at £10K design changes, and approx. £50K to introduce longer road. JR explained to MUA that DOI/DEFA have no funds at the moment.
1. Welcome and Apologies Apologies received from:- Mark Kenyon, Ports Manager, DOI (MK) Tim Cowin, Head of Highways and Asset Management, DOI (TC) Emma Killip, Project Manager, DOI (EK) Stephanie Gray, Head of Waste Management, DOI (SG)
2. Phase 1 – Dredging, dewatering and ground remediation at former Cross Vein Mine (a) Structure of Phases – 1A and 1B JR told of progressing well. It was noted that Phase 1A (DOI led) is the dredging and dewatering of the project, and Phase 1B (DEFA led) relates to moving material to the Deads. Phase 2 is the longer term options (DOI to develop to start with). BW said that Steve Stanley is confused regarding the term of ‘leadership’. BW informed that in terms of work necessary to fulfil the options DEFA is moving forward, however DEFA were under the impression that they would be DOI projects. JR stated that this was not his interpretation as would be better to be a DEFA project. Matter to be discussed outside of the Project Board meeting. TB stated that DOI could not do the remediation works without DEFA’s expertise. JR said that the Deads are DEFA land and was looking at which Department had better expertise to lead the phase/project. Detail to be discussed further at meeting tomorrow. TB stressed of not wanting to duplicate anything. JR told of two different Project Managers for Phases 1A and 1B. BW stressed that 1A and 1B cannot be separated too far as they are linked. TB advised of being one end to end project and wants it driven all the way through. (b) Phase 1A a. Land issues – JR advised of having engaged the services of Brett Woods and have met with both land owners, who are happy to receive an offer from the Department for a fixed price. JR said that both land owners understand both parties are there. [Redacted] has agreed to start the consultation with the Commissioners. Heads of Terms of lease to be included with option to JR/BW
(c) Phase 1B a. DEFA project plan – it was discussed whether phase should be DOI or DEFA led. b. Inclusion of Rockmount and Turkeylands materials – noted not to include Turkeylands material. Cellular geogrid was discussed. JR said that cost elements are vague. TB stated that discussion is required regarding contingency/funding, with the need for a conversation with the Minister and CEO. NG advised that mining assessments are being done. (d) Wrights Pit North Being developed on contingency option. NG told of still doing work in case it has to be used. SG gave the following feedback for the meeting – The draft scope and content of the environmental study has been forward to DEFA Planning Application and Building Control for review. A sampling methodology to advise the Hydrogeological Risk Assessment is being finalised with DEFA Environmental Protection. The specification for additional in-waste boreholes has been provided to DOI for inclusion within the ITT for development of boreholes. Analysis is being undertaken of an additional, non dredged, waste material that may need to be accommodated within WPN. The annual Ayres restoration flora and fauna survey has been commissioned. A bird survey has been completed to advise the WPN site restoration scheme. NG advised of having also done testing at Corletts.
3. Phase 2 a. Silt traps – AR advised that a draft report has been received regarding silt traps which outlined that they do not recommend. AR to get report finalised and will distribute. Noted more than one party is against debris trap. BW queried silt trap and former quarry – JR said that one option was to direct the river and dredge, pump and fill up over the years (as a store). BW told of potential for retention at source rather than collection. TB said of long term option being to repeat the process on an ongoing basis – JR said that this has not been included as is being driven as a temporary solution. b. Energy from Waste Plant – no progress to report. SG advised that this would be a significant piece of work if it is to be undertaken with sufficient scientific rigour to make it valid. It would involve utilising JCKs facility at Balthane to process a representative tonnage of excavated marina silts to extract the aggregate, capturing the residue, drying it and then passing it via the EfWP. All of the above will require environmental containment and management of leachate. AR
4. Overall programme update TB said of the need to drive Phases 1A and 1B. JR told of continually fighting to keep this moving. TB queried remits for Phase 1A and asked if it would be better to go out for 1A and 1B together. JR told of the need to fully understand 1B. BW said of needing to commence on planning front, ie environmental impact assessments. SG outlined in email sent prior to meeting that one of the main problems to face is that we do not have an idea of what the annual maintenance dredge will comprise of – fine silts/larger aggregate and in what %’s. This is critical for the EfWP and also JCK process. Whilst the marina is backlogged we won’t get the information we need to run theoretical modelling via EfWP or an actual trial.
5. Notes from previous meetings TB queried MUA – JR advised that comms plan needs to link.
6. Date of next meeting 12th July 2018 at 1500 hours in West 1, Sea Terminal
TB advised that the Minister had requested the setting up of a Peel Marina Project Board to get the right degree of focus on current issues. A lot of work is going on around Peel Marina and everyone has to be conscious as to where it crosses over Departments/divisions. We need a clear focus on trying to get solutions implemented to allow normal operation of Peel Marina in 2018 and beyond.
1. Scope and Objectives TB said of the need to resolve the silt problems in the Peel Inner Harbour. IH asked TB if he sees it as establishing a long term solution or for the next 2 years – TB answered for both. MK stated that what is agreed for Peel will also have an influence on what the DOI does in Douglas. TB noted that Douglas was not as immediate as Peel. BW advised the heavy metals made the distinction between the silt issues for Peel and Douglas. TB said of the need to be more focused on the specific issue and could consider Douglas as a second phase. IH said that the immediate issue is that Peel Inner Harbour is becoming unusable. TB advised to focus on Peel Inner Harbour, with Douglas to be addressed further down the line. Discussion ensued regarding the storage at Rockmount. AR stated that it could be a two year project to build something to store the Rockmount silts, which under covenant must be removed by May 2020. IH stated that essentially one solution could be if we can get planning/licensing issues dealt with at Wrights Pit North in that it could take all material from current storage sites, for little expense. TB noted a current workstream ongoing within the Waste Management Unit of DOI that will involve the silts being stored at Rockmount. BW said that the work being discussed is to be supported, with the need to
try to establish alternative uses for the material stored at Rockmount, which could be done in parallel. SG advised that you cannot make engineering material out of the silt. TC asked what the classification of waste is – SG answered as to not being sure yet. BW informed that the material has never been classified as hazardous or toxic. SG advised on a medium term option being R & D needs to get started now. IH said of a danger of losing sight of the bigger picture, ie while considering what to do with Peel short term, but beyond that we need a sustainable ongoing solution, with the need to understand what we are dealing with so we can plan capacity requirements going forward. It was noted that Laxey and Ramsey dredging, which are much less amounts, are currently being dealt with and managed. TB advised that Rockmount is out of the scope of this project board, with Waste Management Unit to update group on progress. Douglas currently also out of scope, and the group will consider Douglas once there is sufficient progress on Peel Inner Harbour. Peel Outer Harbour also out of scope.
2. Solutions and what we need to achieve and by when It was agreed that the DOI needs a 2018 and 2019 solution and medium term solutions.
3. Workstreams TB said that there seems to be several pieces of work going on and he wishes to use this project board to capture all the work and to get some results. TB said that in 2018 we need to have some method of disposing of what is extracted. AR queried destinations (ie burning/storage area). TB noted that it was clear that it cannot be put out to sea. BW questioned the suggested practicalities, namely Wrights Pit North or the Energy From Waste Plant (incinerator), as these options have been discounted in the past. SG advised of developments at Wrights Pit North, namely due to a recent survey highlighting that by putting in materials it will have negligible impact on the areas environment and that there is surplus capacity available ahead of the site’s planned closure. TB said we need to focus on what we can do now and if different from the past then to be understand why things have changed. Workstream 1 EFWP/Wrights Pit North – Waste Div (DOI) are working on potential use of the Energy From Waste Plant (EFWP) to burn silts and Wrights Pit North for the storage of silt, dewatered or not. Wrights Pit North will have DEFA/Planning issues to overcome/apply for. Workstream 2 Dewatering – Discussion was held on the various ways of getting the material out of the harbour. MK said that the closer you keep the material to source you can put it back into the harbour. AR said that there were various methods to dewater silts but also the method of removing the SG/IH
silt played a part. TB queried how the Department want to get the material out of the harbour – BW advised that this work has already commenced and of the need to know more about the materials. TB requested that prior to the next meeting MK/TC work out a practical initial proposal for extracting the material from the harbour and dewatering it as close to the point of extraction as possible, including estimating approximate volumes. Discussion ensued regarding dewatering and grading, and BW said of the need to make a distinction between the two. Workstream 3 Understanding the material - It was noted that IH/SG/BW are looking at trying to review terms of reference in minimising contaminants at source. This is a wider project Workstream 4 Potential canalization of Peel Marina - TB asked for a high level assessment (1 page overview) of MK’s idea of separating the main river channel from the pontoon area in Peel Marina, to see if we can get a canalization route in place. It was noted that this solution would require an Environmental Assessment and also hydraulic modelling. MK/TC IH/SG/BW TC/EO’S
4. AOB A) Consultants – BW said that DEFA/Waste Div will get together to discuss the works each have with their respective consultants, to ensure no overlap. B) Contingency for 2018 – AR said that Colas had offered a temporary storage facility at Turkeylands for 2017 however there was insufficient time to make the relevant licence change application in time to make the dredging window. The DOI Minister has asked AR to speak with Colas to see if they will consider making the application now so that if necessary, as a contingency, the storage could be used for 2018 dredging works at Peel. TB agreed AR to progress this suggestion as a contingency. BW advised that environmentally he supports the Colas storage. C) MK stressed of the need to have a solution in place to allow dredging to commence on 1 January 2018. BW/SG AR
4. Next meeting TB stressed the need to keep the momentum of the meetings going. Next meeting to take place before the end of May on a Thursday. Thereafter will need to be at least monthly. Date of next meeting: 25th May 2017 at 1500 hours in West 1, Sea Terminal Building, Douglas
1 Canalisation of Marina Advantages Disadvantages
Replace existing central pontoon with a solid wall/walkway constructedwithsheetpilingtoallowfreeflowofriver.Restrict waterfeedtoMarinabyincorporatingintermittentspillways.This optionreturnstherivertoitsnaturaltidalstatusandallowsiltto flow to the outer harbour area and beyond. > Returns tidal flow to river reducing build up of silts in the marina. > Provides a long term engineered solution for the natural management of silt. > Reduces the burden of seasonal dredging, storage and disposal of silt. > No restrictions to berths Improves safe depths for manoeuvring vessels. > High cost - estimated at £4.4 million, may be difficulties in obtaining funding. > Will require a number of assessments/modelling studies to be undertaken incl. EIA etc. > May be difficulties and associated costs in obtaining planning permission. > Economic impact; no visiting yachts whilst works are carried out, loss of income. > Sediment may instead gather in the outer harbour resulting in a requirement for dredging in this area > Still requires removal of existing silt deposits (19,000 tonnes).
2 Seasonally Impound the Marina Advantages Disadvantages
Leave flap gate open during winter months when river flow is greatest to reduce silting up of Marina. > Returns tidal flow to river for part of the year thereby reducing the build up of silts in the Marina. > Relatively low cost option. > Can be implemented with relative ease. > Winter storms will likely move the sediments out of the outer harbour area (further out to sea). > Sediment modelling required. > Still requires removal of existing silt deposits (19,000 tonnes) > Boats will need to removed or cradled out of the Marina. > May be disruptive and unpopular. > Pontoons will require additional maintenance/management. > Risk that silts may not be carried further out to sea but will deposit in the outer harbour which will then require additional dredging/management. > needs additional area to store boats.
3 Decommission Peel Marina Advantages Disadvantages
Decommission the Marina, remove pontoons and open flap gate. Install tidal berths only. Potential to relocate Marina to Port St. Mary bay. > Short term and long term savings; no requirement to manage, dispose of silt. > Tidal flow is returned and silts are naturally washed out to sea. > Reduces/removes risks associated with future changes to environmental legislation. > Economic impact on Peel and Island as whole. > Costs associated with removing the Marina. > Existing silt deposits still need to be removed and stored/disposed of. > Issue of contaminated silts still exists. > Opposition from Stakeholders. > Environmental impact of removing marina.
4 Install silt trap in the River Advantages Disadvantages
Install and engineered silt trap in the river. > Cost effective and simple engineered solution > No visible or physical impact on the Marina area. > No detrimental economical impacts to area. > Can be implemented relatively quickly. > Will require environmental assessment and modelling. > Specialist design input. > Reduces dredging in the Marina area and associated disruption. > Silt traps will require management. > Traps will need to be accessible in order to remove trapped silts. > Transport, storage/disposal of silts remains an issue. > Existing silt deposits still need to be removed from Marina (19,000 tonnes).
5 Extend dredging window Advantages Disadvantages
Agreement to allow the Department to carry out dredging over a longer period in any one year. > Allows better planning and management of silt dredging, storage/disposal. > Reduces substantial build ups of silt in the Marina > Improves accessibility of the Marina for visiting vessels, increasing visitor numbers and the associated economic benefits. > Environmental impact of dredging during certain seasons. > Existing silt deposits still need to be removed from Marina (19,000 tonnes). > Final solution for storage/disposal of silts still required.
6 Develop Treatment Facility Advantages Disadvantages
Develop bespoke facility to treat contaminated silts e.g. Abilene Snowe. > Provides a long term solution for the management and treatment of silt deposits in Marinas around the > Waste product can be utilised by other industries. > A trial installation could be set up initially at a lesser cost. > Plant will treat existing silt stored at sites on island and free those sites up. > May be able to reduce costs by specifying only partial remediation; removal of only the most hazardous contaminants allowing the end product to be dumped at sea. > High setup and operational costs. > First of its kind - untested > Will require Planning permission - time factor. > Requires a site > Further information on the scientific specifics and certification is required. > Political/local objection.
7 Dump at Sea Advantages Disadvantages
Dredge silts from Marina and dump at Sea. > Removes issue of storage/disposal. > Silts are dumped at sea where they would naturally end up if tidal flow was reinstated. > Silt disposal can be more effectively planned and managed. > Legal/regulatory issues of compliance. > Fines > Environmental impact of concentrated contaminants being dumped. > Economic impact on the islands fishery industry > Local/political objection. > Morality/ethical issues.
8 Land Fill Advantages Disadvantages
> Realitivly Inexpensive > Material can go straight there with minimum treatment > No suitable long term land fill currently Available > Land fill has a large full life cost
1. Welcome and Apologies TB welcomed those to the meeting and noted apologies and that Steve Butler was representing Jennifer Chance.
2. Notes of previous meeting held 4 May 2017 were accepted.
3. Matters arising picked up under agenda items.
4. Workstream updates (1) Potential Disposal route – EFWP/Wright’s Pit North SG talked about undertaking trials of organic matter. SG explained on meeting Consultant from Peter Brett Associates with BW and although we have a lot of data she spoke of gaps that do need analysing to establish, for example, chromium levels and apply to UK standards to identify whether the waste is hazardous or not. It was noted that Wright’s North Pit is not licensed to take hazardous waste. SG recommended more scientific data is needed, which will prove beneficial in the longer-term. SG advised data sampling and analysis will take 4 weeks with a further additional period to check for of chromium whether type ‘3’ or ‘6’. BW suggested that silt/aggregate may be worthy of further treatment to bring the readings below OSPAR levels and therefore could be brought into a condition where it potentially could be disposed of out to sea, however he agreed that we need to know more about the materials. SG advised that in order to consider the short term option of disposing of the sits at Wrights Pit North landfill site the material needed to be classified in accordance with the EWC codes. These codes are used to identify the types of waste that can be managed through an individual waste facility. In SG/BW
presentation and said that it was felt that at £95 per tonne was quite expensive. MK added that they are quite keen to trial, but it would be a big commitment to bring them on board. TB queried if it would be the solution in the short-term. SG suggested it might be better if they were to come back to us, after they had undertaken trials and got the science proven. TB asked to respond in terms that the interest was good, however with budget restrictions may not be able to consider within the current proposals. (3) Long Term solution TC circulated a paper summarising various options for Peel marina dredging (to be attached to these notes). Discussion took place on all 7 proposals. TB advised it was a good start and it was agreed that these will be up-dated and circulated to the next meeting. TC suggested using colour indicators. JBA Report – BW advised that in terms of assessment on what was out there, BW submitted and circulated the Report and said it may prove worthwhile to review the report. BW to send the Report to TC. MUA Sewerage Plant, Peel – SB queried impact and if they could assist. TC advised on works to do the re-generation of the quayside and that it would be highly unlikely that they would want to treat anything other than sewerage. It was noted in discussion that both the EFWP and treatment options such as those offered by Abilene Snow were likely to be long-term, rather than short- term options. TB Co py of Copy of Peel Ma rina Options end of ju TC BW
4. Contingency planning application TB advised that he met with the DOI, CEO and Minister to discuss Turkeylands/Colas. TB talked about their lease coming to an end and it being negotiated with Colas taking on other options for a long-term solution. It was noted that Turkeylands currently has silt temporarily stored for DOI. Subject to agreement, BW said he would sign-off the wavier that identified the circumstances etc for the silt to be stored at Turkeylands. TB queried whether we think we should submit a Planning Application in respect of WPN or confident to wait to the end of August for the results. AR stressed the need to dredge both Peel and Douglas. TB suggested having an early meeting in August and September and by September we should know if we need to put in a Planning Application. SG informed that we would need to liaise with Bride Commissioners if we progressed with WPN. TB advised that in principle what we are going to do has not been defined or what the preferred solutions are.
5. Any Other Business (a) Companies/Consultants – SG suggested that we should be open and welcome any other approaches who may have solutions to our silt problems.
1. Welcome and Apologies Apologies received from:- Ann Reynolds, Director of Ports, DOI (AR) BW confirmed with TB that it was acceptable for KK, SR & NG to attend the meeting to answer any questions directly.
2. Notes of previous meeting held 3 August 2017 were accepted.
3. Progress discussion/update SG referred to the Brett Associates Report, a copy of which was handed to TB. SG said of the need for DEFA to talk to Peter Brett Associates and said that the issue we have is that the classification is dependent on the amount of material that is analysed. SG recommended that, whilst this analysis is not conclusive we (prudently) assume the material as ‘hazardous’ and speak to DEFA about what is required, and also do additional analysis. KK said that it is wise for the lab to consult with Planning regarding minimum assessment requirements. KK stated that previously an assessment was made to see if material was fit for deposit at sea (sieve 2mm); landfill needs to look different criteria and leaching rates on a net weight basis so therefore need to know moisture content. SR said that of primary importance is that we know it has hazardous content (primarily lead) so need to know what will leach and the risk to the environment – looking for Hydrological Risk Assessment. SG spoke about EWC Codes. NG spoke of stable, non-reactive hazardous waste with the need to know if it will leach – KK said that leachate will have contaminants. SR said that a planning application will be required. If dry enough thinks it will be acceptable to dispose of in WPN. SR queried IOM Waste Regulations,
further work to consider this. TB said of the need to look at further tests and get Abilene Snowe to talk to SG/KK etc. TB summarised that we now had the following workstreams; (1) Treatment trial (Abilene Snowe) (2) Wrights Pit North planning application (3) Removal of river deposits (4) Geotextile bag storage. Noted estimate of 20,000 cubic meters to be removed. SG said of the need for indication of amounts for business case. KK said of the need to make an accurate assessment with a bathymetric survey– and work out a deposition rate from that. MK indicated that he was satisfied with the current method used to calculate the current figures and future deposition rates were heavily weather dependant. SR said EPU to put in writing what we need to move forward with planning application. SG to speak to Planning. Need to know indication for number of vehicle movements. TB said to (prudently) do calculations on filling WPN with as much as you can, based on what space is left over and above what is needed for other materials. TB advised that a business case needs to be done for the whole solution, not just WPN. It is vital that we look at this as a holistic process not individual items. TB also reminded the group about the forthcoming Department P&S meeting on this subject and invited BW to attend if available. KK asked if there were any thoughts on a future facility. BW advised that this would form part of the second part of the project. TC presented chart outlining relative costs and advised that previously it cost £285k to remove 10k tonnes. The following figures were outlined: Dumping at sea £7 a tonne Landfill £22 a tonne EFWP £86 a tonne Abilene £95 a tonne
