Poles

Authority [[department-of-infrastructure
Date received 2025-08-18
Outcome Some information sent but part exempt
Outcome date 2025-10-16
Topic [[post-communications

Summary

A request was made for communications regarding pole installations for the 20mph rollout, resulting in the disclosure of internal emails and a stop work instruction, though some personal data was withheld under exemption.

Key Facts

  • Site works for the Douglas and Onchan 20mph Residential Zone were instructed to remain on hold from 27 July 2025 to 31 October 2025.
  • Hooped poles are being retained where existing and proposed speed limits match but removed elsewhere for consistency.
  • A complaint was raised by a House of Keys Member regarding a traffic post incorrectly placed on a pavement in Onchan that was subsequently tarmacked over.
  • The Department of Infrastructure withheld information containing personal data under Section 25(2)(b)(i) of the Act.
  • The final extents of the 20mph scheme were noted as not yet confirmed and likely to change.

Data Disclosed

  • 20mph
  • 27 July 2025
  • 31 October 2025
  • 1st November 2025
  • 29 July 2025
  • 28 August 2025
  • 03 July 2025
  • 18 August 2025
  • 15 October 2025
  • 19 pages
  • 2 documents
  • Section 25
  • Section 30
  • Section 35
  • CI-10
  • Document Log No. 100

Exemptions Cited

  • Section 25(2)(b)(i) of the Act (absolutely exempt personal information)
  • Data Protection (Application of GDPR) Order 2018 Article 5

Original Request

I seek the publication of all internal and external communications since July 1 relating to the installation of and issues raised with any poles installed for the proposed 20mph rollout.