Poles
| Authority | [[department-of-infrastructure |
| Date received | 2025-08-18 |
| Outcome | Some information sent but part exempt |
| Outcome date | 2025-10-16 |
| Topic | [[post-communications |
Summary
A request was made for communications regarding pole installations for the 20mph rollout, resulting in the disclosure of internal emails and a stop work instruction, though some personal data was withheld under exemption.
Key Facts
- Site works for the Douglas and Onchan 20mph Residential Zone were instructed to remain on hold from 27 July 2025 to 31 October 2025.
- Hooped poles are being retained where existing and proposed speed limits match but removed elsewhere for consistency.
- A complaint was raised by a House of Keys Member regarding a traffic post incorrectly placed on a pavement in Onchan that was subsequently tarmacked over.
- The Department of Infrastructure withheld information containing personal data under Section 25(2)(b)(i) of the Act.
- The final extents of the 20mph scheme were noted as not yet confirmed and likely to change.
Data Disclosed
- 20mph
- 27 July 2025
- 31 October 2025
- 1st November 2025
- 29 July 2025
- 28 August 2025
- 03 July 2025
- 18 August 2025
- 15 October 2025
- 19 pages
- 2 documents
- Section 25
- Section 30
- Section 35
- CI-10
- Document Log No. 100
Exemptions Cited
- Section 25(2)(b)(i) of the Act (absolutely exempt personal information)
- Data Protection (Application of GDPR) Order 2018 Article 5
Original Request
I seek the publication of all internal and external communications since July 1 relating to the installation of and issues raised with any poles installed for the proposed 20mph rollout.