4. Summary of potential way forward Based on the above discussions, there is a potential way forward, which can be implemented in 2018. Approx 20,000 tonnes of silt needs addressing. Extraction to commence in early 2018 and to be done in a controlled manner over a 2-3 year period (which suits harbour operations), using an extended 9 month per annum window (DEFA Fisheries likely to consent, subject to appropriate ‘silt screen’ methodology). Proposed solution has several elements:
1. “River channel area” (c.3,500 tonnes) can be extracted immediately as it is not hazardous and could be washed and recycled (subject to assistance from JCK/Colas). This would also partly mitigate the further build-up of silt in subsequent years and would show early progress 2. Abilene Snowe trial (initial trial c.4,000 tonnes) – needs further scientific/data analysis before commencement, however agreed that this approach has merit. 40k investment to conduct trial is money well spent. If successful it opens up some very interesting long-term potential solutions, which could also deal with more of the accumulated volume of silt. Trial must be progressed to either confirm or eliminate this methodology. Trial to be conducted using “fresh” silt extracted from Peel and process to take place on Fenella Beach car park. Target start date of January 2018. 3. Wrights Pit North – dewatered silt can be disposed of to landfill at WPN up until end 2019 and possibly 2020, subject to planning consent being obtained (assumption is that consent can be achieved but planning application MUST show that all non-landfill options have been explored and fully considered). Currently the site is below capacity and, in the absence of the silt being disposed there, would require additional material to bring it up to the required restoration levels. Vital for DEFA that material is appropriately dewatered – but more gradual approach now proposed facilitates this. 4. Geotextile bags – can potentially be filled with extracted silt and utilised for coastal protection around Kirk Michael area. Will require protection with concrete to extend their useful life. Would fill the bags at KM. Avoids disposing of the silt in other manners and has a double-benefit in avoiding expenditure which would otherwise be incurred in due course on coastal protection. Needs fully exploring. Whilst further work is required on each of the above work-streams, discussion provides confidence that, in combination, we have a potentially viable solution that will deal with the legacy silt accumulation from 2018 in a controlled and manageable way and could provide an ongoing long-term solution, along with the other options previously identified. Initial focus is on the immediate 2018 priorities and we can then re-assess the longer-term solution in the light of the learnings from 2018. Note: As part of this longer term planning we need also to assess whether there is any potential in the Foxdale ‘deads’ aspect mentioned in 3 above.
Next meeting to take place on Thursday 12 October 2017 at 1500 hours. Thereafter meetings also calendared for 2 November and 7 December.
1. Welcome and Apologies Apologies received from:- Bernard Warden, Director of Environment, Safety & Health, DEFA (BW) Emma Killip, Project Manager, DOI (EK) Stephanie Gray, Head of Waste Management, DOI (SG) Distribution attendees and apologies Malcolm Cowin, MUA
2. Funding JR told that funding is progressing well and have been asked to amend the bid to split the revenue contingency and capital funding. Revenue funding is everything in phase 1a with the exception of site access approval and early development from Cross Vein site and development of phase 2. Capital funding is for works for Cross Vein and Rockmount. JR said of the need to put in revenue bid to cover revenue contingency funding (3 years of funding out of revenue contingency fund). It was noted that Treasury may ask Department to put in revenue bid. However this allows us to put in place the contract. JR advised that Rachel has a copy of the funding request, which will then go to Treasury. In the meantime, capital bid for 20/21 has been finalised. Invited to SACIC next week to answer questions. Pink paper for the Department to be signed off. JR informed of progressing with appointment of Project Manager, Planning Supervisor and Quantity Surveyor – it was noted that there would be a break clause in contracts if the funding is not received. To be done under Department’s framework. TB said of the need for defined skills sets to get to different stages. TB informed that he feels that Treasury are being reasonably receptive.
3. Adoption of Project Strategy Pink paper to be signed by Minister.
trap) and identify the best option. MK said of the need for something to stop the heavier aggregates coming down the river. TC said that it makes sense to capture. TB said that there should be enough insight within the Department to come up with a solution. JR advised of having looked at different options individually, and that the issues in the marina link back to the catchment. TB said of needing to look holistically, however we still need to do something to prevent the debris. AR said that a practical piece of work could be done, involving MUA and DEFA as a separate piece of work. TB said that the language/terminology used is important, ie aggregate / debris trap, not a silt trap. (b) Energy from Waste Plan Progressing. (c) Canalisation AR queried funding. JR said to include as one of the longer term options. (d) Installation of river bank cut-off wall JR said that one of the potential sources of contaminants is from the historic fuel leak below the power station tanks.
5. Overall Programme Update Programme updated. JR said of being up against it and are behind where we should be. AR queried PIN – JR informed of having gone back and advised interested parties. TB queried slippage – JR said of having taken 2-3 weeks regarding Project Manager, plus documents and paperwork. JR said that if funding comes through as revenue contingency funding then we may be able to accelerate staging.
6. Notes from previous meeting held 14th June TB queried previous discussions regarding Departmental responsibilities – noted CEO is happy for DOI to take responsibility for Phase 1B.
7. Any Other Business TC told of a number of other projects in Peel, ie new bridge (Sept/Oct), sewerage treatment pipeline, resurfacing of the quay and new sewerage treatment works. JR queried the requirement for contractor to provide work boat? AR said that they would have to have additional insurance.
8. Date of next meeting 9th August 2018 at 1500 hours in West 1, Sea Terminal
1. Welcome and Apologies Apologies received from:- Stephanie Gray, Head of Waste Management, DOI (SG) Distribution attendees and apologies Malcolm Cowin, MUA
2. Funding TB advised that funding has been confirmed. It was noted that TB/NB/AR attended SACIC, and NB also went to Treasury. COMIN approval has also been received. JR informed that COMIN endorsed strategy and Treasury approved the monies. JR told of having been granted revenue contingency funding for the dredging and for the development phases for both Cross Vein Mine and Stage 2. A separate Capital Business Case has been submitted for the Cross Vein Mine works phase in 2019/20 and 2020/21. Noted monies for dredging is split across 3 financial years. Noted project won’t have capital money until April for the works phase at Cross Vein mine. BW asked if the need for ongoing funding at Cross Vein mine has been mentioned – JR said that it was mentioned that DEFA could put bid in. TB stressed the need to now ‘crack on’. Regarding the bike fraternity who currently use Cross Vein mine, JR said that the ACU has been advised – JR to find out what the CEO has in mind as alternative. JR
3. Updates Phase 1 – Peel Marina Dredging, Dewatering and Ground Remediation at former Cross Vein mine (a) Phase 1A JR advised that the next issue is planning approval for the lagoons, Peel. JR said that they have spoken to Peel, Patrick and German Commissioners, with positive responses received. Noted generally Peel thought both options are OK, Patrick could see the logic, and German were more concerned about traffic through St Johns and favoured the Ballaterson Farm Field. German were also concerned about traffic from Knockaloe Beg passing close to St John’s School – AR said that previously options have been put in place, i.e. could restrict number of movements per day or the timing of the movements. TB said that there may not be a choice as to which field is used and that the balance of view is that the Ballaterson
September. Most of the bird data is available and DEFA will need a years worth of data to account for visiting birds. Plan is for data to be ready by September 2019 and then analyse, with feedback October 2019. It was noted that November to February is best time to place material. BW said that in the meeting he will push for the information to be front loaded and consider the ways immerging information can be presented at planning, to allow work to start in winter 19/20, subject to a final confirmation from planning. It was noted that it is likely Cross Vein Mine is home to a rare lichen. TB informed that when talking to planning regarding Phase 1A it might be worth talking also about Phase 1B (ie approval in principle). AR asked who was doing the negotiation with the field owners. Noted Brett Woods. TB queried whether Brett should attend the next meeting – JR to invite. JR advised that he met with Stephen Parry regarding Communications Plan, who has asked for additional information regarding environmental benefit of Cross Vein mine, and told BW that he would like this information as soon possible (ie 2 weeks). TB advised to wait a bit longer before putting out information to the general public as the land owners were not yet on board. BW left the meeting. Meeting spoke about German Commissioners and the issue of material at Rockmount, and noted that the Commissioners are looking for a roundabout at St Johns instead of moving material. Meeting also discussed the agreement that is in place. AR said that she is happy to progress, with TC. JR told of possible issues for material remaining at Rockmount permanently, i.e. covenant, planning permission and possibly waste disposal issues with DEFA. (c) Wrights Pit North Ongoing. (d) Phase 2 JR said at this stage we have funding to do development and of focusing at the moment on Phase 1A and 1B. BW JR BW AR/TC
4. Notes of previous meeting (a) Adoption of Project Strategy - noted pink paper has been signed. (b) Overall Programme - being kept under review.
5. Any Other Business TB highlighted issue of sand washing at Corlett’s. MK informed that they do have a series of lagoons and of the need to look at all sources once sampling is done.
6. Next Meeting 13 September 2018 3pm West 1
1. Welcome and Apologies Apologies received from:- Ann Reynolds, Director of Ports, DOI (AR) Mark Kenyon, Ports Manager, DOI (MK) Bernard Warden, Director of Environment, Safety & Health, DEFA (BW) Emma Killip, Project Manager, DOI (EK) Stephanie Gray, Head of Waste Management, DOI (SG) Distribution attendees and apologies Malcolm Cowin, MUA Hydrographic Specialist, Anthony Bates Partnership Dredging Consultant, Anthony Bates Partnership
2. Phase 1A update Appointment of Project Team – JR advised of now having appointed a Project Team, consisting of Anthony Bates Partnership as Lead Engineer, headed by ABP Hydrological Specialist, assisted by colleagues, Primary Consulting as Planning Supervisors and Silva Consultants as QS (noted all technically in contract award appeal week). TB asked about interest received – JR told of 2 applications for Lead Consultant and 2 for Quantity Surveyor and 4 for Planning Supervisor. JR informed of now being able to formulate phase 1A design team to deliver phase 1A as an operational project. Project Board then to take step back from Phase 1A and focus on strategic delivery of the multi-phased project, with regular reporting from each Phase. TB stressed that it is very important that we do not lose focus on delivering Phase 1A and have to maintain Project Board structure. JR said that the Project Board is good as a steering body, and hold each delivery team to account. TB queried how the Project Delivery Team will ‘hang’ together – JR suggested that Terms of Reference be reviewed for each and that essentially the Lead Engineer will act as coordinator and will be invited to attend join the Project Board and they will have to submit monthly progress reports to the Project Board. Planning Issues – JR informed of having met with DEFA, primarily looking at phase 1B and one thing that came out was the need for DEFA to have a ‘ Chinese wall’ to avoid any conflict of interest between project and approvals team. At the meeting, it was noted that a final approved location for the silt is required for the temporary planning approval, otherwise it could be a stumbling block. JR said that he has looked for JR
alternatives and there is no alternative facility to take the silt and Turkeylands does not have planning permission for hazardous waste and the EFWP would not be able to take the volume. TB queried legal requirements for disposal – JR told that there is an issue over the licence of EFWP. JR advised that during the PIN other processes were identified, i.e. chemical process to turn into inert waste, which could then go to Turkeylands. JR told of having had good discussions regarding environmental impact. Consultants starting to discuss with planning regarding EIA. TB queried timetable for professional team and asked when it is anticipated to submit the planning application. JR informed that some surveys are to be done prior to submitting the planning application and of looking to submit first week in January 2019. TB queried the 3 month delay. JR told that this was due to the level of detail required for planning. TB stressed that he was concerned of not meeting the dredging window deadline. JR stated that capital procedures need to be followed and have already commenced work on data collection. TC said of the need for a certain level of detail to gain optimum result. JR advised of not being able to award contract until planning permission is received and therefore would not be liable for any costs. BWo stated that you could extend the window of acceptance for tender and that the land is covered under a 3 year lease. TB said that COMIN calling in was discussed. JR advised that planning is for the dewatering site, not the dredging. JR to ask team to look at marina to identify the priority areas to dredge in first year – however it was noted that this would increase the cost of the project. TC queried, if planning permission was granted 1st April 2019, how long would it take to build the lagoons – it was noted that it would take 3 weeks. TB also told of a 21 day period that persons can appeal planning and JR confirmed that a 2 week standstill was required following contract award. JR said of the need to look at programme again to try to pull some time back and would work with Project Team to review this ASAP. BWo advised that the land owners are willing to enter into an agreement. BWo said that each field has a different value. JR asked how far away on documentation – BWo said of hoping for drafts early next week and of an email outlining heads of terms to be sent to the land owners. Routing in and out of each field was discussed, including ownership. JR told of having spoken to Castle View Nursing Home and EVF who highlighted their concerns. Environmental Issues – JR advised that Martin has drafted the scoping document and will talk to planning before submitting. Communications Plan – JR informed of having spoken to a few more neighbours, and that nothing has been made public. TB said of the need to be clear on timetable before progressing with rolling out the briefings. JR advised that COMIN have accepted the project strategy and agreed finance, this is not the same as granting a planning appeal. TB said that if Phase 1A is going to slip, do you then do a planning application for both 1A and 1B at the same time? It was noted of a 12 month EIA period for 1B having just commenced. R said that having good environment backing is essential and will improve the area, with the need to build up positives. It was noted that Snuff the Wind is under DEFA ownership. TB advised that even if delayed, Phase 1A is better to be ‘ploughed on with’, separately from Phase 1A. JR JR
3. Phase 1B JR advised of not yet having put project team tenders together. Comms part already started. BWo said that that two should be entwined as a plan perspective and noted
chemical alternatives. JR outlined the following from SG: first draft of hydrological risk assessment currently with DEFA /bore holes programme October / planning application progressed subject to work priorities / quarry does not have licence. TB said he is happy there is a process, which is lawful that we would not be left with material once dredged.
4. Feedback from MineXchange conference JR told of having attended a conference last week, run by Natural Resources Wales, about abandoned metal mines. There were a number of talks from speakers with lots of ideas how to deal with metal mines. Trialling in New Zealand using scallops to form a filter was discussed. JR said of having met a number of consultants/specialist who have been involved in similar projects. This will be useful for Phase 2.
5. Notes of previous meeting held 16th August It was noted that the CEO is talking to the ACU regarding alternative for biking fraternity, with possibility of taking over 1 of the 3 former quarry’s. JR said of the need to hold emphasis on press release. Front loading EIA done. JR to chase information to be sent to Stephen Parry with regard to environmental benefit of Cross Vein mine. Noted AR did meet with German Commissioners, with no resolution. More meetings required. JR AR
6. Next Meeting 11 October 2018 3pm West 1
1. Welcome and Apologies Apologies received from:- Ann Reynolds, Director of Ports, DOI (AR) Tim Cowin, Head of Highways and Asset Management, DOI Stephanie Gray, Head of Waste Management, DOI Distribution attendees and apologies Malcolm Cowin, MUA
2. Phase 1A update Programme and risk – HS advised that an updated programme has been provided and highlighted of working on a tight timeline with risks all the way along. General consensus is the need to keep ploughing ahead and stick to the programme as best can and deal with any slips as we go through it. HS told of preparing draft risk register and will distribute to team members for comment. BW asked if there are any real ‘track stopper’ risks. HS told of one potentially detrimental risk, namely if agreement to use land is not received and told of concerns that there may be significant contamination from tank farm in the soil, and also of the requirement for planning permission. TB queried soil – JR told of an historic leak from fuel farm with the question being if it has permeated back to the field – it was noted that hydrocarbons are present in the ground. TB asked about implications if present – HS said that the plan is to excavate material to form bunds and therefore it could contain oil which would be free to soak away into adjacent land. JR said of being addressed by doing bore hole investigations and trial pits. JR said of the need to discuss with [redacted] as is tight on capacity with just one field, with conversation to be held regarding part of next field which is on long term lease to a tenant. HS advised that if more land can be secured it would lessen the pressure to get all the material out in one go, or by making the bunds extremely high. TB queried if this was unmanageable or less manageable – HS said that it is still doable, but bunds could be up to 4m high – TB noted it makes it more difficult, not impossible. MK said that by knowing of the potential for contaminants of lower soils it may be limiting as to how much can be dug until the ground investigation is complete and the way you remediate is via air. HS said the seepage would be an issue. TB queried if bunds could be lined – HS told of not being what has been considered as need natural HS
TB asked about water discharging back into the marina rather than the Neb – JR advised that, following discussion with DEFA, they do not want it to go into the river, however still have concerns about it going back into the marina. JR informed of hydraulic modelling to be carried out by MUA of sewer and that there may be an option to limit discharge of lagoon. Due to licensing issues DEFA looking at discharging the water out to sea. MK told of not being impossible, pump at exit of lagoon down over fish pass. BW told of checks to be run on leachate which will inform decisions. HS queried the meaning of leachate – BW told of run off from dewatering process. HS queried trial – BW told of UK standard method. JR informed that Simon Renton (Environmental Protection Manager) to set up meeting early next week to discuss direct. BW asked HS that in similar circumstances has he been asked to apply for a licence to return leachate water back to marina – HS said no, as it is regarded as a circular process, viewed as most beneficial way of transporting water. BW asked if the fluid output is largely unaltered – HS said yes. BW asked if previous work done have contaminants been in same order of magnitude – HS said no – BW queried impact of fluid fraction – HS told of mainly PAHs which can migrate out of material with no specific information in mind regarding contaminants in transport water – no comparable to level of lead in material – HS to find out further information. Finances – JR said that at this stage there are no cost estimates to compare against budget. Communications Plan – JR told of now wanting to issue revised PIN to get contractor on board – draft ready. JR queried about putting out press release with it. TB advised to prepare simple factual communications piece. MK said that people are already asking questions. BW said that it would be helpful to outline that the material is to be used for remediation. JR said to outline that we are currently looking at 2 land options. TB said that more complete communications could go out once planning application is submitted. MK said that a well worded brief could stop planning objections. Outstanding information – HS spoke about land survey and of prices being due tomorrow for the topographical survey. JR told of working on ground investigation document and of also looking at doing trial pits - it was noted of a lot of information gathering over the next few weeks. TB asked if we need option agreement signed off before any surveys take place – JR said of the need to seek agreement from land owners to do surveys. HS said biometric survey option of using own small boat and asked can it be checked that it is fully functioning and moved to Peel – MK said that boat is on trailer, ready to go. HS left meeting Contingency – SG sent in the following comments from Waste Management: Planning application for WPN – DEFA have now confirmed it is happy with the hydrological risk assessment. Rockmount silts store – SG awaiting confirmation from the Department regarding the long term planning status of this site. In the interim SG is arranging for a small area of the site to be excavated to allow sampling to the base of the deposit to determine the chemistry and leachate/water content of the material. HS
3. Phase 1B
Project Team appointments – JR told of have started work on appointment of Project Team and has drafted remits for Lead Consultant, Quantity Surveyor and Planning Supervisor. Have separately appointment Wardell Armstrong to do mining assessment, looking at historic workings. EIA & Planning Application – BW told of scoping document draft almost complete and will send to JR early next week, and the relevant team members are committed to doing data searches. JR said that the more we can do will reduce the consultant price. BW said of developing before and after sampling plans. Programme – JR advised that the programme has been updated and that gathering some of the environmental data will take 12 months for the surveys – have not looked at how much of planning process can start before EIA completed. BW said that we could approach at how early can we submit planning application and how much of planning application can we get done upfront – all team are committed to get ready early. JR queried the environmental limitations around the construction window – BW to investigate and confirm initial thinking. JR told of traffic issue with risk if doing in shorter time as traffic impact may be too high – it was noted of requiring 4 months minimum to move all the material from Peel. BW told of issues on transportation around schools, immediate access road and site layout. Communications Plan – JR advised of not having been addressed with the need to look at possibly next month when putting out consultant remit. TB asked if we should talk about outline for Phase 1B when advising of Phase 1A. BW said of the need to consider motorcycle lobby and the works being part of bigger trial of upland management. TB queried motorcycle lobby – JR said that he has not had an update – it was noted that SG had spoken to JCK, who thought the local group was trying to get permission to rent Cross Vein – JR to discuss further with CEO. JR said that if capital bid for Phase 1B comes through we could be in a position to put in fencing from April 2019. BW said of being committed to monthly sampling of river water quality and sediments, which the bikes churn up – scope document put in for Phase 1B required for visual element. BW said as long as there was proper plant management for any equipment working on the site, due to the remote nature of the site, there should not be a need for heras fencing. TB queried planning application for fencing as it may be incongruous. MK said that it could be closed off ‘as part of scientific process’. JR
4. Phase 2 update JR said of not being too much to update, however useful to start discussions with Steve Stanley regarding catchment management plan. MK queried regarding goal, ie silt trap – BW told of being part of process, and the more frequent the dredging the lower the contaminants. BW said of bathing water quality, working on communications. JR said at the need to look at if we can reduce volume and level of contamination and looking at traps etc, with all options being looked at. BW said that majority of damage is during heavy rainfall. MK spoke about the need to reinstall a debris screen/trap. JR
5. Notes of previous meeting held 13 September Appointment of Project Team - Noted Primary Consulting dropped out and have now appointed Safety Management Services as Planning Supervisor. Depositing of material - TB queried having somewhere to put, even if not desirable – JR
told of being able to stabilise material and take to Turkeylands which would be viable and legal.
6. Any Other Business Project terminology – JR suggested words sent out. Regarding potential press release for Phase 1B works at Cross Vein Mine – BW suggested Stephen Parry to speak directly to BW for a few sentences on the environmental benefits. German Commissioners – regarding roundabout – ongoing – AR is the lead for this. JR BW AR
7. Next Meeting 8 November 2018 @ 3pm West 1
1. Welcome and Apologies Apologies received from:- Stephanie Gray, Head of Waste Management, DOI Distribution attendees and apologies Malcolm Cowin, MUA Brett Woods, DOI
2. Phase 1A Update DC advised that, from a design point of view, the status is:-  bathymetry survey complete  trial pits undertaken at Ballaterson Farm  topographic survey started today and due for completion tomorrow at Ballaterson today  Quotes received from suppliers for the bore hole campaign – awaiting DOI confirmation Therefore, the design team can now progress with planning application. TB noted agreed strategy to just concentrate on Ballaterson Farm, which is a pragmatic decision based on resources and that Knockaloe Beg Farm was looking like an outside option, at best. Negotiations with land owner at [redacted] are progressing. JR informed that [redacted] has had his Advocates review the proposal, with a few minor questions asked. It was noted that Brett Woods is meeting with [redacted] on Tuesday morning with the hope being to close the deal next week. It was noted that the proposed agreement includes an option on the site for 2 year, commencing from date of signature, and that the Heads of Terms covers rate for 3 year land lease once option is exercised. JR told of issue with MUA pushing for decision on the proposed [redacted] site access road across their site. JR advised that that MUA have developed their design for JR
JR told of concerns regarding resource to do leachate testing. BW told of hoping to do some 2 weeks ago. However, when the fishing trawler caught fire in the marina, sampling was postponed and now the employee is off for at least a month. It was noted of the need for boat/expertise. MK to provide boat and crew and joint DOI/DEFA team to undertake sampling using equipment loaned by ADBP, ASAP. HS stated that sampling will help determine how quickly the silt settles out of suspension. Regarding the traffic study for EIA, JR told of the need to provide swept path analysis for the HGV route. TC said agreed that Highway Services has necessary programmes and will arrange for Scott to assist. TB asked when the planning application is to be submitted. It was noted that the EIA will still take a further 2-3 weeks. HS informed of intention to submit by end of November. TB noted EIA has to go in with planning application. TB advised that there is no mandatory EIA process on Island. JR said that the planners would not comment on the proposed scope of the EIA. HS told of having better focus on what we are going to put in. BW / MK to co- ordinate for this week TC/JR ADBP
3. Phase 1B Update JR advised of having draft scope to appoint Consultants. BW said of being 4 weeks overdue on DEFA elements of the scope document – BW to provide ASAP. JR said that DEFA have commenced sampling to gather data for EIA, and the Consultant will then take this EIA data to use in EIA. The Planning Application will have to be made and Capital Procedures have been looked at. The aim is to start moving material in Autumn 2020. TB asked why the cut off Feb/March for Autumn – JR told of birds and nesting season, plus other environmental constraints. BW advised of Wildlife Act. JR told of 12 months EIA gathering. JR asked, when putting out comms for Phase 1A, should we be putting out Phase 1B. TB advised end of November for comms for whole project (Phases 1A, 1B and 2). TC queried Rockmount, and commitment as a store. AR informed of intention to meet with Commissioners to look at all options. It was noted that if Rockmount material was spread at Cross Vein it would increase layer from 900mm to 1.2m thick. TB said of the need to tell the whole story. JR said that the question will be asked as to what is being done with Rockmount material. AR told of being under covenant until 2020. HS asked if DEFA have been doing sampling at Rockmount – BW advised ‘no’. HS queried summary report, i.e. leachate re Rockmount material – BW to look into and send to JR. AR said that she believes SG has been testing. BW stated that the contaminants in the run off never exceeded the background levels in the stream. BW JR/SP AR/TC BW
4. Phase 2 Update JR has met with Steve Stanley at DEFA to understand more about their catchment management plan – the overall aim is to reduce silt in the rivers. JR outlined proposal for Phase 2 to undertake feasibility study, focussed on contamination reduction and both elements can be combined to look at level of reduction of silt and contamination in River Neb.
JR suggested that the OSPAR and other regulations should be reviewed as part of the feasibility study and advice provided regarding disposal at sea issues. BW confirmed that it would be good to include an update on OSPAR, as approx. 2 years since last major review by DEFA. BW said that work will slot in nicely with DEFA bathing water quality work (DEFA have some monitoring kit on order). TB queried scope of heavy metals or silt. JR said that DEFA are moving with silt side and need the 2 together. JR said that both questions need to be asked. TB asked if Steve’s work is going to deliver the answers – JR told of working to try to frame something together. HS stated as to not having heard much about flocculation process (salt and fresh water mixing in marina and causing silt to drop out) and identify if any contamination is coming into the marina from the Irish Sea? All agreed that both need to be part of the Phase 2 thought process. JR to include in remit
5. Next Meeting 13 December 2018
1. Welcome and Apologies Apologies received from:- Bernard Warden, Director of Environment, Safety & Health, DEFA (BW) Distribution attendees and apologies Malcolm Cowin, MUA Brett Woods, DOI Stephanie Gray, DOI
2. Phase 1A Update Planning Application Submission- TB advised that the planning application has been submitted and validated by DEFA. It was noted that there has been an exhibition in Peel since Monday with a couple of concerns raised with regard to moving of the material by HGV via Station Hill (however this will be covered by the next planning application) and where supply and drainage pipes will go along the riverside footpath. TB told of speaking to municipal colleagues who were extremely complimentary about the solution. It was noted that a letter has been received from the IOM Harbour Users Association – AR to draft response. TB stressed that the key message is that the Department is dealing with the problem. TB told of being pleased that the 30 November deadline was met for the submission of the planning application. JR advised that the 21 day response period closes mid- January and it is hoped that it will be discussed at the 4 February planning committee. TB informed of taking no part in DEFA decision and asked for someone from the Department to register as a speaker – AR/JR to register. TB said that the DEFA planning officers report is worth reading ahead of the planning committee meeting. Regarding planners concerns that the dredging requires planning permission, AR is to respond in writing. AR said that the Department does have a statutory legal duty to keep the marina safe and working. Design & ECI tender progress – noted planning application submitted, with a couple of requests/clarifications. Tender package (design, specification and Bills of Quantities) AR AR/JR AR
Wrights Pit North – contingency option – no update. Communications Plan – noted request received from Manx Radio to speak to Consultants. TB advised of being happy to do further interview, possibly with DEFA colleagues.
3. Phase 1B Update JR told of no progress since last meeting. JR had received DEFA input for remit document and also some input from SG. Consultant will do EIA and DEFA have commenced data processing. AR/TC to meet German Commissioners on 9 January 2019 to discuss Rockmount options. AR asked about samples at Rockmount – clarification to be sought.
4. Phase 2 Update No update.
5. Notes of previous meeting held 13 November Impact of MUA high voltage cable within [redacted] - DC has sent emails regarding cable to MUA - Noted cable is outside 4m wayleave and MUA have gone silent on the matter. MUA aware that current design will build up to cable. TB queried constraints.
6. Any Other Business No matters raised.
7. Next Meeting 31 January 2019
1. Welcome and Apologies Apologies received from:- Ann Reynolds, Director of Ports, DOI (AR) Tim Cowin, Head of Highways and Asset Management, DOI (TC) Stephanie Gray, Head of Waste Management, DOI (SG)
2. Phase 1A Update Planning Application Progress Noted planning application has been submitted with various comments received from stakeholders / government departments / public. Impression is that there are a lot less concerns than expected, most of the comments have been raised by government officers, not the public. JR told of 57 items being addressed, including pipe line route in river which was commented upon, so plan is to take pipe out of the river and run along the roadside / along harbour wall. A table has been compiled setting out the questions and going forward will itemise responses and adjustments made, which will then be resubmitted along with any revised documents. This will trigger another 21 day consultation window. The existing programme can accommodate this delay, but with no further float for other delays, keeping the 2019 dredging option on course. JR advised that DOI and planning have still not yet received a definitive response from DEFA – SR informed that the response is with the CEO – BW to chase. SR told of a review meeting to be held on Monday afternoon, with documents to be submitted to Planning on Tuesday. TB noted draft feedback had been received from DEFA – SR stated that the concerns have not been made in detail. BW said that one issue that was raised related to black guillemots – DC said that this issue is being addressed. BW said that the timing of excavator moving at a reasonable pace would minimise disruption to nesting. It was BW
liability cover re putting field back to original conditions. BW told of undertaking weekly sampling during Rockmount of the run off/leachate. BW asked for more details from contractor regarding proposal. PL told of being able to do weekly samples. Finance Regs compliance JR told of some issues and of currently working with the AGs. Programme and Risks DC said that the key is to do 18 days of dredging in 2019. Land Issues JR advised that the last round of negotiation is ongoing with [redacted]. Issues around working hours. Still working with [redacted] as option as back-up plan. Finances JE told of budget shortfall – volume of material has gone up by 70%. Paper to Treasury required to seek additional budget and appointment of single tender contractor. Wrights Pit North No longer option as application submitted does not include to accept silt. Therefore, option CLOSED. TB asked where material could go if not to Cross Vein Mine – SR told of possibility of New Turkeyland, with possible change in disposal licence and using up significant volumes in strategically important facility. Communication Plan Nothing further – wait until project is further forward. JR JR
3. Phase 1B Update JR told of little progress made. BW informed of having provided EIA scoping – JR said of the need to incorporate comments. JR advised that he will look at Rockmount and of possible requirement for 12 month extension to planning / covenant. JR to arrange for Phase 1B Consultants to do review of Rockmount. TB asked about monitoring at Cross Vein Mine – SR advised that this has commenced. JR
4. Phase 2 Update JR informed of no progress. BW said that Phase 1B solves Phase 2.
5. Response to Environmental & Infrastructure Policy Review JR advised of CEO looking for update. JR to draft response for CEO next week. JR
6. Notes from previous meeting AR/JR to register as Speaker for Planning. JR advised of draft letter to DEFA Planning regarding dredging work in marina sent to AR this afternoon. AR/JR
7. Any Other Business 7.1 Debris screen - BW said that this could house long term monitoring kit. JR said that this may be worth flagging up to the Minister. 7.2 SR advised of having spoken to silt busters and coagulant. DC to speak to MH. JR DC
8. Next Meeting To take place on 14 February 2019
1. Welcome and Apologies Apologies received from:- Bernard Warden, Director of Environment, Safety & Health, DEFA (BW) Paul Lenartowicz, DEFA (PL)
2. Phase 1A DC advised that the ECI Stage One tender report has been approved, with meetings scheduled with the successful tenderer (Land & Water Services) on 28 Feb and 1 March – agenda to be produced. DC told of having been in touch with the bore hole contractor, with draft test results expected this week. DC confirmed all on track. DC informed of comments received back from S Butler (DEFA) regarding planning. JR told of having met with S Butler yesterday to go through comments – draft Officers Report is proposing to accept application. TB noted 5 year approval from when granted. TB told of now having to go through Planning Committee and Officers Report proposes only 4 interested parties (MNH, MUA, [redacted] and Peel Town Commissioners). TB told of having previously received positive feedback from Peel Town Commissioners towards the scheme. AR noted Manx Wildlife Trust does not get interested party status - TB said of there still being a period of time until heard from Committee, and they can still show an interest. DC spoke about EVF queries. TC told of three planning conditions from Highways. TB noted a lot work undertaken in resubmitting information. Noted 4 March Planning Committee – JR to register as Speaker. DC told of the need to firm up the budget. JR went through table summary of costs which highlighted budget of £1.934M, with revised cost forecast being £3.239M, showing a difference of £1.3M. Meeting noted could either modify scheme to fit available money or seek further funds. It was noted that the additional monies are required in later years. TB said of the need to JR
be clear about what we are delivering for the money and to present how many tonnes are to be delivered, ie Department is doing more dredging. MK stated that mobilisation costs are high. JR to show/outline as cost per tonne. JR said that, after fixed costs, there is not much left for dredging. AR said that we could factor in two year’s worth of maintenance dredging savings – JR said that Treasury may want contribution back from Department. TB said that the wording needs to be clear and asked if another paper has to be put together. JR said of the need for a paper to Treasury to cover bothy single tender bid and cost is above budget. JR to produce draft paper – need confirmation that the CEO’s view is the same at TB’s view. AR noted going through ECI stage. AR also noted 7 day a week dredging. AR mentioned work permits and contractor must hold valid work permits – TC told of zero days for construction industry workers. DC told of being a premium to dredge in 2019 due to mobilisation costs of equipment for short period and queried whether the company could hire local excavator for first year to keep mobilisation costs down. MK said of the need to speak to Fisheries about dredging after TT period. JR informed of Cross Vein Mine not ready until after second year of dredging. TB said of the need for definitive dredging dates. TB queried what DEFA will allow the Department to do – what would be the cost saving if dredging was deferred to next year. TB said that he would accept if not value for money. JR to look at costings and model. TB asked what the successful company thinks they have won. JR said to work with ECI to build lagoon, dredge 16,000m3 with option for second 16,000m3. DC told of having priced for 3 dredging campaigns (6,10 & 14,000m3) and have submitted alternative idea for staging the lagoon construction. JR told of commitment to do 16,000m3 and empty lagoon and decommission, with option to do third year. TB asked who has the option. DC said that it is for the Department to place on the contractor. TB noted of company having won contract to finalise design, build and operate from beginning to end. TB asked about [redacted] – JR told of having gone to the AGs. TB asked if there was any reason to be concerned. JR highlighted working hours/description of hours in lease did not tie up with what we were asking for and have gone back to [redacted] with outline of hours. DC told of having asked for 7 days a week operation, 12 hours a day – JR said that what went in is what we put in EIA. JR advised of still having similar paperwork being developed for the [redacted]. SG mentioned possible negotiations with the [redacted] regarding the Raggatt Tip – TB/JR noted. JR JR DC JR
3. Phase 1B Update JR expressed concern in relation to resource to get Phase 1B going. Phase
1A keeps growing with demand for officer time. Know what we need to do to get consultants going, and what is expected for us for 1B – should we be looking at trials/and will we be expected to undertake – have asked for feasibility study. AR told of requiring input from DEFA for 1B. JR said that it is very environmental and suggested DEFA have their own consultants. TB said that Phase 1B is DEFA led and suggested to set up discussions between JR/TB & DEFA (BW/SR) to kick off Phase 1B. SG told of having looked at draft remit and had questions about statements DEFA made and the need to provide supporting documents.
4. Phase 2 Update JR advised that Phase 2 is where we start to reduce the level of contaminants going into the river. Noted letter drafted for CEO for ENI Policy Review Committee. TB said that Phase 1B is linked with Phase 2, and queried how high up list Cross Vein Mine is – TB noted multiple sources. TB stressed that Phase 1B kick off meeting is priority and then mobilise Phase 2 from that. AR said of having written to MUA about silt screens. JR told of the need to analyse point sources and identify and would help with contaminants coming into water. If silt trap still would have problem as to what to do with silt. It was queried if put on the 7 mines if it would make a difference. TB said of the need to understand the bigger picture. Regarding debris screen, TB told to treat as Ports Division issue.
5. Notes from previous meeting Discharge Licence – noted Department would apply for the licence and then transfer to third party. Silt Busters – DC said that for hydraulic option would need at least 5 units. If mechanical dredging used, it is more feasible. There is a cost with the benefits unknown. These may be an option to consider under the adaptive management system. TB asked what Silt Busters do – DC said that they treat water and attempts to remove some of the silt. Noted that they are a potential post-lagoon treatment. TB asked if DEFA are going to control what is going back into marina with the discharge licence – should only be deployed if necessary. DEFA response- noted BW chased response. E&I Policy Review – draft response for CEO done. Speaker for Planning Committee 4 March – JR to register nearer the time. Rockmount – JR told of having been highlighted in planning application process about the 5 year condition on Rockmount with the Department’s JR
response being that the dewatered material would go to Cross Vein Mine and/or remediation at Wright Pitts North, with anything that was not suitably dry going to Cross Vein Mine and the Department would look to put into Peel Lagoon. AR said that overall thoughts are to look for short term extension with Commissioners for extra time so as not to take away priority of Peel. SG told of being too saline to be used for restoration material as is very sandy – no bore hole data – need structural test/analysis. SG stressed the need for evidence based decision making. JR to include in Phase 1B remit. JR stated that it would be useful for SG to be involved. JR
6. Any Other Business No matters raised.
7. Next Meeting To take place on 14 March 2019
1. Welcome and Apologies Apologies received from:- Mark Kenyon, Ports Manager, DOI (MK) Stephanie Gray, Head of Waste Management, DOI (SG) Distribution: Present & Apologies Malcolm Cowin, MUA
2. Phase 1A DC advised of having appointed Land & Water (the dredging contractor) for the ECI phase (Stage 1), the team has met with them and they are helping to develop plan/design. DC said that they have been professional and positive. Programme is on track and currently working towards dredging in 2019. JR advised that planning permission for the project has been received and that the panel were complimentary about the government Departments working together. JR told that the planning approval comes with 28 conditions. We are still on course for Contract award 1 April (subject to departmental approval and Treasury approval) and hope to have both Fisheries and Waste Licence in place before contract award. Water Discharge Licence expected mid to late April. JR informed of risk of land lease, with final version having now gone to the land owners agents. AR asked about length of time the contractor needs to prepare the site. JR advised contract award 1 April with hope to mobilise mid-April to construction of lagoon for this year’s dredging to commence 1 May. BW asked how long construction phase will take – JR told 2-3 weeks – DC advised 24 days to construct and 24 days of dredging. TB queried 250 cubic metres a day and asked if that is a finite volume – DC said that it may
AR asked JR to add communications to the agenda. JR
3. Phase 1B Update JR advised that BW/SR/TB met last week and discussed how to structure. Regarding structure the best way is for DOI to own project with DEFA to have dual role (land owner/environmental regulator). As part of that BW proposed possible changes to attendance at this Project Board meeting. BW told of structural changes within DEFA and that SR is the obvious liaison within DEFA for the Project Board meetings. BW to make sure appropriate specialist officers are invited to meetings where necessary. TC queried if his attendance was still necessary at the meetings as Phases 1A and 1B are under control. It was agreed that TC be kept on circulation list for agenda and notes and to attend if he felt it worthwhile. JR said of the need to understand what is needed at Cross Vein Mine with the need to look at doing feasibility study to validate using Cross Vein Mine. It was noted that some stabilisation of material may be required. AR queried if a feasibility study would help us gauge how we want it to be. Noted don’t have anything scientific yet. BW said that any form of feasibility study is going to support and be complimented by an environmental impact study. BW said that the usual DEFA specialist can see value of approach. The term feasibility study was queried – BW said of possibility to rename ‘proposed review of’ or ‘detailed assessment’. JR to ensure that wording on remit is amended. BW said that there will always be questions about value of putting material to Cross Vein Mine, however metals are less contaminated than at the Deads site. BW spoke about UNESCO. BW said that the project is a catalyst to develop better project management. TB said of needing to be clear of our objectives. SR said of being keen that we keep options open. TB said of being lots of value in wider exercise, and that he wants the focus to achieve the outcome we said we were going to. BW said message is Cross Vein Mine remediation is the core project work. AR noted all in agreement. JR spoke about Dunston Environmental stabilisation process and advised of having received quotes to filter/treat/stabilise material. JR recommended a trail small scale as part of the ‘detailed assessment’. Cross Vein Mine will have to go through planning process. JR told of back up option being to stabilise material. BW said any disposal at sea for material above the OSPAR level 2 threshold would need to demonstrate we have looked at all options. TB stressed of not wanting us to be cavalier about environmental issues and is worth covering bases – can see value in the proposed Dunston Environmental stabilisation trial. TB queried ‘may need treatment’ – BW said of first knowledge being after SR BW JR
spoke to consultants – SR said of needing opinion of a land remediation expert. TB queried verification exercise / detailed assessment and asked if we are going out to market about intent. BW suggested that there is scope for further officer meetings (BW/JR/SR/PL+others). JR advised of having secured budget for Phase 1B. This generally follows the pattern of Revenue funding for dredging and capital for CVM. AR queried phase 2 feasibility – JR said that once Phase 1A and 1B are going, once resource is available. SR told of quantification of benefits of remediating Cross Vein Mine - noted Winter 20/21. JR said that another option could be to use the same consultants to look at Rockmount – AR to look into this. AR
4. Phase 2 Update No progress. AR advised of having a meeting arranged between Ports and MUA regarding debris.
5. Notes from previous meeting Previous notes from 31 January meeting TB queried [redacted] – JR advised of having lease documents. E&I Policy review – JR did draft and had E&I Committee last week. Responses drafted for CEO for both. Previous notes from 14 February meeting Work permits – in process of applying for Land & Water. AR noted Antony Bates Partnership (DC & HS) have work permits. Dredging after TT – risks have been discussed with Land & Water and the risks would be too high to dredge after TT. TB noted it has been evaluated and is commercially too high.
6. Any Other Business BW spoke about DEFA planning consultation response for Phase 1A and said that SR did all the work and did a ‘smashing job’ on it. TB acknowledged support from planning in respect of team/good work.
7. Next Meeting To take place on 11 April 2019
1. Welcome Tim Baker MHK Chairman (TB) Ray Harmer MHK, Minister (RH) – Part only Ann Reynolds, Director of Ports, DOI (AR) Mark Kenyon, Ports Manager, DOI (MK) Bernard Warden, Director of Environment, Safety & Health, DEFA (BW) Stephanie Gray, Head of Waste Management, DOI (SG) Simon Renton, DEFA (SR) Jeremy Reece, Senior Project Manager, DOI (JR) Dredging Consultant, Anthony Bates Partnership (DC) Personal Secretary, note taker Distribution attendees and apologies Malcolm Cowin (MUA)
2. TB opened the meeting at 9am and thanked everyone for coming. Further to Treasury’s decision not to agree to the request for additional expenditure and the waiver to appoint a single tenderer, TB queried the Pink Book budget provision. JR set out the financial provisions within both capital and revenue funding. JR confirmed that any tender with a value of over £100,000 would require Treasury approval to award. TB noted that the project would be unable to move forward in the preferred manner. AR commented that the exemption request to allow Anthony Bates Partnership and Silva Consulting to compile the tender documents was submitted to the Attorney General’s and that a retrospective exemption was issued for permission. Capital Procedure had been followed in all other aspects and it had been confirmed that this was a technicality and did not influence the tender process in any way. AR noted that the formal Treasury Minute had not yet been received and that information relating to Treasury’s decision had been fed back by Nick Black. JR to chase NB for details of the formal minute. TB asked whether dredging could take place after TT 2019; JR added that productivity would be low under the conditions set by DEFA over this time line due to standing time of either three or six hours in every twelve to reflect conditions linked to the tides. MK added that this assumed that the boats would be able to move around to accommodate the restrictions and would present major operational difficulties. DC noted that the contractor could be asked to set their working hours and rest days to suit the tides. AR added that in 2016 mobilised works had to be stopped due to fish spawning early. JR confirmed that Treasury approval would still be required to appoint Land and Water for this work. JR
RH confirmed his agreement to tender in parallel to the planning application for Cross Vein due to the need to move the material at Rockmount to Cross Vein. RH stated that it would be important to ensure that dredging started in January 2020; by not doing it the problem does not go away and it makes it worse. DC and RH suggested letting Land and Water know the situation and ask them to extend the length of time their tender was valid for. RH and DC left the meeting at 11.15am. DC/JR
3. Phase 1B JR noted that the next stage would be scientific and environmental procedure; an exemption would be needed for a consultant to put together the tender documents. TB stated that the proper process must be followed. JR said that the consultant would need to be able to work through the environmental reports, identify requirements and liaise with DEFA and driving it forward. SG added that the planning application for Rockmount had a time limit for the removal of material and DEFA will require information. TB asked that AR start the process of applying for an extension of the planning permission at Rockmount. AR to discuss any possible planning points with Nick Black. It was noted that the Team ensures that the material is not left in the field. TB concluded that the presentation and paper to Treasury needed to be pulled together for May; JR to co-ordinate with DC and the Hydrographic Consultant from ADBP. TB stressed that the paper should speak to people who were not technically minded and that appendices should be included to add detail where required for robustness. Meeting closed at 12.15pm AR AR
6. Next Meeting 9th May 2019
1. Welcome Tim Baker MHK Chairman (TB) Ann Reynolds, Director of Ports, DOI (AR) - part of the meeting Mark Kenyon, Ports Manager, DOI (MK) Jeremy Reece, Senior Project Manager, DOI (JR) Paul Lenartowicz, Government Labs, DEFA (PL) Dredging Consultant, Anthony Bates Partnership (DC) Hydrographic Consultant, Anthony Bates Partnership (HS) Personal Secretary, Note taker Nick Black, Chief Executive, DoI (NB) – part of the meeting Distribution attendees and apologies Tim Cowin, DOI Highways Stephanie Gray, Head of Waste Management, DOI (SG) Simon Renton, DEFA (SR) Malcolm Cowin, MUA
2. TB opened the meeting at 1000hrs and thanked everyone for coming. TB advised that both NB and AR would be attending the meeting shortly as they were invited to meet the Chief Minister in the Chief Secretary’s Office regarding issues surrounding Peel Marina Project. Phase 1A Update TB advised on Treasury’s decision not to agree to the requests for additional expenditure and the waiver to appoint a single tenderer. We need to be clear where we are going and navigate the issues through onto solid ground. As far as the Independent Review was concerned, JR advised on approaching CEFAS, which was liked by Treasury & DEFA. It was noted that CEFAS have come back suggesting they could produce a report by late August/September. Alternatively, JR said we could go to other consultants for example involved in the Deep Water Berth projects. JR advised that it was NB view to use CEFAS as they are accredited to industry standards and would be acknowledged by Treasury and DEFA. JR suggested that he goes back to CEFAS and discuss a quote and plan of delivery. 1010hrs NB and AR joined the meeting. NB advised that they have just come back from a meeting with the Chief Minister and Treasury officials on Peel Marina and gave the following briefing. NB informed that the Chief Minister expressed concerned on this project with the lack of progress together
regarding his increasing workload requesting some additional support. TB supported JR’s position. AR agreed to progress. TB agreed that additional support should be looked at as a priority. Comms Plan JR queried communications in the public domain. AR referred to recent correspondence with IOM Harbour Users Association and of regular meetings where updates are given. Reference was made from an approach from IOM Newspapers with a simple outline response given. TB noted that any communications are vetted through IOMG protocols. DEFA Following on from Bernard Warden’s retirement, Karen McHarg has been promoted into his role. AR agreed to invite her to the next meeting or a named representative. Land Lease – JR advised that the [redacted] are negotiating a deal with MUA on their field at [redacted] for storage and compound facilities. MUA requested that we withdraw from discussions, to release the [redacted] to negotiate with MUA. JR has withdrawn the Department from negotiations and reminded the team that the site posed some access issues and we have secured the lease option on [redacted]. JR to write to [redacted] to confirm. AR added to thank them etc. It was noted that no payments had been made. AR
4. Phase 2 up-date AR advised that MUA needs to be invited to the Project Board when Phase 2 is considered. AR to discuss with NB. AR
5. Actions from the previous meeting No 24 held 12 April 2019 (a) Tender extension – JR to meet tomorrow re: Land and Water. (b) Rockmount – AR talking to NB on the matter. (c) Planning points – extending the application approval.
6. Any Other Business (a) DEFA representation – TB requested the DEFA representative have a consistent attendance. AR to ask NB to discuss further with Richard Lole, CEO, DEFA. Meeting concluded 1145hrs. AR
7. Next Meeting 13 June 2019
Present:- Tim Baker MHK Chairman (TB) Ann Reynolds, Director of Ports (AR) Mark Kenyon, Harbours Ports Manager (MK) Jeremy Reece, Senior Project Manager, DOI (JR) Karen McHarg, Director of Environment, Health & Safety, DEFA (KM) Simon Renton, Environmental Protection, DEFA (SR) Dredging Consultant, Anthony Bates Partnership (DC) (by phone) Hydrographic Consultant, Anthony Bates Partnership (HS) (by phone) Personal Secretary, note taker Distribution Attendees and apologies Tim Cowin, DOI Highways (TC) Stephanie Gray, Head of Waste Management DOI (SG) Paul Lenartowicz, Government Labs, DEFA (PL) Malcom Cowin, MUA (MC)
1. Welcome and Apologies TB welcomed those to the meeting in particular to KM who replaced Bernard Warden following his retirement. Introductions around the table were made.
2. Phase 1A update JR advised on receiving a quote from CEFAS to carry out the independent project review. CEFAS are able to comment on the marine based issues i.e. dredging and de-watering, however they advised that they cannot comment on other land based issues such as the movement of material to Cross Vein Mine. They propose using Environment Agency (UK Gov’t) to undertake the review of the land based issues under a separate quote. Neither CEFAS nor EA would comment on the value for money elements. JR suggested appointing an Independent QS to undertake this element. JR referred to a previous meeting with himself, AR and Andrew Sidebottom, Treasury (AS). It was AS’s view that Treasury wouldn’t give approval unless further information was obtained regarding Cross Vein Mine including assurances on costs. It was suggested that Anthony D Bates Partnership (ADBP) could be approached to recommend a QS who is good with a relevant data set from the dredging industry. DC agreed to give it some thought and feedback to JR. . Discussions were held on a suitable alternative, on or off-island. Silva Consulting DC
JR advised on their credentials as a lab accredited by the MMO in the UK and the only lab that is accredited for all types of tests. SR queried surface fraction issues and deposits to sea. SR suggested it could be cheaper if the test results for the top layers could be dumped out to sea and going forward if minimum levels were decided future silt could go out to sea. JR suggested that the silt may be used in other areas depending on the results. Land and Water Tender DC advised that Land and Water Services (LAWS) are coming back next week with an updated tender based on 2 dredging campaigns, with lagoon construction in late 2019 and the first round of dredging starting January 2020. Silva Consulting (QS) looking at the cost side and expect a saving of £100-£150K with contract to be awarded by 5 August 2019 – there may be some flexibility in this date, as it does not align with the reviews and Treasury approval programme. DC informed looking at the contractors Programme, which appeared OK. JR advised it is going to be tight with some key dates to stick to. TB suggested undertaking some underwriting. JR advised that we may have to look to underwrite some of the advanced procurement costs. Programme JR provided an update on the overall project Programme, with concerns on Phase 1B. In order to mitigate this, advanced procurement will be required on the wildlife surveys. TB queried link between Phase 1A and 1B removal of material and why it is only shown between November to February each year. JR referred to issues being driven by DEFA with working at the Cross Vein Mine between certain times in the year. JR stressed if 1B runs late then 1A there will be knock on effects on moving the material. Comms Plan JR referred to during TT week Mr Crookall, MHK was on MMTV pushing for progress. It was noted that JR had spoken to him this week with an up-date. TB advised on a good meeting when the IOM HUA met the Minister. JR
3. Phase 1B Re: Scientific Study – Noted ADBP has been commissioned to draw up a remit for consultants. JR advised on a meeting held yesterday (12 Jun 2019) between himself, ADBP, and various DEFA officers to discuss the relevant issues. During this meeting a query was made by ADBP in how we address Cross Vein Mine is it landfill or reclamation. ADBP queried that we need to understand what we want to achieve and help clarify issues for the Planning Application in terms of what level of scientific input is required. JR explained that if we treat Cross Vein Mine as remediation then we are likely to have to factor in a liner to separate the existing material from the imported silt and undertake chemical stabilisation of the silt to remove any additional environmental ‘load’, for which we have no budget. If we define Cross Vein Mine as landfill we don’t have to undertake treatment,
Cross Vein Mine is up for questioning and SR confirmed that DEFA need additional study to be able to support their original concept of an environmental net gain at CVM. JR to produce remit for the consultants, then we can put out to tender, however he advised that we need a high level interim report before then. DC to speak with SC on methodology and options. Other areas of storage was discussed, including Turkeylands. AR advised there is a capacity issue and is expensive. SR referred to Billown Quarry as a new infill site and believed it has a massive capacity. AR agreed to speak with NB on these options for advice. MK suggested South Barrule Quarry area. SR advised that DEFA would need to take professional advice on remediation, however offered up any other assistance.
4. Phase 2 update JR advised remit documents drawn up and could go to tender in 2 weeks. However, as the project funding is on stop from Treasury, Phase 2 studies should wait until September. AR advised that the work has to be done and get a spec out and get a price for a “feasibility study”. It was noted that the Minister is keen to push on with Phase 2. AR advised on looking at silt traps next week, trying to work in parallel the project with a view to reducing the amount of silt coming down from the river. AR
5. Actions from the previous meeting No.25 dated 9 May 2019. (a) CEFAS re quote – JR advised quote received and to do a Financial Regs exemption. (b) Meeting Land & Water Services – done. (c) Areas of Programme – JR advised on up-dated timeline. (d) Stand alone letter – ongoing. (e) Bernard Warden’s replacement representative –AR confirmed spoke to KM, done.
6. Any Other Business (a) Silt Traps – AR advised on a meeting next week involving MUA, DEFA, DoI. TB referred to an email from Friends of the Earth who had put down a number of suggestions. TB to send to AR and KM for consideration. (b) JR Workload Resource – JR queried on his current workload. Noted that JR to speak to Paul Slinger. TB
7. Date of Next Meeting Noted 11 July 2019 1500hrs in West 1. TB asked that the time of this meeting be re-scheduled to 0900hrs. This was agreed. Meeting concluded 1715hrs
Present:- Tim Baker MHK Chairman (TB) Mark Kenyon, Harbours Ports Manager (MK) Jeremy Reece, Senior Project Manager, DOI (JR) Karan McHarg, Director of Environment, DEFA (KM) Paul Lenartowicz, Government Labs, DEFA (PL) Simon Renton, Environmental Protection, DEFA (SR) Dredging Consultant, Anthony Bates Partnership (DC) (by phone) Hydrographic Consultant, Anthony Bates Partnership (HS) (by phone) (from 1007hrs) Personal Secretary, note taker Distribution Attendees and apologies Ann Reynolds, Director of Ports (AR) Tim Cowin, DOI Highways (TC) Stephanie Gray, Head of Waste Management DOI (SG) Malcom Cowin, MUA (MC)
1. Welcome and Apologies TB welcomed all those to the meeting. Ann Reynolds had passed on her apologies to the meeting.
2. Phase 1A update JR advised that CEFAS are going to be on the Island 11-12 July and will be meeting separately MK and DEFA team this afternoon with a site visit arranged for tomorrow. It was noted that CEFAS had indicated their report should be with us by 7 August 2019, just before the next Project Board Meeting. JR informed on a telephone conference with CEFAS and they understand the remit and hopefully give us our chosen way forward. TB advised that if they submit other suggestions then we will take them aboard and hopefully they will support our chosen way forward which will give reassurances for Treasury. JR advised that this covers only the marine side. As far the land elements are concerned, JR advised that CEFAS had hoped to engage the Environment Agency to review it, however they could not support it taking account of the time frame, but have supplied CEFAS with a number of possible consultants on their framework contract. CEFAS have been asked to provide a quotation for engaging one of these consultants as a sub-consultant. Therefore JR advised on having 2 reports, one on marine aspects and one on land (sub- contracted) from CEFAS. JR advised Anthony Bates Partnership (ABP) had
identified “Atkins” (formerly W S Atkins) as an independent cost consultant. Atkins work would be headed by the former Chief Engineer at Milford Haven Port who has vast experience working on a number of schemes involving contaminated silt. JR advised that they are aware we need their draft report by 7 August 2019. JR pointed out the deadline for accepting the Land and Water Services (LAWS) tender, which has been extended to Mid-September. TB advised on being clear that the Independent Report under 1A is different than 1B. JR referred to concerns on getting the ‘land’ element to tie in to the timescale and potential additional work involving 1 or 2 parties if CEFAS give advice on other options and if Atkins need to take a look. TB advised it would be helpful to deliver the 2 reports by CEFAS as we need to get Treasury concurrence. For the ‘land’ element, JR advised he will let KM know maybe up to 2 weeks although hopeful to get both reports by the end of August. TB queried LAWS tender price expires. DC confirmed it is valid to 15 September 2019. TB noted that LAWS are keen to progress. Land – DC advised on continuing to work with LAWS on technical and design issues to improve the dewater system. In terms of costs they have revised the figures for 2 campaigns and the expected saving over the original 3 campaign proposal is ca £147K.
3. Phase 1B SR advised the report from Wardell Armstrong (WA) on the suitability of the silt for use at Cross Vein Mine was expected that day and in the meantime WA had provided a short email narrative stating there were concerns that the material is not fit for purpose due to exceedance of lead and PAHs. TB expressed concerns on what their remit/instructions were. SR confirmed that the remit had been circulated in advance and advised that WA had been asked whether the material is fit for purpose to go to Cross Vein Mine (CVM). KM advised that the group needed to see the full report to take a look at the detail. TB stressed that this is a shared problem and that we still have got to do something with the silt - it cannot remain in the marina and has to go somewhere. MK queried the methodology and whether it could review the implications for lining the site or should it be deemed as landfill, i.e. look at options to get the silt to CVM. KM queried the use of other sites - South Barrule quarry / Turkeylands / existing landfill. SR advised his understanding that CEFAS may be looking at depositing at sea and capping with a sand layer. JR referred to using a hydro-cyclone method (like a tumble drier), if the material remains on land - however he explained that it takes a lot of energy and issues with kit may be problematic. MK advised that something similar had been looked at however there were too many issues to deal with. TB queried information on capping. JR advised that the budget does not include anything for any material treatment. JR advised that CEFAS has
talked about looking at an option to deposit the silt out to sea with a sand layer over it (capped). KM advised that she will discuss this option later on today with CEFAS as she had concerns over scallop beds if this was recommended. TB queried capping at CVM as his belief was to layer it over with clay and have WA considered that? SR advised that if it was deemed as landfill, DEFA Planning would expect the environmental impact to be assessed as part of the planning application. JR added that to comply with the Strategic Plan, it has to be demonstrated that if it is deemed landfill, all alternative locations have been assessed and it can be demonstrated that CVM is the best place. JR explained that if we were to put a cap on the existing material with the silt on top then it would be deemed remediation and may be viewed as an environmental enhancement scheme. TB advised on his understanding that this option is an improvement on the problems at CVM and that DEFA would support the improvement of the land as an environmental enhancement exercise. TB informed that ultimately COMIN will have to decide and stressed that the silt is going to go somewhere and that we all have a collective responsibility. KM stated that it was essential for the group to take external independent advice to avoid future public criticism and there is a need to ensure that the development is done for environmental reasons and the risks are reduced wherever possible. MK advised that any option is never going to be a good option, and if CEFAS recommend depositing out to sea and capping then concerns may be raised by marine conservation people/organisations. TB stressed on the need to work up a solution. PL advised that we need to see the WA report and to discuss with them on the points they have raised. It was agreed that JR call an extra Project Board meeting next Thursday (18 July 2019) and invite Neil Hughes from WA to discuss the report and get more information on their findings and their remit. SR confirmed he will circulate WA’s report later on today to the Project Board. JR and KM to speak to WA beforehand. DC expressed surprise that this has come out now as timing is still an issue. 1007hrs HS from ABP joined the meeting (via phone). TB advised that COMIN will ultimately make the decision as to where the silt is to go either on land or out to sea and we have to provide option(s) for them to decide. KM JR SR JR/KM/SR
4. Phase 2 update JR advised on updating the draft remit for the consultants re: Scientific Study. SR queried if consultant had been appointed. JR advised that 6-7 months ago DEFA was going to initiate a Catchment Management Project to include the River Neb and the Phase 2 consultants would need to identify and fill any gaps in the DEFA project.
can be done and there is a need to look at the designs and options for sites. Generally it was agreed it was a productive meeting. TB noted a mini-work stream being developed. TB advised on IOM HUA’s understanding that MUA was more involved with the Peel Marina Board. MK informed that MUA don’t need to be involved and that the MUA are the landowner with flood management responsibilities. They have admitted their guidance document is a little ambiguous and are looking to re-draft it. TB noted that the MUA are engaged with the Peel Marina Board as much as they need to be.
5. Actions from the previous meeting No.26 dated 13 June 2019. (a) QS recommendation - done. (b) Paper re Treasury concerns – done. (c) Programme Management - JR on-going. (d) WA/Scoping – on-going. (e) Phase 2 Report – Treasury paper – JR working to procure working with DEFA and WA to include in Treasury paper. Noted scientific study/stabilisation on hold until WA advice. (f) Silt Traps – done.
6. Any Other Business (a) Turkeylands – SR referred to AR and potential site at Turkeylands as an option and that she was going to speak with NB. JR agreed to speak to AR to get feedback. (b) South Barrule – KM queried possibility of this as a suitable site. MK advised the site is owned by the DoI has been used for disposal of date expired marine pyrotechnics (flares). However, in the past SG has ruled this area out with having licensing, planning and habitat issues. TB referred to the wording in the Strategic Plan with some grey areas as far as planning is concerned. . Referring to the planning process, TB advised working up a framework in line with the Strategic Plan and that the application is balanced. TB advised that the Planning Application will be referred straight away to an Independent Inspector as it is an application involving DEFA owned land. As a result the decision will rest with COMIN. JR added that we need to develop a robust case to gain Treasury confidence. KM advised if we were to treat the contaminated material to reduce the lead/PAH this may increase the cost. MK pointed out issues with where to treat it, including environmental issues and noise may be a concern. JR informed on having received an outline proposal for stabilisation process, as part of the Phase 1A Planning Application (received from Dunton Environmental Ltd). (c) Water Licence – JR requested that KM/SR chase Neil Gray (DEFA) for the formal issue of the Waste Licence. SR agreed to chase. JR SR
7. Date of Next Meeting
Present:- Tim Baker MHK Chairman (TB) Jeremy Reece, Senior Project Manager, DOI (JR) Ann Reynolds, Director of Ports (AR) Mark Kenyon, Harbours Ports Manager (MK) Peter Dainton, Project Manager, DOI (PD) Karan McHarg, Director of Environment, DEFA (KM) Paul Lenartowicz, Government Labs, DEFA (PL) Simon Renton, Environmental Protection, DEFA (SR) Dredging Consultant, Anthony Bates Partnership (DC) Personal Secretary, note taker Distribution Attendees and apologies Hydrographic Consultant, Anthony Bates Partnership (HS) Tim Cowin, DOI Highways (TC) Stephanie Gray, Head of Waste Management DOI (SG) Malcom Cowin, MUA (MC)
1. Welcome and Apologies TB welcomed all those to the meeting.
2. Phase 1A update JR confirmed that CEFAS marine report has been received and circulated to members. TB noted on a comprehensive document. To sum up, JR advised that CEFAS have recommended to pursue the land based option. Noted CEFAS had identified alternative option for disposal at sea, but with capping. CEFAS have concluded that for the capping option, the costs could escalate and the risks would be higher and timetable may take longer. AR suggested that Treasury may not approve a scheme which involved such high risks. JR tabled an Options Summary (appended) to the meeting giving a breakdown on overall costings and comparing either dredging, dewater and hold in lagoon against dredge and cap at sea. Page 1 – Excluded the costs associated with the Rockmount material and looked at the cost per cubic metre, vehicle miles, environmental issues/impacts and including risks the meeting noted the overall costs range. Page 2 – Including the costs associated with the Rockmount material. TB advised on excluding Rockmount as CEFAS have already given us 2 core options. JR reminded all that the business case includes the costs for the Rockmount material.
finding of the last 2 months and that some areas to be covered in the report have already been duplicated by the WA and CEFAS (Arcadis) reports. JR advised that one area of the study would be a feasibility study looking at Rockmount, which could be done as a separate study. JR to ask ABP to edit the remit for 1B consultant. DC suggested to narrow the scope down – JR recommended push for 1B Study, ultimately then we have a consultant’s report. CEFAS (marine) report JR asked for comments on the report by tomorrow. SR advised that CEFAS were suggesting water coming back from the lagoon may need treatment and asked for examples where this has taken place and relevant licence conditions. JR identified that it has been recommended that the flapgate remains closed for 6 hours after dredging finishes. Given that the flapgate is open for 4 hours each tide, it only leaves 2 hours per tide to dredge. SR referred to the use of silt curtains and need to sustain pathway for the fish. PL suggested closing the marina and removing the boats. MK confirmed this would not be practicable. Phase 2 SR advised on agreement reached by DEFA/MUA to engage a consultant to provide a catchment management plan, in line with ongoing flood risk management. AR referred to a meeting with MUA to discuss silt traps. Noted JBA is working on a feasibility study. AR advised that the IOM Harbour Users Association are continuing to press for a solution. 1704hrs SR left the meeting. JR All JR JR SR/KMc
5. Actions from the previous meeting No.27 dated 11 July 2019. (a) Scallop Bed concern – not now the preferred option. Closed. (b) Additional PMB Meeting– done took place 18 July 2019. Closed. (c) Circulating WA Report – done. Closed. (d) KM/JR speak to WA – done. Closed (e) KM speak to DEFA re clarification - done. Closed. (f) Phase IB remit – done. Closed. (g) IOM HUA response - draft letter produced AR to send to TB. Noted meeting next week. Closed. (h) Turkeylands – JR advised not done and to speak to AR. (i) Water Licence – JR advised outstanding will email Neil Gray (DEFA) by the end of the month. JR/AR JR
6. Any Other Business No new issues raised
7. Date of Next Meeting
Present:- Tim Baker MHK Chairman (TB) Jeremy Reece, Senior Project Manager, DOI (JR) Ann Reynolds, Director of Ports (AR) Ports Project Coordinator, DOI (PC) Karen McHarg, Director of Environment, DEFA (KM) Paul Lenartowicz, Government Labs, DEFA (PL) Simon Renton, Environmental Protection, DEFA (SR) Dredging Consultant, Anthony Bates Partnership (DC) Personal Secretary, note taker Apologies:- Mark Kenyon, Harbours Ports Manager (MK) Hydrographic Consultant, Anthony Bates Partnership (HS) Distribution Attendees and apologies Tim Cowin, DOI Highways (TC) Stephanie Gray, Head of Waste Management DOI (SG) Malcom Cowin, MUA (MC)
1. TB advised now in end game of this project, and purpose of today is to bring the project to a proposed solution prior to the all parties meeting next Monday, 23 September. Object of meeting is to have an agreed solution between both departments ahead of the Treasury discussion. It was noted that there are still some boxes to tick in terms of Treasury obligations. ie, “What are we going to do and when?”. TB stressed that doing nothing is not an option.
2. Outcomes and recommendation of Independent Review and resampling of marina Marine, Land and Cost reports Reports previously circulated, together with summary report. JR told of the objectives of the review, namely;  Is the two phase strategy still valid – answer yes  Is selected option for phase 1 the most effective – yes. However Arcadis were non-committal.  Alternative options – no one has said not right option – CEFAS have left open a couple of possible options. Arcadis and Atkins have said that without stabilising, CVM was not feasible.  Costs – Atkins confirm the tender is within the plus or minus 5% range – provides value for money.  Piping vs haulage – Atkins have said that mechanical is the right option,
appears to be out of line with historical comparators – with MS11 and MS13 being high contaminant levels and retest to make sure you have not got a cross contaminated sample pot – KH said they were also inconsistent with previous results in river channel. TB told to do testing and get results which define area that can go to sea then need some work doing EIA or risk assessment coordinated by or done by CEFAS. JR asked DEFA colleagues to confirm what we are actually asking CEFAS to do, within the next day or so. SR confirmed a disposal at sea licence is required under Part 2 for dredging. DC asked if Peel has its own designated disposal areas - AR said that in the past DEFA came back with 3 sites - PL said that there is a site that has been licenced not far from Peel which has been issued in past for small dredging’s. However he has concern that a much larger deposits would need a review. The previous report identified areas on the “least worst for fishing” basis - AR to look for a copy of the report and the previous dispersal modelling reports. TB queried potential sites – AR advised 3 sites highlighted in 2015. PL said if below Action Level 2 some of the previous concerns cease to be appropriate. PL informed that the OSPAR wording is below upper level should require more detailed assessment before depositing at sea – our concerns are fishing industry and if nutrients in it. JR asked if he could have all that test requirements out by end of tomorrow. TB queried if we are asking CEFAS to evaluate the green areas and dispersal at sea? KH said depending on sampling results -TB queried why? KM said that if all untested samples are below level 1 it can be disposed at sea – if over 1 then more rigorous assessment needs to be done as to where to go. PL asked if it is better to ask them to do that in respect of 2 sites on basis if assessment says not going to do any harm just off Peel it would save on costs. DC said that the approach he would take is to gather everything and give to CEFAS and see what they recommend/advise. KM said that DEFA would have to do some kind of consultation with fishing industry. DC said that info received from CEFAS was would draw mid-way point for sea disposal and noted DEFA have differing opinion. DC queried the area around MS1 – a lot of area is at flap gate level and below, so the volume to be dredged is only 1000m3. JR suggested waiting to get resampling data back before reviewing it. AR KMcH/ SR/PL
3. Phase 1B update JR told of 16,000 m3 capacity in lagoon and the need to think how we develop 1B, to avoid refilling the lagoon, if possible. JR outlined the new option of a modification at the Energy for Waste plant. SR asked if he would try to do both dredging to sea and land in one year – JR said that the disruption to the harbour would be colossal if done in one year. Normal practice would be to dredge the less contaminated areas first, however from a logistics point of view to do river first would free up pontoon spaces to provide space to relocate boats to – TB said that this has yet to be determined. TB confirmed that dredging will be done over 2 years and the material not going to sea will go to site to dewater – all needs to be properly evaluated. JR told of the need to be pursuing both options, EFWP and Cross Vein. TB stressed that it is down to us
to drive forward every solution – TB wants someone from group to take ownership of this. PL raised concern about how it works at EFWO as most of the material won’t burn –TB noted all a part of appraisal – who is going to deal with it – AR said that Ports will pick up. JR reminded all that the independent review had effectively eliminated the “Landfill” option at CVM, Phase 1B is down to 2 options – stabilisation of material for Cross Vein and EFWP. JR suggested that next step being to commission a start of design for stabilisation option at CVM. TB queried where it sits in terms of process with Treasury and their previous restriction to stop work on the project. TB’s view would be that it would be reasonable to progress work on dispersal to sea, but don’t think we should be instructing design of the Cross Vein solution until through the Treasury approval loop. Treasury do not have any of the independent review reports. TB queried what we need to do to move Cross Vein forward, JR said Treasury have given permission to commence environmental surveys at Cross Vein which has been ongoing since the Spring. If we don’t start design now we will, in all likelihood, not be able to empty the lagoon at end of year 1 dredging. TB stated that if you do the disposal to sea first, we have bought ourselves another year. AR noted aim for next Monday is to tell attendees where we are with the options. KM asked if anything is going to be circulated ahead of the meeting – AR said that we could circulate the slides. AR/PC AR
4. Proposed Way Forward Joint meeting to be held next week. We have tender with Land and Water Services extended to end of October and in order to commence dredging in January need to know by end of October. Looking at early October for resampling results – could then be back to Treasury mid-October. AR suggested to write to Andrew Sidebottom – TB asked AR to liaise with CEO. TB said we should give them some update. TB told of concerns re instructing Land and Water due to the October timescale. JR advised that there could be an option for the contract with Land and Water Services to be varied for first year to take to sea and then second year to build lagoon. Re money JR explained if all material has to go to land looking at £7-7.5M to dredge, dewater, stabilise – if some going to sea and some to Cross Vein Mine looking at £4.7M. If EFWP for material not to sea looking at £3.6M – SR noted development of EFWP is included. JR said cost of some material going to sea is a lot cheaper (a tenth of the cost). Budget request in 2018 for phase 1A and 1B total was £2.485M and in April 2019 it was increased to £4.3M. If all to EFWP cost is £4.5M. TB noted some risk around EFWP costs. JR stated that none of the costs include gate fees at EfWP and ash disposal fees at Turkeyland costs. DC told that EFWP gives long term solution (Phase 2). AR
JR will work on remit for 1B at Cross Vein Mine in the background. JR
5. Phase 2 update JR told of being ready to put our feasibility study brief to get long term options looked at. Will hold off until at least had initial feedback to Treasury. AR asked if we have to check with Andrew Sidebottom re costs as going back to ask for more CEFAS work and more sampling – noted independent review was okayed by Treasury, not cost.
6. Actions from previous meeting  TB re all parties meeting – all set for 23rd Sept.  Reports – all back – TB said well done to everyone for getting them back.  JR action re transporting re Wardell Armstrong report – re differing option – superseded. Not looking at taking option 5 any further forward.  Comments re CEFAS marine report – done.  JR action re SC remit – not done.  Examples where taken place – email with SR from CEFAS – SR CEFAS have not come back with anything – if mechanical dredge there will able a lot more settlement and could let settle for discharge – did not see need for any additional - DEFA to come back.  JR re flap gate closing for 6 hours after dredging finishes – CEFAS have come back re netting.  Re phase 2 – KM have quote to do work and project spec, but no one to manage.  Re water licence – have water licence - await waste licence. DEFA
7. Any Other Business AR asked who is coming to Monday meeting – DEFA unsure – TB said he would like some continuity - KM to check with Richard Lole. KM
8. Next Meeting Thursday 17 October 2019
Present:- Ann Reynolds, Director of Ports (AR) (Acting Chairman) Jeremy Reece, Senior Project Manager, DOI (JR) Mark Kenyon, Harbours Ports Manager (MK) Ports Project Coordinator, DOI (PC) Karan McHarg, Director of Environment, DEFA (KMcH) Paul Lenartowicz, Government Labs, DEFA (PL) Dredging Consultant, Anthony Bates Partnership (DC) Hydrographic Consultant, Anthony Bates Partnership (HS) Personal Secretary, note taker Apologies:- Tim Baker MHK Chairman (TB) Simon Renton, Environmental Protection, DEFA (SR) Distribution Attendees and apologies Tim Cowin, DOI Highways (TC) Stephanie Gray, Head of Waste Management DOI (SG) Malcom Cowin, MUA (MC)
1. AR opened the meeting and advised that TB had been unavoidably detained at Tynwald. However he had asked her to Chair the meeting.
2. Outcomes and recommendation from additional silt samples AR advised that following on from the meeting held 23 September with DOI and DEFA the remaining silt sample testing has been completed, with the results fed through at the beginning of the week. AR suggested that in reality, depositing silt at sea is no longer a recommendation / feasible. DC advised on up-dating his report accounting for the latest results and advised that undertaking further sampling or testing would not be worthwhile. DC & PL discussed amalgamating a number of sample results to provide average readings that would be below CEFAS Action Level 2. DC believed this to be acceptable but queried whether they would have to be combined and that a determination would need to be made by this Board. AR referred to the amount work involved to seek approval for sea depositing for only 4-5000 tonnes, accounting for the cost/work and time, and questioned whether it was a viable option. AR stressed that we need to keep to the
water testing is required to allow future depositing at sea to be agreed (See previous note). It was noted that that all of the above had covered 2, 3 and 4 of the Agenda.
5. Programme for approvals/contract award JR advised if going to Turkeylands, to plan for approval by Summer 2020, top allow transport of the first campaign of dredged material in Autumn 2020 to allow further dredging in January 2021. JR referred to some existing studies to be done that had been instrumental using CEFAS, Arcadia and Aitkens and queried whether the previously requested addendums following receipt of the latest test results is still required? Atkins already starting work and a quote received from CEFAS for the Arcadis report (not sure with CEFAS re on the marine side). AR advised that CVM isn’t necessarily off the table and recommended that the reports should be completed. JR referred to one outstanding piece of work from the Manx Wildlife Trust for Phase 1B, re: ecology survey at Cross Vein Mine. Approx half of the work is complete. It was agreed to continue the work.
6. Phase 2 update DC queried progressing with Phase 2. It was noted that Treasury had effectively put phase 2 on hold. It was noted that the latest sampling results indicate results on the surface samples are below CEFAS Action Level 2, with the exception of Lead and Zinc. JR advised that within phase 2 we could take a look at the source of the Lead and Zinc to target possible removal close to source, to continue sampling and monitoring and work up designated target sites. AR stressed that it is not our priority and that we will need to address phase 2 following approval to proceed with Phase 1A. KMcH advised on a meeting with the MUA to commission a review of the River Neb catchment, working with JBA consultants who will put together management options. JBA consultants are fully aware of the Peel Marina silt issues. KMcH informed on waiting to hear for a further up-date spec to include any environmental change. KMcH suggested of benefit for JBA to meet with JR/AR or the Board to discuss their remit. KMcH
7. Actions from the previous Meeting held 16 September 2019. Page 2 depth samples – JR done and DC up-dated the table. Page 3 environmental assessment / risk assessment for disposal site if silt deposited at sea - KM – noted not applicable.
Page 5 previous dispersal modelling report – AR - AR advised report was sent. Closed. Page 5 JR asked that test requirements out by end of tomorrow – KMcH, SR & PL – done. Page 5 materials that won’t burn – AR/PC – AR matter superseded, with meeting to take place. Page 6 circulate slides to the meeting – AR – AR advised that copies the actual slides that were shown at the DOI/DEFA meeting will be circulated. Page 6 AR to liaise with CEO re: write to Andrew Sidebottom – AR – AR confirmed action outstanding and will up-date. Page 7 – JR to work on remit re: CVM – JR – noted superseded. Page 7 – water licence DEFA – JR advised on receiving waste licence for lagoon. Closed. Page 7 – DOI/DEFA Meeting 23 September 2019 – KMcH – noted PL and Peter Duncan attended the meeting. Closed. AR
8. Any Other Business (a) AR advised on a meeting with Colas next week and will discuss options at the next meeting. (b) Availability Nutrient Testing – PL advised it may be relevant to progress and help with the Hydrological Risk Assessment re: Turkeylands. KMcH informed that SR has some work for WPN suggesting that he may want to speak with SG. AR suggested taking this piece of work internally. KMcH suggested that Colas will probably be undertaking testing with procedures and criteria in place and of the importance that both sets of testing use the same method. PL agreed to email DC a paper. (c) Treasury concurrence – KMcH queried when it would be likely that Treasury will be considering our re-submission. AR advised that Treasury have put the project on hold. Noted Independent Review is now completed and, AR advised that we need to re-submit with final recommendations, which currently (subject to further investigations) is the silt (de-watered) and destined for Turkeylands. JR advised that Treasury meet every week. (d) Socotec - DC advised that samples are currently being stored by Socotec and requested advice, noting that there is enough to do some nurtrient testing but not enough to do WAC testing. DC advised that Socotec to retain samples and nutrient testing requirements to be authorised, once a price has been agreed. PL
9. Next Meeting Thursday 14 November 2019 15.00hrs at Sea Terminal Building
Present:- Tim Baker MHK Chairman (TB) Ann Reynolds, Director of Ports (AR) Jeremy Reece, Senior Project Manager, DOI (JR) Mark Kenyon, Harbours Ports Manager (MK) Ports Project Coordinator, DOI (PC) Simon Renton, Environmental Protection, DEFA (SR) Paul Lenartowicz, Government Labs, DEFA (PL) Dredging Consultant, Anthony Bates Partnership (DC) Hydrographic Consultant, Anthony Bates Partnership (HS) Personal Secretary, note taker Apologies:- Karen McHarg, Director of Environment, DEFA (KM) Distribution Attendees and apologies Tim Cowin, DOI Highways (TC) Stephanie Gray, Head of Waste Management DOI (SG) Malcom Cowin, MUA (MC)
1. TB opened the meeting and apologised for the slight delay. JR advised that KMcH had tabled apologies but had provided an up-date for the meeting.
2. Phase 1B Update JR referred to discussions that had taken place between DoI and Colas looking at Turkeyland Old Quarry (TOQ) as a preferred site to deposit the silt and of a proposal to link to the Problematic Waste Facility Project. AR pointed out that discussions had started with Colas regarding the Turkeyland New Quarry (TNQ) however it was agreed not to pursue and revert back to TOQ. JR advised that TOQ had an overall potential capacity of 80Ktonnes and whilst the Department were working to store Problematic Waste (PW) at TOQ, there was capacity there for the Peel silt with possible capacity extension for the future. JR explained that there had been concerns with landfill liners degrading over time and the proposal to use 2 existing cells for silt and 1 for PW, with a future extension for PW was felt to be a better method than initially constructing 3 cells for PW. It was noted that SR had met with Colas. AR advised on bringing both strategies into one with a view to reducing costs and having options to expand capacity in the future. TB informed he felt comfortable with this proposal and it was a beneficial step in the right direction. AR advised that NB was speaking with the CEO of Colas, to negotiate contract
linked to organic content, which is higher in finer silt and lower in course gravels. MK advised the 2020 works are taking place out of season for algae bloom to happen and will involve the more coarse materials, so the risk is low. It was agreed that PL and DC discuss further in terms samples and types of analysis. All agreed that the risk of algae blooms would not stop the job (e.g. prevent dredging in April / May) and that steps are put in place to minimise the risk.
3. Phase 2 up-date Re: DEFA / MUA Catchment Study – JR advised that KM had sent through the scope that has been agreed from JBA, which outlined 8-10 weeks delivery time – JR to circulate to the Board members. It is unknown when the 8-10 weeks will start . PC queried on needing to know what the MUA are going to do. SR suggested it would be worthwhile for MUA to do some monitoring before any options are considered. AR suggested setting up a sub-committee to the PMPB to regularly report back, in the same way that Phases 1A and 1B can regularly report back. TB agreed. AR agreed to write to the MUA on the matter. JR AR
4. Actions from previous Meeting No30 held 17 October 2019 (a) Page 2 -Note of DoI/DEFA Meeting – TB advised on further meetings taking place with contents now superseded. No need to circulate notes. (b) Page 3 -JR to check indication of £20 per tonne – JR advised cost was built in. (c) Page 3 -DC to forward proposed nutrient testing to PL – noted the matter has now been covered. (d) Page 4 -JR to sent WAC surface test results to AR – JR advised done and copied to Colas. (e) Page 4 -JR to speak to Steve Butler, Planning – JR advised still to do and for Colas to give input (f) Page 5 -JR to review the costed options spreadsheet – JR advised done. (g) KM meeting with JBA – carried forward. (h) Page 6 –AR to liaise with Andrew Sidebottom – AR advised done. (i) Page 6 –PL to email DC re Nutrient Testing – noted done. Closed Closed Closed Closed JR Closed KM Closed Closed
5. Any Other Business No new issues raised.
6. Next Meeting Thursday 12 December 15.00hrs STB Noted 2020 dates to be calendared in remaining on the second Thursday of each month.
Present:- Tim Baker MHK Chairman (TB) – left 1630hrs Ann Reynolds, Director of Ports (AR) Jeremy Reece, Senior Project Manager, DOI (JR) Mark Kenyon, Harbours Ports Manager (MK) Ports Project Coordinator, DOI (PC) Paul Lenartowicz, Government Labs, DEFA (PL) Andrew Lees, Director of Agriculture & Lands, DEFA (AL) Neil Gray, Environmental Protection Officer, DEFA (NG) Dredging Consultant, Anthony Bates Partnership (DC) Anthony Bates Partnership (AC) Personal Secretary, note taker Apologies:- Hydrographic Consultant, Anthony Bates Partnership (MM) Karen McHarg, Director of Environment, DEFA (KM) Simon Renton, Environmental Protection, DEFA (SR) Distribution Attendees and apologies Tim Cowin, DOI Highways (TC) Stephanie Gray, Head of Waste Management DOI (SG) Malcom Cowin, MUA (MC)
1. TB opened the meeting and welcomed all to the meeting noting some new attendees. Introductions round the table were made. It was noted that AL is representing KM. AR advised that AL will be receiving an invite to attend the Sub-Committee of the Peel Projects Board focusing primarily on Phase 2 works/initiates. AR
2. Phase 1A Update DC up-dated the meeting by advising that the Design Team had met with Land & Water Services (LAWS) today on Island to discuss contract details and contract signing. It is currently planned to finalise the contract and LAWS to sign by next Friday 20 December 2019, to be returned to DoI to sign. DC referred to issues surrounding the level of Professional Indemnity insurance that LAWS have recently highlighted and their issues in securing £5m PI cover. LAWS have agreed to send an email to DC which will be forwarded to JR putting forwards options for discussion on levels of cover, which hopefully will be acceptable. TB queried if this was going to be an obstacle as we will not be going back to Treasury. JR referred to insurance industry changes following recent incident (e.g. Grenfell fire) that has affected the insurance market. DC
TB queried when will we be able to start dredging. DC advised dredging can be done as soon as lagoon is built currently planned for 4 March 2020. TB queried any risk around building the lagoon. DC informed it should be straight forward and the long-lead item (clay liner) has already been ordered. TB confirmed that the Minister is keen to progress. TB queried how long to complete the first campaign. It was noted ca64 days with a view to finish before TT week. NG advised DEFA were happy with this timescale. PL advised that he could see no reason why the timetable cannot go ahead. DC informed on having fisheries approval letter. The Waste Licence only needs the contractor’s working plan to finalise. MK has drafted the Harbours approval letter and will draft a circular for the Marina boat-owners (to be released after press release w/c 6th Jan). JR advised on working with DC and Steve Butler on satisfying the remaining planning conditions. Harbours Preparation - MK advised until we have drawings of the areas of occupation and phasing of works he felt that there is little benefit of going public. MK advised on a meeting with Bob Stimpson (MUA) as they are planning to carry out a phased work programme on East Quay. MK pointed to a few logistics to keep an eye upon. AR confirmed that she has warned the Harbour Users Association (HUA) of the impending works and requested assistance with communications with boat-owners to move their boats as they had done in the past. TB noted lots of engagement between the DoI and MUA. AR advised that the MUA attend the Sub-Committee and are up to speed with the Project. Campaign 2 - JR advised that this is currently planned for early 2021 (13 January 2021). TB noted if went to plan the works would run through 14 April and queried any issues with this. DC advised there shouldn’t be as the programme holds a little bit of breathing space within. DC MK JR/DC
3. Phase 1B JR confirmed that work is progressing. However, as outline earlier, there is a chance/risk that Turkeyland won’t be ready for November 2020 as currently planned. JR advised that having taken advice from Colas and others who have recommended that you shouldn’t build landfill sites during the winter months. That said, JR added it still could fit in with our plan for the second dredging campaign starting in January 2021. AR always good to aim for plan A and have a plan B as a back-up. TB queried introducing incentives when negotiating the contract either build a bonus payment or include penalties - JR agreed to take forward. TB referred to the meeting with Colas where they appeared to be ready to take on the project. TB stressed on the need to determine the type of Planning Application Colas has submitted in terms of details especially if we want it operational by November 2020. AR queried on delays with submitting an outline planning application. TB suggested it could take twice as long as the application has to be considered twice. JR
4. Phase 2 Up-date JR reported on his attendance at MineXchange Conference in Aberystwyth, which focused on remediation of heavy metal mines.
JR reminded the meeting the more we can do now, the better, as it takes time for the river to naturally flush through. JR advised that our levels are lower compared to some other sites in the UK featured at the MineXchange conference. PL queried if the problem is coming from the surface could we put something on top of the land (ie concrete or other material). JR suggested using the clay liner from Peel Marina lagoon at CVM to stop the water seeping through. JR confirmed he will invite the Coal Authority over to give advice as they are not looking for any professional fees, just flights and a hotel. JR
5. Actions from previous meeting No 31 held 14 November 2019 (a) Page 2 – AR to email NB re: Treasury Meeting and JR to speak to Andrew Sidebottom, Treasury – done. (b) Page 2 JR to share first part of the strategy report – done. (c) Page 2 – AR to invite SR to speak with Colas – done. (d) Page 2 – JR to speak with Stephen Parry on comms plan – done. (e) Page 3 – JR to prepare brief on worst case if Treasury approval not forthcoming – JR advised we got the approval however was otherwise prepared. Done. (f) Page 3 – PC undertaking water monitoring – done. (g) Page 3 – PL and DC to confirm spec for nutrient testing – done. (h) Page 4 – JR to circulate DEFA/MUA catchment study – done – JR advised that KM is waiting to hear back from JBA regarding when planning to start. (i) Page 4 – AR to write to MUA on new Sub-Committee to PMPB – AR advised on first meeting held 10 November 2019. AR added also has a representative from DEFA. (j) Page 4 – JR to speak to Steve Butler, Planning re: Colas and Environmental Assessment – done. (k) Page 4 – KM to meet with JBA - done. KM
5. Any Other Business (a) DC attendance at PMPB – DC advised that he will be attending these meeting in person more often than not going forward into 2020. DC advised on giving a proposed schedule to JR.
6. Next Meeting Thursday 16 January 2020 – 1500hrs – STB Boardroom
Feasibility Study - Project Board 12 12 2019 (2).pdf
1. Welcome and Apologies Apologies received from:- Ann Reynolds, Director of Ports, DOI (AR) BW confirmed with TB that it was acceptable for KK, SR & NG to attend the meeting to answer any questions directly.
2. Notes of previous meeting held 3 August 2017 were accepted.
3. Progress discussion/update SG referred to the Brett Associates Report, a copy of which was handed to TB. SG said of the need for DEFA to talk to Brett Associates and said that the issue we have is that the classification is dependent on the amount of material that is analysed. SG recommended that, whilst this analysis is not conclusive we (prudently) assume the material as ‘hazardous’ and speak to DEFA about what is required, and also do additional analysis. KK said that it is wise for the lab to consult with Planning regarding minimum assessment requirements. KK stated that previously an assessment was made to see if material was fit for deposit at sea (sieve 2mm); landfill needs to look different criteria and leaching rates on a net weight basis so therefore need to know moisture content. SR said that of primary importance is that we know it has hazardous content (primarily lead) so need to know what will leach and the risk to the environment – looking for Hydrological Risk Assessment. SG spoke about EWC Codes. NG spoke of stable, non-reactive hazardous waste with the need to know if it will leach – KK said that leachate will have contaminants. SR said that a planning application will be required. If dry enough thinks it will be acceptable to dispose of in WPN. SR queried IOM Waste Regulations,
further work to consider this. TB said of the need to look at further tests and get Abilene Snowe to talk to SG/KK etc. TB summarised that we now had the following workstreams; (1) Treatment trial (Abilene Snowe) (2) Wrights Pit North planning application (3) Removal of river deposits (4) Geotextile bag storage. Noted estimate of 20,000 cubic meters to be removed. SG said of the need for indication of amounts for business case. KK said of the need to make an accurate assessment with a bathymetric survey– and work out a deposition rate from that. MK indicated that he was satisfied with the current method used to calculate the current figures and future deposition rates were heavily weather dependant. SR said EPU to put in writing what we need to move forward with planning application. SG to speak to Planning. Need to know indication for number of vehicle movements. TB said to (prudently) do calculations on filling WPN with as much as you can, based on what space is left over and above what is needed for other materials. TB advised that a business case needs to be done for the whole solution, not just WPN. It is vital that we look at this as a holistic process not individual items. TB also reminded the group about the forthcoming Department P&S meeting on this subject and invited BW to attend if available. KK asked if there were any thoughts on a future facility. BW advised that this would form part of the second part of the project. TC presented chart outlining relative costs and advised that previously it cost £285k to remove 10k tonnes. The following figures were outlined: Dumping at sea £7 a tonne Landfill £22 a tonne EFWP £86 a tonne Abilene £95 a tonne
4. Summary of potential way forward Based on the above discussions, there is a potential way forward, which can be implemented in 2018. Approx 20,000 tonnes of silt needs addressing. Extraction to commence in early 2018 and to be done in a controlled manner over a 2-3 year period (which suits harbour operations), using an extended 9 month per annum window (DEFA Fisheries likely to consent, subject to appropriate ‘silt screen’ methodology). Proposed solution has several elements:
1. “River channel area” (c.3,500 tonnes) can be extracted immediately as it is not hazardous and could be washed and recycled (subject to assistance from JCK/Colas). This would also partly mitigate the further build-up of silt in subsequent years and would show early progress 2. Abilene Snowe trial (initial trial c.4,000 tonnes) – needs further scientific/data analysis before commencement, however agreed that this approach has merit. 40k investment to conduct trial is money well spent. If successful it opens up some very interesting long-term potential solutions, which could also deal with more of the accumulated volume of silt. Trial must be progressed to either confirm or eliminate this methodology. Trial to be conducted using “fresh” silt extracted from Peel and process to take place on Fenella Beach car park. Target start date of January 2018. 3. Wrights Pit North – dewatered silt can be disposed of to landfill at WPN up until end 2019 and possibly 2020, subject to planning consent being obtained (assumption is that consent can be achieved but planning application MUST show that all non-landfill options have been explored and fully considered). Currently the site is below capacity and, in the absence of the silt being disposed there, would require additional material to bring it up to the required restoration levels. Vital for DEFA that material is appropriately dewatered – but more gradual approach now proposed facilitates this. 4. Geotextile bags – can potentially be filled with extracted silt and utilised for coastal protection around Kirk Michael area. Will require protection with concrete to extend their useful life. Would fill the bags at KM. Avoids disposing of the silt in other manners and has a double-benefit in avoiding expenditure which would otherwise be incurred in due course on coastal protection. Needs fully exploring. Whilst further work is required on each of the above work-streams, discussion provides confidence that, in combination, we have a potentially viable solution that will deal with the legacy silt accumulation from 2018 in a controlled and manageable way and could provide an ongoing long-term solution, along with the other options previously identified. Initial focus is on the immediate 2018 priorities and we can then re-assess the longer-term solution in the light of the learnings from 2018. Note: As part of this longer term planning we need also to assess whether there is any potential in the Foxdale ‘deads’ aspect mentioned in 3 above.
Next meeting to take place on Thursday 12 October 2017 at 1500 hours. Thereafter meetings also calendared for 2 November and 7 December.
1. Welcome and Apologies Apologies received from:- Ann Reynolds, Director of Ports, DOI (AR) Emma Killip, Project Manager, DOI (EK) Stephanie Gray, Head of Waste Management, DOI (SG)
2. Notes of previous meeting held 3 August 2017 were accepted.
3. MK said that we need to face up to the fact that we are not going to be commencing dredging on 1st January 2018. Even if a site was identified today the preparation of the disposal site together with the requirement to procure the physical work and mobilisation means that we are out of time Referring to the recent P&S, TB said he was confident regarding the river dredging. BW advised that SG had been referring to samples taken on the river stretch where the gravel is. If we get the go ahead from operators at Turkeylands there are ways and means of being able to start the process as there is an element of recycling. BW said that there are smaller portions of reusable materials further down the river flow and all depends on JCK/Colas support. BW said that he would give a letter of comfort. TB noted to focus on the channel. MK said that the best way to achieve any progress dredging early next year is via a land based excavator working in the channel from the West Quay. The chances of tendering for vessels to mobilise and be involved were slim. BW said that he would be happy if we had concentrations that would break-down like last time, ie 90% reusable. MK stated that the nature of the material would change as progress was made down river reducing the re-usable element. BW said that during the operation in 2014 the water used to wash the dredgings was considered to be contaminated water so a licence was given for the liquid fraction to be tankered to a manhole in Balthane, and he would be more comfortable if JCK would do it having been involved previously. Meeting agreed for AR to speak to JCK about washing/recycling of material from the river stretch. However, conclusion was that the area of the river channel that BW was happy to be dredged was upstream from that which AR
MK advised was crucial. Therefore, whilst feasible, it would not significantly enhance the marina to dredge this area at this stage. BW and MK spoke about the possibility of retaining the dredged material within the marina in a contained area. Noted cost of piling was prohibitive and impacted seriously on the marina operation and berth numbers. TB advised that someone had contacted the Minister regarding the old brickworks quarry further up the river. BW said that this has previously been looked at, and was a viable option, but a lengthy process would be required as the quarry was water filled and owned by a private landowner. MK said that it would be the ideal site if the Government owned it, but was concerned that the area may be considered a nature reserve. BW said that land ownership is an issue but it is worthy of further exploration given its proximity to Peel Marina and potential to pump direct and use a closed system. TB to speak to AR to explore further. MK highlighted the very high road lorry miles to take material to Wright’s Pit North via a number of villages which in itself could have significant environmental issues. It would be likely that delays would be caused by consultations and safety concerns based on experiences during the ’Rockmount’ process. MK spoke about the small bridge in Peel being rebuilt during 2018 and of a temporary structure across the river which may cause access problems. TC added that any temporary structure would be able to carry wagons. TB noted river stone dredging is not going to do much to impact our problems overall – BW said that we would not get support for further down the river since the material lacked much in the way of re-usable aggregate. MK advised of 5,000 tonnes needing to be removed from the river stretch alone down to the fish pass. Workstream TB said of the need to explore brickworks quarry. TB
4. Workstream updates (a) Abilene Snow treatment trial MK told of having received an email from the company that morning in which Abilene Snowe described having been in contact with Kev Kennington, who is now apparently happy with the process as described. Noted Non-Disclosure Agreement signed. TB noted more work needs to be done. MK informed that contracts/ planning/permissions/ mobilisation were all required and all will take time. Business case will need Treasury approval. (b) Wright’s Pit North BW advised that the Environmental Protection Unit found the environmental impact study from the original inert landfill application and with one or two amendments felt the pre-existing EIA & GO would be suitable. It was noted that SG wanted to go ahead with Fate and Path analysis. MK said that the biggest impact on the environment is going to be the road
delicate from fisheries perspective.
5. Management TB said of the need for a more coherent proposition before establishing more formal project management arrangements.
6. Any Other Business 6.1 BW suggested BW/TB/Karen McHarg meet to see what KH would agree to. 6.2 Turkeylands – noted AR doing work with Colas/DOI re lease arrangements. BW advised that Neil Gray, new DEFA Environmental Protection Officer saw the facilities at Turkeylands and asked why we are not using this as they were in his opinion ideal. BW to speak further to NG. TB to progress with AR. Specific additional Workstreams: (a) Turkeylands (b) Brickworks quarry (c) Rockmount (d) Deads BW/TB TB/AR
7. Date of next meetings 2 November 2017 then 7 December 2017
1. Welcome and Apologies
2. Notes of previous meeting held 12 October 2017 were accepted.
3. Update on subsequent developments (a) 18 October meeting TB said that the Minister was keen to make sure we have momentum. Noted that there was a P&S held in September which gave an update of work which was very positive. Further Project Board meeting held on 12 October which refined thinking. Minister suggested we should meet and ‘take stock’. (b) 27 October pink paper Noted Minister/CEO/TB/AR met on 18 October to talk through options and put together a coherent plan, where the Minister suggested to consider also option of Peel Brickworks Quarry. TB said that the meeting resulted in a pink paper which has been signed and will be circulated to this group. Paper focused on options with clear preference to go for a solution which is sustainable and fulfils environmental issues. TB said there were three resulting short term preferred options; (1) Geotextile coastal protections, (2) Mining remediation (the deads); and (3) Abilene Snowe trial (or similar), which are where the Minister wants us to focus. TB stated that if solutions are viable and successful for 2018 then they are also applicable beyond 2018. Three landfill options also need to be worked on as a contingency, however of these Turkeylands is more problematic. TB said that whilst we have landfill solutions possibly available now, they are not going to be going forward long term. Longer term options around silt traps/canalisation also need be looked at, however need to focus on present situation. AR stated that part of meeting on 18 October was to look at ability to go to Treasury for funds, and as part of the business case would need to take silt Sec
4. Workstream summary (a) Geotextile coastal protections To be run alongside coastal erosion environment. Led by DOI. (b) Mining remediation (the Deads) DEFA to take lead. BW said that if ‘deads’ proposal is successful, needs to be disposal path for sediments. (c) Abilene Snowe trial DEFA to take lead. AR to do PIN (and business case once idea on funding requirements known). (d) WPN SG to do detailed piece of work and scope out what is involved. (e) Peel Brickworks Quarry BW said of the need for this to be fully explored. (f) Turkeylands Contingency planning only. (g) Longer Term Options Engineering-solutions and landfill DOI DEFA DEFA SG
5. Date of next meeting 7 December 2017
1. Welcome and Apologies Apologies Bernard Warden, Director of Environment, Safety & Health, DEFA (BW)
2. Notes of previous meeting held 2 November 2017 were accepted.
3. Progress update on preferred potential solutions for 2018 TB said of there being three preferred sustainable solutions, plus other fallback/long term positions, and stressed that the Minister wants us to focus on the three solutions below. AR said that she had met with JR as was looking for a coordinator. AR stressed that Emma is a Project Manager who will be doing the day to day management, ie they are 2 different roles. (a) Geotextile coastal protection AR advised of a meeting scheduled to take place next week with JBA regarding scope of viability assessment with regard to the use of geotextile bags. Discussion took place regarding issues and looking at using at Kirk Michael. JR queried JBA timescale – AR advised of information to be received by the beginning of January. PS informed that there are 2 main areas to consider; (1) do they provide the coastal defence we require; and (2) would they hold the silt. There are some issues at Kirk Michael which make the use of the bags challenging and would they perform what we need to do at that location. Other area of concern is, would they contain the pollution? PS said that he is not convinced they would. SG advised that sampling has been done and contaminants are very small. PS stated that geotextile bags have to have a permeability which will let 40 microns minimum to pass. PS said that material has to be reasonably ‘soupy’ and in order to make work can be used as underwater reef or in a
Actions TB stressed the need for AR to push regarding the Expressions of Interest. TB to talk to Abilene Snowe. Find site in Peel. MK/TC to view Mill Road area.
Progress update on other potential solutions (a) Wrights Pit North SG advised of having done a project plan and would take 12 months to get planning permission including required background research and moisture content analysis. Looking to contact JCK with regard to long reach extraction for trial. Bore holes progressing. Joint bid with Highways. Work in progress. Had meeting with DEFA regarding additional information who are happy and fully aware of content. TB asked when anything visible will be done – SG said of the need to contact Peel Commissioners regarding scooping out which is one day’s work and will also need to speak to Bride Commissioners. TB suggested a draft communications plan was required before starting communicating – SG to progress re WPN. Noted JR doing comms plan for whole project. It was noted that facility is to close 31.12.19 therefore 12 months to put material in. SG said that there is space for 19,000 tonnes – MK advised of 10,000 tonnes in Rockmount. SG said that the decision as to what goes in is a political one. (b) Peel Brickworks Quarry AR advised that JBA are to look into this matter and that it would need planning, environmental impact study, discussion with owners and viability. Could use river into that area and re-route. Do have 850m worth of piping. TB queried whether this could be a long term silt trap (settlement lagoon) or long term disposal route. (c) EFWP Noted not progressed as a workstream. SG said that she has mentioned it to EFWP and will speak to them next week about how much they would need to do a trial. SG advised that an organics test is being done.
5. 2018 Approach Extraction & Dewatering TB said that whatever the chosen disposal route we will need a contractor to extract silt. AR said she thought a framework had been commenced. AR to check. TB queried lead time – TC said that if in framework it can be done quite quickly, and over £10k have a different process to follow. Formal tender over £100k and 3 quotes if under £100k. TB asked when we need to start the procurement process to get material out of the harbour. TC said that if the framework is in place we need to appoint someone off the list. AR to check and send out results. JR advised that drafting takes time. AR
6. Any Other Business JR to pull together Project Programme of all options and show critical path and circulate draft for comments. JR
7. Date of next meeting 11 January 2018
1. Welcome and Apologies Apologies received from:- Steve Butler, Head of Development Management, Planning Dept, DEFA
2. Notes of previous meeting held 7 December 2017 were accepted.
3. Progress update on preferred potential solutions for 2018: (a) Geotextile coastal protection AR advised that she has met with JBA to discuss geotextile coastal protection, silt trap and Peel Brickworks Quarry regarding scope and viability. Budget is £10k. AR said that JBA want to speak to DEFA and the Quarry owners. JBA require 3 weeks from order being placed. AR stated that JBA have queried if DEFA would approve of use of the quarry, if recommended – BW said of the need for a discharge licence and that PAH’s would be a problem, however PCBs in the marina are negligible. AR advised of having received a report back from Colas with regard to materials currently stored at Turkeylands – BW asked for a summary – AR to send out. (Post Meeting Note – the report from Colas was not finalised so once received AR to send out.) It was noted that the brief is still outstanding for Kirk Michael. (b) Mining remediation – The Deads BW advised that SG was trying to set up a site visit for TB for the week after next which should be seen as a positive. There is a large area that needs to be covered. However strength of the off-road motorcycle lobby is a disadvantage. BW said that it would have to be properly engineered and landscaped. It was noted that contamination levels are 8 times more concentrated than the material in the marina. BW said of a cautionary note being the motorcycle lobby and potential safety
issues with unknown mining shafts. Environmental impact assessment would take a year to complete. TB noted that the Deads approach has real potential from a DEFA position. BW said that it has to seriously be considered and it would get support as a solution for Peel silt. TB said of being cautious but encouraged by this option. He also stated that alternative arrangements could potentially be made to accommodate any impact on the off-road motorcyclists – so that should not prevent us pursuing this solution. (c) Proposed treatment trial AR referred to PIN-v-EOI approaches. JR said that he has spoken to 2 dredging contractors, one who has a specialist team. TB asked why we cannot write a tender document – JR said that the issue is difficult as to what to write now as we currently don’t know which option (ie process) to tender. BW asked what would stop us from saying what we have and what we need to achieve, ie below OSPAR1. MK said of the need to make sure DEFA are happy with what we are doing, ie material down to recommended OSPAR level. BW said that if contaminants are below OSPAR1 then DEFA would be relieved. JR stated that we could find already proven methods. AR said that we can ask in the PIN for figures/accounts, etc. It was noted that AR has drafted a pink paper re PIN. TB said of the need to do some proper PR when we undertake works. JR said of the need to think about options regarding material at Turkeylands and Rockmount – TB said that his only concern is we don’t lose focus on what we are trying to achieve at Peel. TB said of ‘one hit’ or ‘phased approach’ to be outlined in the PIN. JR said to not make too technical. TB stated that a press release has to be good thing and of the need to have a big picture and then determine detail once we have solutions. JR asked is OSPAR1 is more or less restrictive if land based – SG said that it is not specific as some are classed as hazardous. BW said that if reduced to almost OSPAR1 the material could go to somewhere that takes asbestos. It was agreed for the contact points for the PIN will be EK and JR. TB asked JR to start an information pack. AR to speak with Richard Parslow re press release. JR AR
4. Progress update on other potential solutions (a) Wright’s Pit North (c) EFWP Noted SG is currently doing work re WPN (12 month process). SG said contaminant would have to be inert, however WPN does not have the capacity to take all material. SG informed of progressing with background information with DEFA. Issue is the moisture content of the silt. Plan to take 4 scoops from the harbour and then drive around to be able to determine the moisture content. SG said that there is a lake at the side of WPN with works ongoing with regard to this, and also looking at average composition of the silt. SG to do working methodology and contact JCK re SG
long reach excavator. JCK continuing aggregate sampling (ie clay) for trial with EFWP. TB said of the need to excavate and take aggregate out and dewater, the residue of which could have potential to go to EFWP. SG said that this would have to be a long term solution. SG to explore with JCK. BW highlighted inflexibility with Glashen Stream and possible issues with Derbyhaven. (b) Peel Brickworks Quarry To be covered as part of JBA works.
5. Any Other Business (a) Haulage framework AR said that this includes carriage of contaminated dredged materials. (b) Dredging period TC highlighted that we are now in this year’s dredging period which runs to June. (c) Dredging framework JR asked if we currently have a dredging framework in place. Noted there is no existing framework. (d) EFWP JR said of the need to agree scope of EIA with development management and consult. (e) Abilene Snowe TB said of having been chased by Abilene Snowe and of having explained context. AR to contact Abilene Snowe re PIN details, and to progress communications that way. (f) Complaints – current state of Peel Marina MK said that we are likely to start receiving a lot of complaints from Peel boat owners as unlikely to get any dredging done in 2018. (g) Short Term resolution TB asked if we have any short term resolutions – AR said that a debris screen has been requested by IOMHUA, and was to be part of advice received from JBA. BW said that this would need input of DOI Engineering colleagues. CLOSED AR
6. Date of next meeting 8 February 2018
1. Welcome and Apologies Apologies received from:- Bernard Warden, Director of Environment, Safety & Health, DEFA (BW) Steve Butler, Head of Development Management, Planning Dept, DEFA
2. Notes of previous meeting held 11th January 2018 were accepted.
3. Progress update on preferred potential solutions for 2018: (a) Proposed treatment trial – update of PIN (JR) JR advised that the PIN has been released with closing date 14th February. It was noted that the PIN was picked up by Dredging Today website which has resulted in it going far and wide. EK said that there had been 12 responses as of last week. JR stated that generally the responses are from people/companies that seem to think they can do something. Issue may come from whether works can be undertaken by land or water, as land based works may require planning permission. JR spoke about being asked about material composition, etc. JR asked who we want involved in evaluating the responses – AR suggested that JR/MK/EK would be sufficient – SG suggested someone from DEFA to also be involved – meeting agreed. JR to arrange PIN review meeting JR has approached three dredging / marine specialist consultancies for quotes to help evaluate the responses, with the cheapest quote being just under £5k to review up to 12 responses. However they have also included a site visit and attendance at a Project Board meeting which AR/TB did not think was necessary, ie a report would suffice. TB wanted a controlled process and to come back with proposal of how to move forward with a summary produced and high level overview. TB noted that from the PIN we will end up with the information necessary to make a decision on the way forward. JR said that the objective is to understand if a chemical cleaning up process is viable which can then guide what we put into the tender documents. JR
on fees for affected boats in Peel Marina as per last year. Interim meeting on 22nd February to be held to discuss the outcome from the PIN. TB stressed that he does not want the programme to slip more than is essential. (b) Geotextile coastal protection and Peel Brickworks Quarry (AR) AR advised of not having yet signed the scoping report with JBA re geotextile bags, Peel Brickworks and silt trap. Report will take 3 weeks from placing order and she expected the scope and price back imminently. TB queried if Paul Salmon had looked further into coastal erosion – TC said not yet. AR said that she has advised JBA that we need to know tomorrow and will then look for another consultant to pick up if JBA are not forthcoming. (c) Mining remediation – The Deads (BW) Not aware of any progress being made. JR to liaise with BW regarding possible support to ensure this can move forward (d) Programme update JR said that the programme is dependent on whether planning permission is required or not and are currently on programme with the exception of JBA reports. It was noted that SG’s work re Wright’s Pit North is also mapped. Programme does not yet include any details on DEFA – The Deads or use of geotextile bags. TB asked if there if anywhere as a fall back – TC said possibly the quarry. JR informed that in one of the example projects, silt was pumped 6km on land and queried where we could drive/pump to. TC said that Poortown quarry is under the Department’s ownership. MK said that it would require several supplementary pumps to pump. AR JR
4. Progress update on other potential solutions (a) Wright’s Pit North SG advised of having met with Steve Butler and agreed the scope of EIA. However it will need full planning permission due to the nature of the planning approval, as cannot vary the use of the land. It was noted that originally the plan allowed 12 months for restoring the site. However it is likely the PA will request permission to infill until June 2020, giving an additional 6 month extension for filling (to June 2020). Hydrological risk assessment (HRA) was mentioned and AR agreed Ports will fund £14k for HRA. SG said of the need to get additional sampling from the Marina to advise the HRA modelling. (b) Peel Brickworks Quarry To be covered as part of JBA works. (c) EFWP JCK happy to undertake trial. SG said that once material is washed it needs to dry out and could then be drip fed into EFWP. SG asked about the nature of the material on an annual maintenance dredge. TB stressed that this is not going to give a solution for next year’s challenges. JR said that it needs AR
to be worked on in the background. TB stated that EFWP is a longer term solution, along with silt traps and canalisation.
5. Any Other Business (a) Peel Commissioners - AR advised of having sent email to Peel Commissioners regarding the PIN and was waiting for a date to meet with them. TB said of the need to consider how and when to communicate. (b) Press release - TB queried when we need to put a summary out about where the project is going, once decision has been made. JR to brief new Communications Manager (Steve Parry). JR
6. Date of next meeting 8 March 2018 Interim meeting to discuss PIN to take place on 22 February 2018
1. Welcome and Apologies Apologies received from:- Tim Cowin, Head of Highways and Asset Management, DOI (TC) Stephanie Gray, Head of Waste Management, DOI (SG)
2. Notes of previous meeting held 8th February 2018 were accepted. Matters Arising from previous notes: (a) Ownership of sections of land for possible use JR said that EK/JR met with Paul Slinger regarding funding, with recommendation being to make an application to Treasury for contingency funding, which would not need to go through Tynwald for approval. It was noted that TC has investigated the ownership of the land and has a name and address, however no approach has yet been made to the farmer. TB noted that if a land based solution is required, it is worthy of exploration. JR said that Fenella Beach car park could also potentially be used – MK said that this could be controversial. (b) Capital Procedures JR/EK discussed this with Paul Slinger and concluded that as this project is not a typical civil engineering / building project, the full capital procedures for civil engineering works would not need to be implemented. However some reporting procedures would have to be followed and will be agreed with PS when funding is agreed. (c) Initial Business Case Noted AR forwarded a copy of the initial business case for reference to JR. (d) JBA AR advised of having originally met with JBA but the scoping of the works had been delayed by JBA as the person who was writing the scoping Closed
document was off sick. AR noted she was not happy with the scoping document, as it did not fully reflect our requirements. After subsequent meeting with JBA, a purchase order will be issued today with works to commence on Monday and will take approx. 4 weeks. AR has approached the landowner to advise that they will be contacted by JBA. JBA will also contact BW. TB stated that we have taken a wide approach and need to be clear at looking at all options. (e) Mining remediation – the Deads BW advised that a visit is planned for tomorrow to see/look at the potential. (f) HRA funding AR informed that a purchase order has been supplied for the hydrological risk assessment. AR said that she has queried with SG what happens if we need anything further. (g) Press Release JR said that he has spoken to the DOI Communications Manager (SP) to give an update and that he is thinking about how to approach. It was agreed to await definitive decision of works before publicising. AR Closed
3. Evaluation of Prior Information Notice JR outlined the background for the PIN and reminded all that Abilene Snowe approached the Department regarding their process and wanted us to fund a trial, which would tie us in commercially for the remainder of the material. This would require an FD8 waiver on the basis that Abilene Snowe were the only potential supplier and the PIN was developed test the market to establish if they were the only company able to provide such a service. The PIN asked interested companies to tell us about their capabilities and how they would tackle Peel Marina and were asked to complete a pre- qualification questionnaire. 18 submissions were received, 12 of which were of significance, and 6 from local companies submitting their interest (which were noted). 12 submissions were looked at in detail. Each company was asked to indicate if they were interested in dredging, treating or both, with majority able to do both. Also asked to tell us would they be able to treat the contaminants to below OSPAR level 1 and could they treat on land or sea. Basically, the summary is that it was questionable of being able reduce contamination below OSPAR levels to dispose at sea, but reuse / disposal on land appears to be achievable. All were asked to indicate whether treatment could be undertaken on water (pontoon / barge) or on land. All but one indicated land was required, so establishing seems to be a requirement to be able to move forward. BW said that he has met colleagues and tried to get some answers and has looked at various options and the impediments and unfortunately most of the options being considered would need full planning permission. AR queried if material could be dredged, treated and then taken away, ie if only temporary would planning permission still be required. BW confirmed there is a 30 day threshold for “temporary”. BW advised that proposal should be put forward
review all ongoing options again in 2 week’s time at the next meeting. TB did not want any option closed down until we know more of the future.
4. Progress update on other options: Wright’s Pit North SG advised, via email sent prior to meeting, that the Hydrological Risk Assessment has been placed and awaiting confirmation from DEFA that the sample locations proposed are adequate before completing the sampling methodology statement and organising work. SG/AR to meet with Peel Commissioners in advance to advise of the works. NG said that in the next 2 weeks we need to know if the lab has bought the bit of kit and relative samples can be taken from the harbour and western lake. DEFA AR/SG
5. Any Other Business No matters raised.
6. Date of next meeting 23rd March 2018
1. Land Update JR advised that the land owner of the fields is [redacted], and that he has been in touch with the Minister with regard to meeting. JR has spoken to MUA to find out some background information and discovered that it was not the easiest of dealings with the landowner, and also that planning was an issue due to a neighbour. JR said that the Department should consider options for leasing the fields, as well as purchase. JR outlined an additional option a field which is owned by [redacted], and access could be created through the MUA site. TB queried if able to pump to this area – JR & HS confirmed it can be done but preferred method being to dredge with a closed bucket, as the volume of water increases significantly if pumped and all water will need to be treated before return to river / marina. DC raised concern about the use of some flocculents and the need to look at the environmental impacts.
2. DEFA PAPERS Remediation Paper DC advised that a working trial is being assessed and that works would have to be undertaken to engineering the site at the Foxdale Deads and include blocking up some drains. Forestry have worked on Environmental Impact Assessments which would have to be concluded. HS queried salt content – DC said that this would have to be looked into, however there is an option to put top soil with the appropriate Ph content to cap the silt. TB reminded all that the land is heavily contaminated already, at a higher concentration than the silt material, and that the land is the source of the majority of heavy metals that end up in Peel Marina. DC explained the issues of vehicles churning up the soil and that water samples were taken last week which showed lesser where soil is not churned up. JR queried the timescales for geological and EIA survey. DC said that EIA species will need to be looked at and that a breeding birds survey would take the longest period of time, with the need to start as soon as possible, with
project costs. TB queried pumping to the field and drying out and also whether it needs to be kept covered – HS confirmed it is very rarely covered as some of the drying process is evaporation. TB asked, if dried out, can the material be put straight onto the Deads – all agreed it appeared feasible. JR highlighted the need to manage rain water run off, so the drainage water treatment process (capture & treatment, if necessary) will be required throughout the length of the drying out process. JR told that Neil Gray was to look at leachate tests at Rockmount and could be based on samples taken at Rockmount. TB stated that if we can acquire use of the privately owned land then we potentially have a solution. HS said that if renting the land, the land owner will require indemnity due to remaining contamination and testing should be done on the land prior to use to be used as a baseline. JR said of assessment of costs missing. HS estimated that this process is approx. a quarter of the cost of chemical treatment process. JR/TB agreed that the way forward was to identify feasible options, then costs estimation carried out. JR queried how far material could be pumped – HS said one kilometre, however may need an interim pumping station, if up hill. TB asked if the contactor would provide this, ie from dredging to delivering to field – HS replied yes. All discussed the need for a package of works to offer to the market, and once agreed with the [redacted], could potentially go for Early Contractor Involvement due to the need for detailed site development for planning. HS advised to think about the dredged material as a resource, rather than a waste, ie remediation material. TB confirmed the following approach; Phase 1 – Dredge, pump, dewater & hold Phase 2 – Transport, spread & remediate Once this has been developed a bit further, funding requests should be submitted for all the works (including The Deads remediation works by DEFA). TB requested that HS develop an outline proposal for the field site, to allow discussions with [redacted] and planning. JR / HS to discuss timescales and costs separately All to note HS
Next Meeting Next full Project Board Meeting – 12th April, 3pm – West 1, STB
Number Date meeting took place Date meeting originally scheduled (subject to rearrangement) Comments
1 4th May 2017 - Inaugural meeting of Project Board
2 - 25th May 2017 Meeting cancelled
3 29th June 2017 Options attachment enclosed
4 3rd August 2017 3rd August 2017
5 7th September 2017 7th September 2017
6 12th October 2017 12th October 2017
7 2nd November 2017 2nd November 2017
8 7th December 2017 7th December 2017
9 11th January 2018 11th January 2018
10 8th February 2018 8th February 2018
11 8th March 2018 - Interim meeting to discuss PIN calendared for 22nd February 2018 Meeting mislabelled as ‘Meeting No 10’
11A 23rd March 2018 22nd February 2018
12 12th April 2018 12th April 2018
13 3rd May 2018 14th June 2018
13A 16th May 2018 - Interim meeting to update and discuss proposals
14 14th June 2018 15th June 2018
15 12th July 2018 12th July 2018
16 16th August 2018 9th August 2018
17 13th September 2018 13th September 2018
18 11th October 2018 11th October 2018
19 8th November 2018 8th November 2018
20 20th December 2018 13th December 2018
21 31st January 2019 31st January 2019
22 14th February 2019 14th February 2019
23 14th March 2019 14th March 2019
24 11th April 2019 11th April 2019
25 9th May 2019 9th May 2019
26 13th June 2019 13th June 2019
27 11th July 2019 11th July 2019
28 8th August 2019 8th August 2019
29 16th September 2019 16th September 2019
30 17th October 2019 17th October 2019
31 14th November 2019 14th November 2019
32 12th December 2019 12th December 2019 Slides relating to a feasibility study attached

Full Response Text

Feasibility Study Remit Objective:- Best solution to deal with ongoing problematic silt arriving at Peel Marina, taking account of:- • Cost • Environment • Operational impact Feasibility Study Remit Options:- • Canalisation of Peel Marina • Removal / collection of contamination at source and allow silt to be deposited at sea (below Cefas Action Level 2 threshold) • Working with Cefas to develop Isle of Man specific regional “action levels” based on background geological concentrations and ecotoxicological assays. • Silt reduction (link with MUA / DEFA work on catchment management plan) • Silt traps – River Neb close to marina – Utilising the former peel brickwork quarry – Foxdale area – Divert river Neb to create natural siltation area • Disposal through Energy from Waste Plant • Installation of cut-off wall on river bank – to isolate ground contamination from historic fuel oil leak at the Peel Power Station from the River Neb Surface silt sample results Lead exceeds Cefas Action Level 2 in 60% of surface samples Average of all Lead levels exceeds Action Level 2 thresholds Zinc exceeds Cefas Action Level 2 in 10% of all samples In order to ensure maintenance dredging material can be deposited at sea in future, Lead levels must be reduced and Zinc levels examined (Data – Ecospan silt samples – Summer 2019) Surface Layer Sample Arsenic Cadmium Chromium Copper Mercury Nickel Lead Zinc 1 23.7 1.75 23.1 70.7 0.06 24.2 496 439 2 19.6 1.6 24 108 0.14 23.1 601 557 3 21.3 2.33 20.9 65.2 0.09 21.3 743 554 4 16.9 0.68 22.8 30.9 0.03 23.8 277 253 5 31.1 2.93 26.2 66.8 0.1 26.1 948 667 6 40.3 3.65 31.8 75.7 0.11 31.5 1060 797 7 12.3 1.42 33.5 56.2 0.07 32.8 206 237 8 34 3.6 28.5 72.5 0.12 27.5 1037 797 9 37.6 3.59 32.2 74.5 0.08 29.2 976 780 10 38.1 3.27 32.9 76.3 0.1 30.8 1099 751 11 17.1 1.06 18.4 31.2 <0.015 20.6 286 258 12 26.2 2.12 20.2 68.8 <0.015 23 916 640 13 18 1.36 29.1 60.6 <0.015 26.8 444 417 14 23.7 0.95 20.9 67.6 <0.015 22.5 729 512 15 17.6 0.59 34.2 30.2 <0.015 34.2 194 265 Water Quality Lead concentrations in water 1 730 micrograms / l 2 34 micrograms / l 3 118 micrograms / l 4 26 micrograms / l 5 less than 5 micrograms / l 6 Less than 5 micrograms / l 7 6 micrograms / l Highest concentrations at site 1 indicate source is Cross Vein Mine area (Data – 31/10/18 DEFA sample results) Water Quality Zinc concentrations in water 1 150 micrograms / l 2 382 micrograms / l 3 249 micrograms / l 4 155 micrograms / l 5 less than 20 micrograms / l 6 77 micrograms / l 7 32 micrograms / l Highest concentrations at site 2 indicate source is above Kerrowdhoo Stream / Upper Foxdale (Data – 31/10/18 DEFA sample results) Water Quality Zinc concentrations in water 1 125 micrograms / l 2 22 micrograms / l 3 33 micrograms / l 4 less than 20 micrograms / l 5 less than 20 micrograms / l 6 261 micrograms / l 7 240 micrograms / l Highest concentrations at site 6 and 7 indicate source is or above Kionslieau Reservoir (Data – 27/11/19 DOI sample results) Cross Vein Mine Site 1 – run off undisturbed by off- road bikes. Suspended Solids less than 10 milligrams / l Site 2 – run off disturbed by off-road bikes. Suspended Solids 288 milligrams / l Site 3 – adjacent to road and run off disturbed by off-road bikes. Suspended Solids 192 milligrams / l Lead Results Site 1 – 2,153 micrograms / l Site 2 – 10,940 micrograms / l Site 3 – 8,525 micrograms / l (Data – 15/03/18 DEFA sample results) Metal Mines Possible pathways:- • Surface runoff from waste areas • Mine water from adits & shafts • Groundwater seepage Metal Mines No precise models available to predict exact change in water quality or change to silt content in marina Monitor -> design -> implement -> monitor and evaluate (repeat as necessary) Changes take time to settle down (1-3 years) – water quality likely to deteriorate before improving Impact on silt – How to ensure it is below Cefas Action Level 2 after Spring 2021 dredging? • Remove off-road bikes & enforce • Determine sources at Cross Vein Mine & Kionslieau Reservoir? • Consider silt traps in Foxdale area to capture Lead & Zinc? • Coal Authority support? Other Actions • Monitoring shellfish and fish meat throughout the year and every year to determine natural variability both seasonally and spatially • Monitoring of sediments outside the Harbour entrance (pre and post dredging) • Assessing hydrocarbon contamination in terms of the Goram Test


Page 1 Peel Marina Project Board meeting 12.4.18

CONFIDENTIAL

Department of Infrastructure

Notes of the Peel Marina Project Board Meeting No 12 held 12th April 2018 at 1500 hours at the Sea Terminal

        Present:-

Tim Baker MHK Chairman (TB) Ann Reynolds, Director of Ports, DOI (AR) Mark Kenyon, Ports Manager, DOI (MK) Jeremy Reece, Policy & Strategy, DOI (JR) Bernard Warden, Director of Environment, Safety & Health, DEFA (BW) Tim Cowin, Head of Highways and Asset Management, DOI (TC) Personal Secretary, note taker

                  FOR ACTION
  1. Welcome and Apologies

Apologies received from:- Emma Killip, Project Manager, DOI (EK) Stephanie Gray, Head of Waste Management, DOI (SG)

  1. Preferred option to deal with silt already in Marina

JR told that the preferred option now is to look at dredging the silt, store to dewater (approx. 12 months) and then move the dry material to the Foxdale Deads. Advantage with this solution is that it would allow the dredging to take place in the January to May 2019 window, and will give DEFA the time to undertake the necessary monitoring at the Deads. TB said that the 12 month drying time is a broad brush figure as do not have to get the material to a specific dryness before moving.

JR said that in conversations with MUA and landowners the Department has intimated 12 months and the more the silt is dewatered the less risk there is of liquid being lost during transportation. Likely cost of this method is a quarter of the cost of chemical treatment, and is a simple, more cost effective method.

Regarding potential sites, JR told of having spoken to [redacted], who has indicated that he is interested to talk about the field by the power station [redacted]. JR said of being able to pump into the field, form a bund and then use the slope of the field to allow the material to drain, with water either going to the MUA stream or the river itself or back to the marina. JR stated that some of the drying process is through evaporation and therefore the material would not be covered. TB said following the recent meeting that [redacted] had the understanding of the wider good for the Peel community and was also interested if the field could end up as a place of employment for Peel, i.e. with improved road access.

JR advised that the access to the site is currently via Mill Road. Extension of the existing access road onto A27 Glenfaba Road, owned by the

Page 2 Peel Marina Project Board meeting 12.4.18

Commissioners, would require improvements to the junction with A27 – TC informed of having information on the junction but no costings. TC to review design and provide costings.

JR told of possible road issues if using the Mill Road access, with restrictions alongside the House of Manannan. BW said that the performance of the transport contractors was good last time and so it is doable.

JR outlined a second option was to continue the piping up the river and use land beyond the Brickyard quarry. The field immediately adjacent has a steep slope and there is another field (relatively flat) adjacent to the MUA Glenfaba House STW site. As this is further up the hill, it would require additional pumps. TB said if the local resident was an issue we could look at using the top part of the field only. JR confirmed of potentially having 2 feasible sites.

AR asked if planning permission would be required for both land suggestions – TB informed that the Power Station field is zoned for industrial use. Dewatering process is currently thought to only require a temporary planning permission, as it will be completed within 2 years.

Anthony Bates Partnership Lagoon report outlines possibility of using geotextile bags during dewatering process, it visual restrictions imposed by planners. There is a cost and could potentially slow the process down.

Minister Harmer has been requested to set up a meeting with the owners of the field adjacent to Glenfaba STW site. JR to chase

JR to go back to [redacted] to advise the material will fit in one field, meet the Quarry owners and Planning.

BW asked if any research has been done regarding buried cables – TC said that the MUA were looking to put pipes for the treatment works through the heritage trail and therefore plans are available.

JR said of the need to work with BW regarding approach, licensing and water testing etc. BW said that tests are being done and now have much better resource available and that the Deads is being viewed as a viable option. It was noted that the silt from the marina has an eighth of the contamination of the material already at the Deads. BW said that the material could become too dry and make handling more difficult?

Contracting Strategy: JR said of the need to look as one big contract, and that the transport from dewatering site to Deads could be the break point.
TB queried if there will be maintenance of the material stockpile required -
MK said that it depends on drying process. JR said that the fields need to be put back to their original state. TB stated that, although not currently knowing which field to use, could start to draft contract/tender. JR said of the need to decide on how we will project manage the scheme. BW advised that another piece of significant work would be the survey on the disused mines etc. JR said that a separate meeting with DEFA to map out the environmental side is required, including the full EPU team.

TC

JR

JR

Page 3 Peel Marina Project Board meeting 12.4.18

AR advised of having some material stored at Turkeylands, and if moved could release funds for leasing/storage of field. TB said of not wishing to move it to the field, but moving it to the Deads could be an option. JR said that this could be identified as a saving in the application for contingency funding.

  1. Progress update on other options

(a) Wrights Pit North – SG sent in comments to advise that the methodology for sampling has been agreed and await confirmation from contractor re dates for sampling to advise HRS. Project spec for additional Point of Ayre, CHs drafted. Site to be surveyed.

(b) Energy from Waste Plant – SG sent in comments to advise within the time constraints this will be progressed once WPN is underway.

(c) Material treatment and recycling – JR said that this is still available as an option. Draft PIN response done, however need some information from DEFA.

  1. Long Term Options

(a) & (b) Geotextile coastal protection and Peel Brickworks Quarry and Silt Traps – AR advised that the JBA report should be available before the next meeting.

(c) Glenfaba field – JR informed of being part of the discussions with MUA as to whether some material could be used to fill hole at Glenfaba site. TB said that this adds complexity.

  1. Funding & Project Management

TB said of currently not having a defined project or money. JR said of the need to write a paper to Treasury (Contingency Fund) and of the need to establish costs ahead of being set up and need to understand what funding DEFA is looking for. BW said that after the two meetings mentioned earlier we will be in a better position to identify the project and funding requirements.

JR said of the need to look at who is going to manage the project, ie internal or external/tech specialist. TB advised of requiring conversation with CEO and was concerned about any delay resulting in loss of focus and momentum. JR said that if internal will need technical input. JR informed that he would like to award contract and start on site in January 2019.

Regarding land issues, JR said that we may need to find a small space for a compound for the dredging contractor – MK/AR said of previously having a site hut in the boat park. AR advised of having 800m worth of piping – TB queried the contractor bringing their own. BW stated that if help/advice if needed the H&S team would be forthcoming.

Page 4 Peel Marina Project Board meeting 12.4.18

  1. Overall programme update

Programme to be updated.
TB noted of requiring conversations with the Quarry owners and [redacted], planning pre-application discussions and meeting with DEFA.

Referring to the procurement side, TC said of window being at the start of the year, and queried if we need to have the contractor in place early. JR said that we could put information out to those who expressed interest in the PIN. MK said of the need to wait until we have a firmer understanding of the land commitment – JR said that this would be in the next 2-3 weeks. TB asked for information to be started to be put together. It was noted that the project is now main steam dredging works. TB asked if we are going to be writing back to those who responded with an update. TB queried expression of interest phase as may get people that did not respond to the PIN. JR to talk to procurement. TB stressed that early contractor engagement is key and the more we can do in advance the better. TB said of the need for early engagement with procurement and sending an update letter to PIN responders.

JR

JR 7. Any Other Business

JR told of an individual with an interest in the subject wanting to talk through the history of Peel marina and that a useful view was that the water in the Neb comes from Glen Helen and Foxdale. BW said that the water quality of the lagoons at Rockmount showed some significant metal figures which comes from Glen Helen. One option would be to divert the river when it gets to the marina. He also mentioned university/academic research and that we should approach a university to look at.

JR queried if we should be looking for someone to focus on the long term solutions. TB said of the need to concentrate on 2019/20.

TB noted that canalisation has not gone off the agenda.

[Response truncated — full text is 385,256 characters]